November 12, 2008 Mr. Ashok S. Bhatnagar Senior Vice President Nuclear Generation Development and Construction 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
BELLEFONTE NUCLEAR PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING ENVIRONMENTAL ASSESSMENT FOR REINSTATEMENT OF CONSTRUCTION PERMITS (TAC NOS. MD9564 AND MD9565)
Dear Mr. Bhatnagar:
By letter to the Nuclear Regulatory Commission (NRC) dated August 26, 2008, as supplemented September 25, 2008, Tennessee Valley Authority submitted a request for authorization to reinstate the Construction Permits CPPR-122 and CPPR-123 for Bellefonte Nuclear Plant, Units 1 and 2, respectively.
The NRC staff is reviewing TVAs submittal and has determined that additional information is needed to complete its review. The specific information requested is addressed in the enclosure to this letter.
This request for additional information was discussed with members of your staff, and it was agreed that a response would be provided within 14 days of the date of this letter. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-1457.
Sincerely,
/RA/
Patrick D. Milano, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-438 and 50-439
Enclosure:
Request for Additional Information cc w/encl: See next page
Mr. Ashok S. Bhatnagar Senior Vice President Nuclear Generation Development and Construction 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801
SUBJECT:
BELLEFONTE NUCLEAR PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING ENVIRONMENTAL ASSESSMENT FOR REINSTATEMENT OF CONSTRUCTION PERMITS (TAC NOS. MD9564 AND MD9565)
Dear Mr. Bhatnagar:
By letter to the Nuclear Regulatory Commission (NRC) dated August 26, 2008, as supplemented September 25, 2008, Tennessee Valley Authority submitted a request for authorization to reinstate the Construction Permits CPPR-122 and CPPR-123 for Bellefonte Nuclear Plant, Units 1 and 2, respectively.
The NRC staff is reviewing TVAs submittal and has determined that additional information is needed to complete its review. The specific information requested is addressed in the enclosure to this letter.
This request for additional information was discussed with members of your staff, and it was agreed that a response would be provided within 14 days of the date of this letter. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-1457.
Sincerely,
/RA/
Patrick D. Milano, Senior Project Manager Watts Bar Special Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-438 and 50-439
Enclosure:
Request for Additional Information cc w/encl: See next page DISTRIBUTION:
PUBLIC RidsOgcRp Resource RidsNrrLABClayton Resource (Hard Copy)
RidsNrrDorlLp-wb Resource RidsNrrPMPMilano Resource RidsNrrDorlDpr Resource RidsNrrPMJLamb Resource R. McIntyre, NRO RidsNrrDlrReba Resource LP-Wb R/F RidsAcrsAcnw_MailCTR Resource RidsRgn2MailCenter Resource RidsRgn2MailCenter Resource (R. Haag)
ADAMS Accession Number: ML083170122 OFFICE LWPB/PM LWPB/LA LWPB/BC NAME PMilano BClayton LRaghavan DATE 11 / 12 /08 11 / 12 /08 11 / 12 /08 OFFICIAL RECORD COPY
REQUEST FOR ADDITIONAL INFORMATION BELLEFONTE NUCLEAR PLANT UNITS 1 AND 2 DOCKET NOS. 50-438 AND 50-439 By letter to the Nuclear Regulatory Commission (NRC) dated August 26, 2008, as supplemented September 25, 2008, Tennessee Valley Authority (TVA) submitted a request for authorization to reinstate the Construction Permits CPPR-122 and CPPR-123 for Bellefonte Nuclear Plant (BLN), Units 1 and 2, respectively.
The TVA letter, dated August 26, 2008, stated that the environmental impacts associated with the construction of BLN Units 1 and 2 have been previously discussed and evaluated by TVA in accordance with its National Environmental Policy Act obligations as a federal agency, as well as by the NRC consistent with its domestic licensing and related regulatory authority.
The most recent NRC environmental assessment (EA) for BLN Units 1 and 2, was completed on January 16, 2003 (see Agencywide Document and Access Management System Accession No. ML030170463), for the extension of CPPR-122 and CPPR-123, respectively. In preparing that EA, the NRC staff requested additional information (ML021560599) from TVA regarding changes to construction-related impacts documented in the 1974 Final Environmental Statement (FES) for CPPR-122 and CPPR-123. By letter dated August 26, 2002 (ML022400277), TVA provided its response to the NRC.
In order to adequately assess the environmental impacts associated with TVAs request to reinstate CPPR-122 and CPPR-123, the NRC staff will evaluate any deviation from the original proposal to construct BLN, Units 1 and 2, and all impacts associated with such deviation, as compared to the 1974 FES. Accordingly, the NRC staff requests a response to the following questions:
REQUEST FOR ADDITIONAL INFORMATION (RAI) QUESTIONS
- 1. With respect to TVAs RAI responses, dated August 26, 2002, please confirm whether the responses remain full and accurate, and if not, what new or updated information regarding construction impacts pertains to the current request for reinstatement of CPPR-122 and CPPR-123. If there is new or updated information, please provide such, as appropriate. In addition, please disclose any other activities that may have occurred since the September 14, 2006, termination of CPPR-122 and CPPR-123 that may have impacts to the environment and/or natural resources.
- 2. With respect to TVAs response to Question 2 of the NRC staff RAI, dated June 5, 2002, regarding facilities that remain to be constructed, please confirm that any impacts to natural resources (e.g., aquatic, terrestrial, air quality, water quality, etc.) from such projected construction activities would remain within scope of the assessment conducted for the 1974 FES.
- 3. Please provide any changes or updates to the construction-related radiological impacts assessed in the 1974 FES.
Enclosure
Ashok S. Bhatnagar BELLEFONTE NUCLEAR PLANT Tennessee Valley Authority UNITS 1 AND 2 cc:
Mr. William R. Campbell, Jr.
Chief Nuclear Officer and Executive Vice President Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 General Counsel Tennessee Valley Authority 6A West Tower 400 West Summit Hill Drive Knoxville, TN 37902 Mr. John C. Fornicola, General Manager Nuclear Assurance Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Mr. Mike Lorek, Vice President Nuclear Engineering & Projects Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Mr. Heyward R. Rogers, Vice President Nuclear Support Tennessee Valley Authority 6A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Mr. Jack A. Bailey, Vice President Nuclear Generation Development and Business Support Tennessee Valley Authority 3F Blue Ridge 1101 Market Street Chattanooga, TN 37402-2801 Chairman Jackson County Commission Courthouse Scottsboro, AL 35752-0200 State Health Officer Alabama Dept. of Public Health RSA Tower - Administration Suite 1552 P.O. Box 303017 Montgomery, AL 36130-3017 Director Alabama Emergency Management Agency P.O. Drawer 2160 Clanton, AL 35045-5160 Mr. Larry E. Nicholson, General Manager Performance Improvement Tennessee Valley Authority 3R Lookout Place 1101 Market Street Chattanooga, TN 37402-2801 Mr. Andrea Sturgess New Generation Licensing Manager Tennessee Valley Authority 5A Lookout Place 1101 Market Street Chattanooga, TN 37402-2801