UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 November 24, 2008 EA-08-046 Mr. Charles G. Pardee Chief Nuclear Officer and Senior Vice President Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
BYRON STATION, UNITS 1 AND 2 - NOTIFICATION OF NRC INSPECTION AND REQUEST FOR INFORMATION
Dear Mr. Pardee:
By a letter dated April 1, 2008, the NRC communicated to you the final significance determination for a finding having low to moderate safety significance (White) at your Byron Nuclear Power Station. The finding involved the failure to take timely corrective actions after the identification of extensive corrosion on essential service water system riser pipes and the failure to verify the adequacy of the methodology and design inputs in calculations that supported your staffs decision to accept three degraded essential service water system riser pipes for continued service.
In September 2008, we were notified by your staff that applicable corrective actions for that finding had either been completed or initiated, and that you were ready for the NRC to conduct our supplemental inspection to review the actions taken to address the White finding.
Accordingly, we plan to conduct a supplemental inspection, beginning on January 20, 2009, at Byron Station using Inspection Procedure 95001, Inspection for One or Two White Inputs in a Strategic Performance Area. This on-site inspection is scheduled to be performed January 20 through January 23, 2009. In order to minimize the impact to your on-site resources and to ensure a productive inspection for both organizations, we have enclosed a request for documents needed for this inspection. The documents identified are those that the inspectors will need prior to and upon arrival at the site. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the on-site portion of the inspection.
We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Ms. Tracey Hulbert of your organization. If there are any questions about this inspection or the material requested, please contact the inspection team leader, Mr. Brian Kemker at (217) 935-9521.
C. Pardee In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Richard A. Skokowski, Chief Branch 3 Division of Reactor Projects Docket Nos. 50-454; 50-455 License Nos. NPF-37; NPF-66
Enclosure:
Supplemental Inspection Document Request cc w/encl:
Site Vice President - Byron Station Plant Manager - Byron Station Regulatory Assurance Manager - Byron Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Braidwood, Byron, and LaSalle Associate General Counsel Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency J. Klinger, State Liaison Officer, Illinois Emergency Management Agency P. Schmidt, State Liaison Officer, State of Wisconsin Chairman, Illinois Commerce Commission B. Quigley, Byron Station
C. Pardee In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely, Richard A. Skokowski, Chief Branch 3 Division of Reactor Projects Docket Nos. 50-454; 50-455 License Nos. NPF-37; NPF-66
Enclosure:
Supplemental Inspection Document Request cc w/encl:
Site Vice President - Byron Station Plant Manager - Byron Station Regulatory Assurance Manager - Byron Station Chief Operating Officer and Senior Vice President Senior Vice President - Midwest Operations Senior Vice President - Operations Support Vice President - Licensing and Regulatory Affairs Director - Licensing and Regulatory Affairs Manager Licensing - Braidwood, Byron, and LaSalle Associate General Counsel Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency J. Klinger, State Liaison Officer, Illinois Emergency Management Agency P. Schmidt, State Liaison Officer, State of Wisconsin Chairman, Illinois Commerce Commission B. Quigley, Byron Station DOCUMENT: G:\\Byron\\BYR 95001 Letter.doc Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE ClinRIO E RIII NAME BKemke*RAS for via emailr RSkokowski DATE 11/24/08 11/24/08 OFFICIAL RECORD COPY
Letter to C. Pardee from R. Skokowski dated November 24, 2008 DISTRIBUTION:
Tamara Bloomer RidsNrrDorlLpl3-2 RidsNrrPMByron Resource RidsNrrDirsIrib Resource Mark Satorius Kenneth OBrien Jared Heck Allan Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak
Enclosure SUPPLEMENTAL INSPECTION DOCUMENT REQUEST Inspection Dates:
January 20 - 24, 2009 Inspection Procedure:
IP 95001, Supplemental Inspection Inspectors:
Brian Kemker, Team Leader U. S. Nuclear Regulatory Commission ATTN: Resident Office - Byron 4448 German Church Byron, IL 61010-9750 Brian.Kemker@nrc.gov John Jacobson U. S. Nuclear Regulatory Commission Region III - Division of Reactor Safety 2443 Warrenville Road, Suite 210 Lisle, Il 60532-4352 John.Jacobson@nrc.gov Information Requested Two Weeks Prior to the On-Site Inspection Week To assist NRC inspectors in conducting the supplemental inspection scheduled for the above dates, we request the following information, in hard copy or electronic format, be delivered to each of the inspectors on or before January 9, 2009. If you have any questions regarding this information, please contact the inspectors as soon as possible.
All documents associated with your evaluation of the White finding identified in Byron Station Inspection Report 05000454/455/2007009. The scope of the documents should include:
Your analysis of the root cause(s) and contributing cause(s) of the identified issue; Your evaluation of the extent of condition and extent of cause of the issue; All corrective actions implemented for the identified issue, including the schedule established for implementing and completing the corrective actions; and Your assessment/evaluation of the effectiveness of the corrective actions that have been implemented.
Information Requested for the On-Site Inspection Week To assist NRC inspectors in conducting the supplemental inspection scheduled for the above dates, we request the following information, in hard copy, be available at the entrance meeting for the inspection (January 20, 2009). The inspectors understand some of the requested documents or records may require special handling and will be available after the entrance meeting to ensure appropriate protection and control of the documents or records. If you have any questions regarding this information, please contact the inspectors as soon as possible.
All supporting documents or records associated with your corrective actions implemented for the identified issue including work packages and examination records for repairs to the essential service water system piping, plant procedure changes, training completion records, etc.