Turkey Point Units 6 & 7 Limited Work Authorization William Maher - Director Licensing

2 The information provided in the following presentation is of a preliminary nature and is considered DRAFT

3 General Project Information

- Approximately 210 acre island area within the Turkey Point Plant Property

- Finished grade at nuclear island will be raised approximately 26 ft due to storm surge wave run up

- Estimates are for use of upwards of 10 million cubic yards of fill Turkey Point Units 6 & 7 will require extensive earthwork Site Plan

4

5 Begin Site Clearing/Preparation

- Access to island

- Dewatering / Demucking

- Reuse of site material

- Retaining Wall

- Reclaimed Water pipeline Begin Site Pre-construction

- Buildup of site

- Offices / Laydown / parking

- Equipment Barge Unloading Area work

- Infrastructure water and power Turkey Point Units 6 & 7 Project Sequencing -

Pre-construction activities Following ACOE Permits (3rd Qtr 2011)

Expected time to complete from ACOE permit to Deep Hole - 16 months

6 Turkey Point Units 6 & 7 Plant Area

7 Turkey Point Units 6 & 7 Site Plot Plan

8 Turkey Point Units 6 & 7 Excavation Plan (typical)

9 Turkey Point Units 6 & 7 Excavation Plan (typical)

10

  • Plant Construction

- Prepare nuclear island foundation surface preparation with dental concrete

- Place Lean concrete under the nuclear island

- Install mud mat under the nuclear island

- Install waterproofing under the nuclear island

- Erect safety-related concrete placement forms

- Install turbine, annex, and radwaste buildings foundations

- Install permanent reinforced concrete diaphragm wall to facilitate excavation for the nuclear island

- Site preparation and erection of the Training Building, which will house the Technical Support Center.

- Site preparation and erection of the Maintenance Shop / Office Building, which will house the Operations Support Center.

Turkey Point Units 6 & 7 - LWA would allow site work to continue Following LWA Issuance (3rd Qtr 2011)

11 Turkey Point Units 6 & 7 Site Rendering