ML090720462

From kanterella
Jump to navigation Jump to search
IR 05000321-08-009, 05000366-08-009, on 07/12/2008-03/10/2009, Edwin I. Hatch, Unit 1, Other Activities
ML090720462
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 03/13/2009
From: Wert L
Division Reactor Projects II
To: Madison D
Southern Nuclear Operating Co
References
EA-09-054 IR-08-009
Download: ML090720462 (11)


See also: IR 05000321/2008009

Text

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

SAM NUNN ATLANTA FEDERAL CENTER

61 FORSYTH STREET, SW, SUITE 23T85

ATLANTA, GEORGIA 30303-8931

March 13, 2009

EA-09-054

Mr. Dennis R. Madison

Vice President

Southern Nuclear Operating Company, Inc.

11028 Hatch Parkway, North

Baxley, Georgia 31513

SUBJECT: EDWIN I. HATCH NUCLEAR PLANT, NRC INSPECTION REPORT

05000321/2008009 AND 05000366/2008009 AND PRELIMINARY WHITE

FINDING

Dear Mr. Madison:

On March 10, 2009, the Nuclear Regulatory Commission (NRC) completed an in-office

inspection of the 1B Emergency Diesel Generator (EDG) generator coupling failure which

occurred on July 12, 2008. Additional inspection activities were documented in NRC Special

Inspection Report 05000321/2008008 and 05000366/2008008, which was issued on

September 6, 2008.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

Based on the results of this inspection, a finding was identified involving the failure to identify

and correct cracks observed during routine maintenance inspections which resulted in

degradation of the 1B EDG generator coupling. Consequently, the generator coupling failed

during a routine surveillance test causing the 1B EDG to be declared inoperable on July 12,

2008. On July 16, 2008, the generator coupling was replaced and the 1B EDG returned to

service.

This finding was assessed, based on the best available information, including influential

assumptions, using the applicable Significance Determination Process (SDP) and was

preliminarily determined to be a low to moderate safety significance (White) finding. The final

resolution of this finding will convey the increment in the importance to safety by assigning the

corresponding color, i.e., White, a finding with low to moderate increased importance to safety

that may require additional NRC inspections. The dominant accident sequences involved: (1)

Loss of offsite power (LOOP) with loss of emergency power (2) a Transient induced LOOP with

failures of primary containment suppression (PCS) and high pressure coolant injection (HPCI)

(3) LOOP with loss of emergency power, reactor core isolation cooling (RCIC), and HPCI with

failure to recover offsite power and the EDGs. These events ultimately could result in the loss of

all injection due to inability to recover EDGs or offsite power leading to core damage. The

exposure period was a total of 182 days including the 4 day repair interval and the178 day

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

SNC 2

interval consisting of the individual success periods. The SDP analysis included an increase in

the EDG common cause fail to run probability due to failure of the 1B EDG. All five Hatch EDGs

were vulnerable to an increased likelihood of coupling failure because all couplings had similar

age related deterioration, environmental conditions and overall operating history. The 1B EDG

coupling experienced a catastrophic failure during voluntary testing while the other couplings

had indications of the same degradation mechanism. As such, the EDG coupling components

met the criteria for common cause treatment in the Risk Assessment of Operational Events

(RASP) Handbook Volume 1 Internal Events (Revision1.01), sections 3.4 pages 3-6. The

NRCs evaluation of the common cause within the SDP analysis recognized that the 1B EDG,

being the swing diesel for Hatch, had approximately 20% more operating hours on its coupling

than the other EDGs; however, the increased common cause probability for the other couplings

was still considered to be applicable for environmental, age and other considerations. The SDP

analysis is included as Enclosure 2.

