Letter Sequence Response to RAI |
|---|
|
|
MONTHYEARML0818203482008-06-25025 June 2008 License Amendment Request - Revision to Technical Specification 4.3.1.1.a Concerning k-infinity Project stage: Request ML0821105162008-10-10010 October 2008 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0821105032008-10-10010 October 2008 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0831908402008-11-0606 November 2008 Response to Request for Additional Information - Revision to Technical Specification 4.3.1.1.a Concerning K-Infinity Project stage: Response to RAI ML0833702792008-12-29029 December 2008 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0821204862009-01-21021 January 2009 License Amendment Request to Revise Technical Specification 4.3.1.1.A Concerning K-Infinity Project stage: Other ML0906908042009-03-0909 March 2009 Exelons Response to Request for Additional Information - Revision to Technical Specification 4.3.1.1.a Concerning K-Infinity Project stage: Response to RAI ML0909107332009-05-13013 May 2009 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0909901262009-05-13013 May 2009 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0917404462009-06-12012 June 2009 Response to Request for Additional Information - Revision to Technical Specification 4.3.1.1a Concerning K-infinity Project stage: Response to RAI ML0918108912009-07-14014 July 2009 Summary of Meeting with Exelon to Discuss Management of Boraflex Degradation at Peach Bottom Units 2 and 3, and the Associated License Amendment Request Under Review to Revise the Technical Specifications for the Spent Fuel Pool. Project stage: Meeting ML0924607132009-09-16016 September 2009 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0924704772009-09-16016 September 2009 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML0935214352009-12-18018 December 2009 Revised Criticality Analysis - Revision to Technical Specification 4.3.1.1.a Concerning K-infinity Project stage: Other ML1006102902010-03-0404 March 2010 Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 4.3.1.1.A Concerning K-Infinity Project stage: RAI ML1009100752010-03-26026 March 2010 Response to Request for Additional Information - Revision to Technical Specification 4.3.1.1.a Concerning k-infinity Project stage: Response to RAI ML1009205372010-04-20020 April 2010 FRN: General Notice. Notice of Consideration of Issuance of Amendment to Facility Operating License for Peach Bottom Atomic Power Station, Units 2 & 3 Opportunity for a Hearing, and Order Imposing Procedures for Access to Sensitive Unclassi Project stage: Request ML1009205262010-04-21021 April 2010 Individual Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for Hearing, and Order Imposing Procedures for Access to Sensitive Unclassified Non-Safeguards I Project stage: Other ML1016903772010-06-18018 June 2010 License Amendment Request - Revision to Technical Specification 4.3.1.1.a Concerning K-Infinity Project stage: Request ML1016200312010-06-24024 June 2010 Fr Notice--Peach Bottom, Units 2 and 3 - Withdrawal of an Amendment Request Project stage: Withdrawal ML1016007242010-06-24024 June 2010 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML1016200172010-06-24024 June 2010 Withdrawal of an Amendment Request Project stage: Withdrawal NRC-2010-0160, Fr Notice--Peach Bottom, Units 2 and 3 - Withdrawal of an Amendment Request2010-06-24024 June 2010 Fr Notice--Peach Bottom, Units 2 and 3 - Withdrawal of an Amendment Request Project stage: Withdrawal ML1016007022010-06-25025 June 2010 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML1033506182010-12-13013 December 2010 Summary of Meeting with Exelon to Discuss Proprietary Information Related to a Request for Additional Information Associated with a License Amendment Request Under Review to Revise the Technical Specifications for the Spent Fuel Pool K-I Project stage: RAI ML1033505502010-12-13013 December 2010 Summary of January 7, 2010, Meeting with Exelon to Discuss Proprietary Information Related to a License Amendment Request Under Review to Revise the Technical Specifications for the Spent Fuel Pool K- Infinity Value Project stage: Meeting 2009-07-14
[Table View] |
Text
10 CFR 50.90 March 9, 2009 U. S. Nuclear Regulatory Commission Attn: Document Control Desk 11555 Rockville Pike Rockville, MD 20852 Enclosed is Exelon's Response to Request for Additional Information - Revision to Technical Specification 4.3.1.1.a Concerning k-infinity Questions concerning this submittal may be directed to:
Exelon Nuclear Attn: Thomas Loomis, (610) 765-5510 e-Mail: thomas.loomis@exeloncorp.com 200 Exelon Way Kennett Square, PA 19348 cc:
S. J. Collins, Regional Administrator, Region I, USNRC F. L. Bower, USNRC Senior Resident Inspector, PBAPS J. D. Hughey, Project Manager [PBAPS] USNRC R. R. Janati, Commonwealth of Pennsylvania S. T. Gray, State of Maryland Document Components:
001 Exelon Transmittal Letter, pdf 190,194 bytes 002 Exelon Response to RAI, pdf 5,031,962 bytes 003 Attachments 4, 5 and 6, pdf 5,766,933 bytes, Proprietary