December 9, 2008 Mr. Alexander Marion, Executive Director Nuclear Operations & Engineering Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708
SUBJECT:
DRAFT REVISION OF DIGITAL INSTRUMENTATION AND CONTROL PROJECT PLAN FOR REVIEW AND COMMENT
Dear Mr. Marion:
The purpose of this letter is to provide you with the draft revision of the U.S. Nuclear Regulatory Commissions (NRCs) Digital Instrumentation and Control (DI&C) Project Plan (Enclosure 1) for review and comment.
The DI&C Project Plan was initially issued on July 12, 2007 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML071900253) and was revised on March 14, 2008 (ML080220448).
This draft revision of the project plan will be discussed at the next public meeting of the NRCs DI&C Steering Committee on December 11, 2008. The Steering Committee looks forward to receiving any comments you may have as it considers final changes to the draft. We expect to issue the project plan early in March.
If you have any questions, please contact Stewart Bailey at 301-415-1321.
Sincerely,
/RA/
Patrick Hiland, Director Division of Engineering Office of Nuclear Reactor Regulation
Enclosure:
As stated cc w/enclosure: See next page
December 9, 2008 Mr. Alexander Marion, Executive Director Nuclear Operations & Engineering Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708
SUBJECT:
DRAFT REVISION OF DIGITAL INSTRUMENTATION AND CONTROL PROJECT PLAN FOR REVIEW AND COMMENT
Dear Mr. Marion:
The purpose of this letter is to provide you with the draft revision of the U.S. Nuclear Regulatory Commissions (NRCs) Digital Instrumentation and Control (DI&C) Project Plan (Enclosure 1) for review and comment.
The DI&C Project Plan was initially issued on July 12, 2007 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML071900253) and was revised on March 14, 2008 (ML080220448).
This draft revision of the project plan will be discussed at the next public meeting of the NRCs DI&C Steering Committee on December 11, 2008. The Steering Committee looks forward to receiving any comments you may have as it considers final changes to the draft. We expect to issue the project plan early in March.
If you have any questions, please contact Stewart Bailey at 301-415-1321.
Sincerely,
/RA/
Patrick Hiland, Director Division of Engineering Office of Nuclear Reactor Regulation
Enclosure:
As stated cc w/enclosure: See next page ADAMS ACCESSION NOS.:
Package: ML083440345 Letter: ML083440209
- ML083440221 OFFICE DI&C/DD NRR/DE NAME SBailey PHiland DATE 12 / 09 / 2008 12 / 09 / 2008 OFFICIAL FILE COPY
ENCLOSURE LETTER TO NEI: DRAFT REVISION OF DIGITAL INSTRUMENTATION AND CONTROL PROJECT PLAN FOR REVIEW AND COMMENT DISTRIBUTION Email PUBLIC RidsNrrAdro RidsNrrAdes RidsNrrDpr RidsNrrDprPgcb RidsOpaMail RidsNrrDe RidsOgcMailCenter RidsAcrsAcnwMailCenter JGrobe MMayfield MBailey SMorris MCase SBailey MGareri IJung RSchaaf WKemper MJunge PSilva SBurla DSantos SArndt DHerrmann PHiland DRahn External Email See Next Page Nuclear Energy Institute Project No. 689 cc:
Mr. Alexander Marion, Executive Director of Nuclear Operations Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 am@nei.org Mr. James Riley, Director of Engineering Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 jhr@nei.org Mr. Gordon Clefton, Senior Project Manager Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708\\
gac@nei.org Mitch Lucas, (TXU) mlucas3@luminant.com Rick Libra, (DTE)
Rick.Libra@exeloncorp.com Amir Shahkarami, (Exelon)
Amir.Shahkarami@exeloncorp.com Chuck Welty, (EPRI) cwelty@epri.com