The finding is also an Apparent Violation (AV) of 10 CFR 50 Appendix B Criterion XVI,

Corrective Action, for failure to identify and correct a condition adverse to quality and is being

considered for escalated enforcement in accordance with the Enforcement Policy. In addition,

this finding is considered to have a cross-cutting aspect related to the identification of issues

P.1(a), as described in the corrective action program component of the problem identification

and resolution cross-cutting area. Accordingly, for administrative purposes, Unresolved Item

05000321, 366/2008008-01 is considered closed. The current Enforcement Policy is included

on the NRCs website at http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html.

In accordance with Inspection Manual Chapter (IMC) 0609, we intend to complete our evaluation

using the best available information and issue our final determination of safety significance

within 90 days of the date of this letter. The SDP encourages an open dialogue between the

staff and the licensee; however, the dialogue should not impact the timeliness of the staffs final

determination. Before we make a final decision on this matter, we are providing you an

opportunity to: (1) present to the NRC your perspectives on the facts and assumptions used by

the NRC to arrive at the finding and its significance at a Regulatory Conference or (2) submit

your position on the finding to the NRC in writing. If you request a Regulatory Conference, it

should be held within approximately 30 days of the receipt of this letter and we encourage you to

submit supporting documentation at least one week prior to the conference in an effort to make

the conference more efficient and effective. If a Regulatory Conference is held, it will be open

for public observation. The NRC will also issue a press release to announce the conference. If

you decide to submit only a written response, such a submittal should be sent to the NRC within

30 days of the receipt of this letter.

Please contact Mr. Scott Shaeffer at (404) 562-4521 within 10 business days of the date of your

receipt of this letter to notify the NRC of your intentions. If we have not heard from you within 10

business days, we will continue with our significance determination and enforcement decision

and you will be advised by separate correspondence of the results of our deliberations on this

matter.

Since the NRC has not made a final determination in this matter, no Notice of Violation is being

issued for this inspection finding at this time. In addition, please be advised that the number and

characterization of the apparent violation may change as a result of further NRC review.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

SNC 3

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and

enclosure 1 will be made available electronically for public inspection in the NRC Public

Document Room or from the NRC=s document system (ADAMS), accessible from the NRC Web

site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RTM RA for/

Leonard D. Wert, Jr., Director

Division of Reactor Projects

Docket Nos.: 50-321, 50-366

License Nos.: DRP-57, NPF-5

Enclosures: 1. NRC Inspection Report 05000321/2008009 and 05000366/2008009

2. SDP Phase 3 Summary (OFFICIAL USE ONLY - PROPRIETARY

INFORMATION)

cc w/encl.: (See page 4)

cc w/o encl. 2: (See page 4)

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

_________________________ X SUNSI REVIEW COMPLETE /SMS/

OFFICE RII:DRP RII:DRP RII:EICS RII:DRP RII:DRP RII:EICS RII:DRS

SIGNATURE JAH /via email/ TXL /RA/ SMS /RA/ JTM /RA/ CFE /via email/ GMD /via email/

NAME JHickey TLighty SSparks SShaeffer JMunday CEvans GMcDonald

DATE 03/10/2009 03/10/2009 03/11/2009 03/13/2009 03/11/2009 03/10/2009

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

SNC 4

cc w/encl:

