E-mail from Brett Rini, NRC to Alex Marion, NEI Transmitting Information on Control Rod Cracking Found at Swedish BWRs
ML083330170
Person / Time
Issue date: 11/26/2008
From: Brett Rini
NRC/NRR/DIRS/IOEB
To: Marion A
Nuclear Energy Institute
Brett Rini, NRR/DIRS/IOEB, 301-415-3931
Shared Package
ML083330227 List:
References
Download: ML083330170 (2)


Text

From:

Brett Rini Sent:

Wednesday, November 26, 2008 9:06 AM To:

'am@nei.org' Cc:

Jack Grobe; Bruce Boger; Jim Wiggins; Frederick Brown; Michael Cheok; Leslie Fields; John Thorp; Eric Thomas

Subject:

Information on Control Rod Cracking Found at Swedish BWRs Attachments:

Swedish Control Rod Cracking Public Info.doc Mr. Marion, Per your November 14 request to Jack Grobe, NRR Associate Director for Engineering and Safety Systems, we are providing the attached information regarding the control rod cracking experienced at two Swedish Boiling Water Reactors (BWRs). The information was obtained from various public sources, some of which were translated from Swedish. In addition, there was some information in recent editions of Nucleonics Week. The dates and pages for those articles are provided in the attached. Some of the information in the attached has changed from when it was originally reported (e.g., the plants will be shut down longer than originally thought).

Please share with us any additional information that you are able to obtain from INPO, WANO, EPRI, or others regarding this event. We are working to determine the applicability of this issue to the US plants.

Thank you, Brett Rini Brett A. Rini Reactor Systems Analyst M/S O-12G13 U.S. Nuclear Regulatory Commission Washington, DC 20555 301-415-3931 Brett.Rini@nrc.gov From: MARION, Alex [1]

Sent: Friday, November 14, 2008 7:55 AM To: Jack Grobe

Subject:

Forsmark FORSMARK MANAGEMENT SAID IT WILL TRY TO USE CONTROL RODS FROM THE CLOSED BARSEBAECK nuclear power plant to replace rods with broken and cracked shafts in Forsmark-3. About 25% of the Swedish unit's 197 rods are cracked and at least one is broken. In a November 13 statement, Forsmark management said it wants to use the Barsebaeck rods because it would be difficult to quickly order and install so many new rods. Forsmark-3, an Asea BWR, went online in 1985.

Barsebaeck-1 and -2 are an earlier generation of the Asea BWR and were

permanently shut in 1999 and 2004, respectively, when Sweden was still planning early phase-out of nuclear power. All three reactors are majority owned by Vattenfall.

Do you have any additional info on this??

Alex Marion Executive Director, Nuclear Operations Nuclear Energy Institute 1776 I St. N.W., Suite 400 Washington, DC 20006 www.nei.org P: 202.739.8080 F: 202.533.0164 M: 202.439.3224 E: am@nei.org nuclear. clean air energy.

E-mail Properties Mail Envelope Properties (499C2FC6BB962446994CA8682D8ADF331179C5E1D8)

Subject:

Information on Control Rod Cracking Found at Swedish BWRs Sent Date: 11/28/2008 11:20:23 AM Received Date: 11/26/2008 9:05:00 AM From: Brett Rini Created By: Brett.Rini@nrc.gov Recipients:

am@nei.org ('am@nei.org')

Tracking Status: None Jack.Grobe@nrc.gov (Jack Grobe)

Tracking Status: None Bruce.Boger@nrc.gov (Bruce Boger)

Tracking Status: None Jim.Wiggins@nrc.gov (Jim Wiggins)

Tracking Status: None Frederick.Brown@nrc.gov (Frederick Brown)

Tracking Status: None Michael.Cheok@nrc.gov (Michael Cheok)

Tracking Status: None Leslie.Fields@nrc.gov (Leslie Fields)

Tracking Status: None John.Thorp@nrc.gov (John Thorp)

Tracking Status: None Eric.Thomas@nrc.gov (Eric Thomas)

Tracking Status: None Post Office:

HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 57487 11/28/2008 Swedish Control Rod Cracking Public Info.doc 46586 Options Expiration Date: