Serial No.
NL&OS/ETS Docket Nos.
License Nos.
VIRGINIA ELECTRIC AND POWER COMPANY RICHMOND, VIRGINIA 23261 January 8, 2009 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555 08-0782 RO 50-338/339 NPF-4/7 VIRGINIA ELECTRIC AND POWER COMPANY (DOMINION)
NORTH ANNA POWER STATION UNITS 1 AND 2 ONE-TIME RISK-INFORMED EXTENSION TO THE COMPLETION TIME FOR EDG FUEL OIL STORAGE TANK RECOATING - REVISION TO THE TECHNICAL SPECIFICATIONS BASES By letter dated December 17, 2007 (Serial No. 07-0803), Dominion requested license amendments to permit a one-time extended 14-day completion time for each of the two underground diesel fuel oil storage tanks to permit removal of the current coating and recoating of the tanks in preparation for use of ultra-low sulfur diesel fuel oil. Associated TS Bases changes were also provided for information.
Subsequent to the submittal of the license amendment request (LAR), the NRC technical review staff noted that the Bases revision included in the LAR incorporated the discussion associated with the new TS Action A.4 Completion Time Note into the APPLICABILITY section of the TS 3.8.3 Bases. This discussion should have been incorporated into the ACTIONS section of the Bases.
Therefore, following NRC approval of the LAR, but prior to implementation of the license amendments, Dominion will revise the North Anna Units 1 and 2 TS B 3.8.3 Bases to relocate the discussion associated with the new TS Action A.4 Completion Time Note from the APPLICABILITY section to the ACTIONS section.
If you have any questions regarding this submittal, please contact Mr. E. Thomas Shaub at (804) 273-2763.
Sincerely, J. AI n Price President - Nuclear Engineering Commitment made in this letter:
- 1. Following NRC approval of the LAR, but prior to implementation of the license amendment, Dominion will revise the North Anna Units 1 and 2 TS B 3.8.3 Bases to relocate the discussion associated with the new TS Action A.4 Completion Time Note from the APPLICABILITY section to the ACTIONS section.
cc:
U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW Suite 23T85 Atlanta, Georgia 30303 NRC Senior Resident Inspector North Anna Power Station Mr. J. F. Stang, Jr.
NRC Project Manager U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 0-8G9A 11555 Rockville Pike Rockville, Maryland 20852 Ms. D. N. Wright NRC Project Manager U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 0-8H4A 11555 Rockville Pike Rockvilie, Maryland 20852 Serial Number 08-0782 Docket Nos. 50-338/339 Page 2 of 2