Jeffrey T. Gasser Cynthia Sanders

Executive Vice President Program Manager

Southern Nuclear Operating Company, Inc. Radioactive Materials Program

P.O. Box 1295 Department of Natural Resources

Birmingham, AL 35201-1295 4220 International Parkway

Suite 110

L. Mike Stinson Atlanta, GA 30354

Vice President

Fleet Operations Support Reece McAlister

Southern Nuclear Operating Company, Inc. Executive Secretary

P.O. Box 1295 Public Service Commission

Birmingham, AL 35201-1295 244 Washington Street, SW

Atlanta, GA 30334

David H. Jones

Vice President Chairman

Engineering Appling County Commissioners

Southern Nuclear Operating Company, Inc. County Courthouse

P.O. Box 1295 69 Tippins Street, Suite 201

Birmingham, AL 35201-1295 Baxley, GA 31513

Moanica Caston Mr. K. Rosanski

Vice President and General Counsel Resident Manager

Southern Nuclear Operating Company, Inc. Oglethorpe Power Corporation

Bin B-022 Hatch Nuclear Plant

P.O. Box 1295 P.O. Box 2010

Birmingham, AL 35201-1295 Baxley, GA 31515

cc w/o encl: Senior Engineer

Laurence Bergen Power Supply

Oglethorpe Power Corporation Municipal Electric Authority of Georgia

2100 East Exchange Place 1470 Riveredge Parkway NW

P.O. Box 1349 Atlanta, GA 30328-4684

Tucker, GA 30085-1349

Arthur H. Domby, Esq.

Troutman Sanders

Nations Bank Plaza

600 Peachtree Street, NE, Suite 5200

Atlanta, GA 30308-2216

Dr. Carol Couch

Director

Environmental Protection

Department of Natural Resources

2 Martin Luther King Drive, S.E.

Suite 1152 East Tower

Atlanta, GA 30334

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

SNC 5

Letter to Mr. Dennis Madison from Leonard D. Wert, Jr. dated March 13, 2009

SUBJECT: EDWIN I. HATCH NUCLEAR PLANT, NRC INSPECTION REPORT

05000321/2008009 AND 05000366/2008009 AND PRELIMINARY WHITE

FINDING

Distribution w/encl:

C. Evans, RII

L. Slack, RII EICS

OE Mail

RIDSNRRDIRS

PUBLIC

R. Martin, NRR

D. Wright, NRR

B. Westreich, NSIR (hard copy w/encl)

E. McNiel, NSIR (hard copy w/encl)

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket No.: 05000321, 05000366

License No.: DPR-57 and NPF-5

Report No.: 05000321/2008009 and 05000366/2008009

Licensee: Southern Nuclear Operating Company, Inc.

Facility: Edwin I. Hatch Nuclear Plant

Location: Baxley, GA

Dates: July 12, 2008 - March 10, 2009

Inspectors: J. Hickey, Senior Resident Inspector (Section 4OA5, 4OA6)

P. Niebaum, Resident Inspector (Section 4OA5, 4OA6)

G. MacDonald, Senior Reactor Analyst (Section 4OA5)

T. Lighty, Project Engineer (Section 4OA5)

Approved by: Scott M. Shaeffer, Chief

Reactor Projects Branch 2

Division of Reactor Projects

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

Enclosure 1

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

SUMMARY OF FINDINGS

IR 05000321,366/2008-009; 7/12/2008-3/10/2009; Edwin I. Hatch Nuclear Plant; Unit 1; Other

Activities.

The report transmits the results of the NRCs preliminary assessment of the 1B Emergency

Diesel Generator coupling failure. One Apparent Violation with potentially low to moderate

safety significance (White) was identified. The significance of most findings is indicated by its

color (Green, White, Yellow, or Red) using Inspection Manual Chapter (IMC) 0609, ASignificance

Determination Process@ (SDP). Findings for which the SDP does not apply may be Green or

assigned a severity level after management review. The NRC's program for overseeing the safe

operation of commercial nuclear power reactors is described in NUREG-1649, AReactor

Oversight Process.

Cornerstone: Mitigating Systems

C TBD. A self-revealing apparent violation of 10 CFR 50, Appendix B, Criterion XVI,

Corrective Action, was identified for failure to promptly identify and correct a condition

adverse to quality. Since 1988, the licensee had observed cracks in the glands of the EDG

couplings, but did not identify the cracking was an indication of coupling degradation.

Therefore, no condition report was written to identify and correct the condition adverse to

quality. Consequently, the 1B coupling developed higher than normal vibration on July 12,

2008, during a routine surveillance which prompted the licensee to declare the 1B EDG

inoperable.

The failure to promptly identify and correct a condition adverse to quality for the

observed degraded condition of the 1B EDG coupling is a performance deficiency.

