VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 February 9, 2009 U. S. Nuclear Regulatory Commission Serial No.09-088 Attention: Document Control Desk NAPS/MPW RO One White Flint North Docket No.

50-338 11555 Rockville Pike 50-339 Rockville, MD 20852-2738 License No.

NPF-4 NPF-7 VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)

NORTH ANNA POWER STATION UNITS 1 AND 2 SETTLEMENT MONITORING PROCEDURE REVISION Enclosed is a summary of changes to North Anna Power Station Settlement Monitoring Procedure 0-PT-1 15. This information is being transmitted for your review pursuant to Atomic Safety and Licensing Appeal Board Decision ALAB-578 dated February 11, 1980.

Please contact Mr. Michael Whalen at (540) 894-2572 if you have any questions or require additional information.

Sincerely, Eric S. Hendrixson Director - Nuclear Station Safety and Licensing Commitments made in this letter: None Attachment

Serial No.09-088 Docket No. 50-338/339 Page 2 of 3 cc:

U. S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, S.W., Suite 23T85 Atlanta, GA 30303-8931 U. S. Nuclear Regulatory Commission Director - Office of Nuclear Reactor Regulation (Mailstop 13D1 3)

One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector North Anna Power Station

Serial No.09-088 Docket No. 50-338/339 Page 3 of 3 Summary of Settlement Monitorinq Procedure Revision The following items were revised in periodic test procedure 0-PT-1 15, Survey of Settlement Monitoring Points, approved February 4, 2009:

1. Test procedure references for Reference Monument "K" were removed from the test procedure.

Reference Monument "K" is located outside of the station Protective Area adjacent to the west end security gate.

Reference Monument "K" was originally installed to provide a turning point for survey loop closure.

It has been determined that any solid surface near the west end security will provide the same function.

The monument is being removed as a result of site preparation work associated with the proposed North Anna Unit 3. Loop closure is validated using the current Reference Monument "J".

2. The Kern centering heads have been removed from Reference Monuments "A" and "B" to eliminate a human performance concern when performing the surveys. The reference monument illustration, an attachment to the test procedure, has been revised to no longer depict the Kern centering heads. Only Reference Monuments "A" and "B" had Kern centering heads.

The procedure change does not impact the design, function, ability to function, method of performing the function, or control or operation of a system, structure or component.