September 18, 2008 MEMORANDUM TO:
Dave Pstrak, Branch Chief Rules, Inspections, and Operations Branch Division of Spent Fuel Storage and Transportation Licensing and Inspection Directorate Office of Nuclear Material Safety and Safeguards FROM:
Sandra Wastler, Branch Chief /RA/
Materials, Waste, and International Security Branch Division of Security Policy Office of Nuclear Security and Incident Response
SUBJECT:
STAFF REVIEW OF EXELON NUCLEAR RESPONSE FOR, LIMERICK GENERATING STATION TO THE JANUARY 28, 2008 SECURITY ORDERS ISSUED TO PROPOSED DRY STORAGE AT INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS On July 2, 2008, and September 5, 2008, Exelon Nuclear submitted its responses to the January 28, 2008, Order imposing additional safeguards and security compensatory measures for spent fuel storage at Independent Spent Fuel Storage Installations (ISFSIs). Their responses concerned the implementation of security upgrades as directed by the Order and Additional Security Measures (ASMs) for Limerick Generating Station ISFSI. These upgrades are now complete. The licensee is tentatively scheduled to have their initial movement of spent nuclear fuel in early 2009. Based on our review, we have determined that the Limerick Generating Station Physical Security Plan has met the performance objectives and general requirements outlined in Title 10 of the Code of Federal Regulations 73.51 and the ASMs. This will be verified by the conduct of on-site inspections.
CONTACT: Paul Kelley, Jr., DSP/NSIR (301) 415-6106 Ed Johannemann, DSP/NSIR (301) 415-8147
September 18, 2008 MEMORANDUM TO:
Dave Pstrak, Branch Chief Rules, Inspections, and Operations Branch Division of Spent Fuel Storage and Transportation Licensing and Inspection Directorate Office of Nuclear Material Safety and Safeguards FROM:
Sandra Wastler, Branch Chief /RA/
Materials, Waste, and International Security Branch Division of Security Policy Office of Nuclear Security and Incident Response
SUBJECT:
STAFF REVIEW OF EXELON NUCLEAR RESPONSE FOR, LIMERICK GENERATING STATION TO THE JANUARY 28, 2008 SECURITY ORDERS ISSUED TO PROPOSED DRY STORAGE AT INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS On July 2, 2008, and September 5, 2008, Exelon Nuclear submitted its responses to the January 28, 2008, Order imposing additional safeguards and security compensatory measures for spent fuel storage at Independent Spent Fuel Storage Installations (ISFSIs). Their responses concerned the implementation of security upgrades as directed by the Order and Additional Security Measures (ASMs) for Limerick Generating Station ISFSI. These upgrades are now complete. The licensee is tentatively scheduled to have their initial movement of spent nuclear fuel in early 2009. Based on our review, we have determined that the Limerick Generating Station Physical Security Plan has met the performance objectives and general requirements outlined in Title 10 of the Code of Federal Regulations 73.51 and the ASMs. This will be verified by the conduct of on-site inspections.
CONTACT: Paul Kelley, Jr., DSP/NSIR (301) 415-6106 Ed Johannemann, DSP/NSIR (301) 415-8147 DISTRIBUTION:
DSP r/f ADAMS ACCESSION No.: ML082610734 OFFICE DSP/MWISB DSP BC: DSP/MWISB NAME E. Johannemann P. Kelley S. Wastler DATE 09/18/08 09/18/08 09/18/08 OFFICIAL RECORD COPY