This finding is more than minor because it was associated with the Equipment

Performance attribute of the Mitigating Systems cornerstone and adversely affected

the objective in that there was no reasonable assurance the 1B EDG could meet its

mission time. This finding was assessed using the applicable SDP and preliminarily

determined to White because there was a calculated risk increase over the base

case between 1E-5 and 1E-6. The dominant sequences included (1) LOOP with

loss of emergency power (SBO), success of RCIC, successful depressurization,

failure to recover offsite power and the EDGs within 5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />, and failure of firewater

injection due to repressurization caused by inability to operate SRVs without DC

power (2) a Transient induced LOOP with failures of PCS and HPCI, successful

depressurization and failure of all injection due to inability to recover EDGs or offsite

power and (3) LOOP with loss of emergency power, RCIC, and HPCI with failure to

recover offsite power and the EDGs. The HPCI system is failed in the model with

loss of room cooling due to SBO. The exposure period was a total of 182 days

including the 4 day repair interval and the 178 day interval consisting of the

individual success periods.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

Enclosure 1

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

REPORT DETAILS

4. OTHER ACTIVITIES

4OA5 Other

(Opened) Apparent Violation (AV) 05000321,366/2008009-001, 1B EDG Coupling Failure

a. Inspection Scope

The inspectors conducted a review and significance evaluation of the failure of the 1B

EDG coupling.

b. Findings

Introduction. A self-revealing apparent violation of 10 CFR 50, Appendix B, Criterion

XVI, Corrective Action, was identified for failure to promptly identify and correct a

condition adverse to quality. Since 1988, the licensee had observed cracks in the glands

of the EDG couplings, but did not identify the cracking was an indication of coupling

degradation. Therefore, no condition report was written to identify and correct the

condition adverse to quality. Consequently, the 1B coupling developed higher than

normal vibration due to coupling degradation on July 12, 2008, during a routine

surveillance which prompted the licensee to declare the 1B EDG inoperable.

Description. On July 12, 2008, the 1B EDG was manually shutdown due to excessive

vibration and declared inoperable. As part of the troubleshooting effort, vibration

monitoring equipment was installed for an unloaded maintenance run of the 1B EDG on

July 14, 2008. This run was stopped after approximately 45 minutes due engine block

vibration levels exceeding an operational limit recently supplied by the EDG vendor.

Post-event inspections by the licensee identified several cracks of the rubber gland on

both the diesel engine flywheel side and the generator side of the coupling. It was later

determined that the cause of the excessive vibration was the age-related cracks in the

rubber gland of the EDG coupling. Subsequent to the 1B EDG coupling vibration issues,

the licensee replaced all five EDG couplings. During the root cause analysis, the

licensee determined that cracks on the 2C EDG coupling had been observed as early as

1988 and similar cracks had been seen on the other EDG couplings. However, these

conditions were not documented during routine maintenance inspections and no

condition report was written to identify this condition adverse to quality. As the condition

was not identified, corrective actions were not taken to address the degraded conditions.

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

Enclosure 1

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

4

In November 2008, the licensee completed voluntary offsite testing on the 1B EDG

coupling to determine if the 1B EDG could meet the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> mission time. The coupling

catastrophically failed about 30 minutes into a fully loaded 2-hour test run. This indicated

that the 1B EDG would not have met its mission time. The failure mechanism was

determined to be age related deterioration of the coupling combined with running the 1B

EDG in its fully loaded condition. This resulted in high stress on the EDG couplings.

However, start-up torque conditions could also have contributed to coupling deterioration.

The 1B EDG had 20% more run time than the other EDGs (approximately 2754 hours0.0319 days <br />0.765 hours <br />0.00455 weeks <br />0.00105 months <br /> vs.

