Edwin I Hatch Nuclear Plant, Units 1 and 2 - Project Manager and Backup Reassignment
ML090920943
Person / Time
Site: Hatch, Vogtle, Farley  Southern Nuclear icon.png
Issue date: 05/04/2009
From: Melanie Wong
Plant Licensing Branch II
To: Gasser J
Southern Nuclear Operating Co
Lingam, Siva NRR/DORL 415-1564
References
Download: ML090920943 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 r~ay 4, 2009 Mr. Jeffrey T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.

P.O. Box 1295 Birmingham, AL 35201-1295

SUBJECT:

JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2, VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2, AND EDWIN I. HATCH NUCLEAR PLANT, UNIT NOS. 1 AND 2 - PRO..IECT MANAGER AND BACKUP REASSIGNMENT

Dear Mr. Gasser:

This letter is to inform you that as of May 4,2009, Ms. Donna Wright is assigned as the U.S. Nuclear Regulatory Commission's Project Manager (PM) for Edwin I. Hatch Nuclear Plant, Unit Nos. 1 and 2 (Hatch), and Vogtle Electric Generating Plant, Units 1 and 2 (Vogtle). Mr. Robert E. Martin will serve as the backup PM for Hatch and Vogtle, and will continue to serve as the PM for Joseph M. Farley Nuclear Plant, Units 1 and 2 (Farley). Ms. Wright will serve as the backup PM for Farley.

Please include Ms. Wright for Hatch and Vogtle, and Mr. Martin for Farley on your distribution to receive all licensing correspondence.

Ms. Wright may be reached at (301) 415-1864, and Mr. Martin may be reached at (301) 415-1493.

Sincerely, ,

'(~J LWut (l~

Melanie C. Wong, Chief Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-348, 50-364, 50-424, 50-425,50-321, and 50-366 cc: Distribution via ListServ

May 4,2009 Mr. Jeffrey T. Gasser Executive Vice President Southern Nuclear Operating Company, Inc.

P.O. Box 1295 Birmingham, AL 35201-1295

SUBJECT:

JOSEPH M. FARLEY NUCLEAR PLANT, UNITS 1 AND 2, VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2, AND EDWIN I. HATCH NUCLEAR PLANT, UNIT NOS. 1 AND 2 - PRO~IECT MANAGER AND BACKUP REASSIGNMENT

Dear Mr. Gasser:

This letter is to inform you that as of May 4,2009, Ms. Donna Wright is assigned as the U.S. Nuclear Regulatory Commission's Project Manager (PM) for Edwin I. Hatch Nuclear Plant, Unit Nos. 1 and 2 (Hatch), and Vogtle Electric Generating Plant, Units 1 and 2 (Vogtle). Mr. Robert E. Martin will serve as the backup PM for Hatch and Vogtle, and will continue to serve as the PM for Joseph M. Farley Nuclear Plant, Units 1 and 2 (Farley). Ms. Wright will serve as the backup PM for Farley.

Please include Ms. Wright for Hatch and Vogtle, and Mr. Martin for Farley on your distribution to receive all licensing correspondence.

Ms. Wright may be reached at(301) 415-1864, and Mr. Martin may be reached at (301) 415-1493.

Sincerely, IRA!

Melanie C. Wong, Chief Plant Licensing Branch 11-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-348, 50-364, 50-424, 50-425, 50-321, and 50-366 cc: Distribution via ListServ DISTRIBUTION:

Public RidsNrrLASRohrer Resource (hard copy)

RidsNrrPMDWright Resource (hard copy) RidsOgcRp Resource LPL2-1 RlF RidsRgn2MailCenter Resource (SShaeffer)

RidsNrrDorlLpl2-1 Resource (MWong) RidsAcrsAcnw&mMailCenter Resoruce RidsNrrDori Resource RidsNrrPMSLingam Resource (hard copy) RidsNrrPMRMartin Resource (hard copy)

LPerch, DORL ADAMS Accession No'.. ML090920943 NRR-106 OFFICE NRRlLPL2-1/PM NRRlLPL2-1/LA NRRlLPL2-1/BC NAME DWright SRohrer MWong DATE 4/22/09 4/20109 5/4109 OFFICIAL RECORD COpy