2200 hours0.0255 days <br />0.611 hours <br />0.00364 weeks <br />8.371e-4 months <br />). Therefore, the 1B EDG coupling was considered to be the bounding case

for all the EDGs with regards to run hours. The 1C EDG coupling did not fail during the

full load offsite testing and all other EDG couplings did not exhibit any operational

problems prior to replacement in 2008. However, the EDG couplings had several strong

factors which support common cause treatment including common hardware,

maintenance program, environment, equipment age, operating hours and similar

degradation.

Analysis. The failure to identify and correct a condition adverse to quality for the

observed degraded condition of the 1B EDG coupling is a performance deficiency. This

finding is more than minor because it was associated with the Equipment Performance

attribute of the Mitigating Systems cornerstone and adversely affected the objective in

that there was no reasonable assurance the 1B EDG could meet its mission time. This

finding was assessed using the applicable SDP and preliminarily determined to White

because there was a calculated risk increase over the base case between 1E-5 and 1E-

6. The analysis included an increase in the emergency diesel generator (EDG) common

cause fail to run probability due to all five Hatch EDGs being vulnerable to an increased

likelihood of coupling failure due to degraded couplings. All couplings had similar age

and operating history and one EDG coupling suffered a catastrophic failure while the

other couplings had indications of the same degradation mechanism which meets the

criteria for common cause treatment in the Risk Assessment of Operational Events

(RASP) Handbook Volume 1 Internal Events, sections 3.4 page 3-6. The dominant

sequences included (1) LOOP with loss of emergency power (SBO), success of RCIC,

successful depressurization, failure to recover offsite power and the EDGs within 5

hours, and failure of firewater injection due to repressurization caused by inability to

operate SRVs without DC power (2) a Transient induced LOOP with failures of PCS and

HPCI, successful depressurization and failure of all injection due to inability to recover

EDGs or offsite power and (3) LOOP with loss of emergency power, RCIC, and HPCI

with failure to recover offsite power and the EDGs. The HPCI system is failed in the

model with loss of room cooling due to SBO. The exposure period was the 178 day

interval consisting of the individual success periods and a 4 day repair interval for a total

of 182 days.

Enforcement. 10 CFR 50, Appendix B, Criterion XVI, Corrective Action, states in part

that measures shall be established to assure that conditions adverse to quality are

promptly identified and corrected. Contrary to the above, the licensee failed to promptly

identify and correct a condition adverse to quality. Since 1988, the licensee had

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

Enclosure 1

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

5

observed cracks in the EDG couplings, but did not identify the cracking as an indication

of coupling degradation. The licensee did not document the conditions during routine

maintenance inspections and no condition report was written to identify and correct this

condition adverse to quality. Consequently, the 1B coupling developed higher than

normal vibration on July 12, 2008, during a routine surveillance which prompted the

licensee to declare the 1B EDG inoperable. In addition, this finding is considered to have

a cross-cutting aspect related to the identification of issues P.1(a), as described in the

corrective action program component of the problem identification and resolution cross-

cutting area. Specifically, that the licensee identifies issues completely, accurately, and

in a timely manner commensurate with their safety significance. URI 05000321,

366/2008008-01, which was opened during the special inspection is considered closed.

Pending final significance determination, this finding is identified as Apparent Violation

(AV) 05000321,366/2008009-01, 1B EDG Coupling Failure.

4OA6 Meetings, Including Exit

On March 10, 2009, the NRC presented the inspection results to Mr. Dennis Madison

who acknowledged the findings.

ATTACHMENT: SUPPLEMENTAL INFORMATION

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

Enclosure 1

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

SUPPLEMENTAL INFORMATION

LIST OF REPORT ITEMS

Opened

05000321, 366/2008009-01 AV 1B EDG Coupling Failure (Section 4OA5)

Closed

05000321, 366/2008008-01 URI Review of EDG Coupling Root Cause Evaluation (Section

4OA5.3).

OFFICIAL USE ONLY - PROPRIETARY INFORMATION

Enclosure 1