Summary of Public Meeting to Discuss Cross-Cutting Issues, Nuclear Safety Culture Assessment, and Confirmatory Order EA-06-178 at the Point Beach Nuclear Plant
ML082480639
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 09/04/2008
From: Michael Kunowski
NRC/RGN-III/DRP/B5
To: Meyer L
Florida Power & Light Co
References
EA-06-178
Download: ML082480639 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 September 4, 2008 EA-06-178 Mr. Larry Meyer Site Vice President FPL Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241

SUBJECT:

PUBLIC MEETING TO DISCUSS CROSS-CUTTING ISSUES, NUCLEAR SAFETY CULTURE ASSESSMENT, AND CONFIRMATORY ORDER EA-06-178 AT THE POINT BEACH NUCLEAR PLANT

Dear Mr. Meyer:

This letter confirms the plans, as discussed between you and Cynthia Pederson on Friday, August 22, 2008, to hold a public meeting on your actions to address substantive cross-cutting issues at the Point Beach Nuclear Plant, Units 1 and 2. This meeting is a follow-up to the 2007 end-of-cycle public meeting held on July 16, 2008. The discussion at that earlier meeting did not provide sufficient detail for us to understand the full scope of your actions.

In addition, you and Ms. Pederson agreed that you would provide information on the preliminary results of the 2008 culture survey assessment and on the status of actions taken in response to Confirmatory Order EA-06-0178, issued on January 3, 2007.

The meeting is scheduled for Wednesday, September 24, 2008, at 9:30 a.m. (CDT), at the Region III office, 2443 Warrenville Road, Suite 210, Lisle, Illinois. The meeting is open to the public. The public is invited to observe this meeting and will have an opportunity to communicate with the NRC after the business portion, but before the meeting is adjourned.

If you have any questions regarding this meeting, please contact me at (630) 829-9618.

Sincerely,

/RA/

Michael A. Kunowski, Chief Branch 5 Division of Reactor Projects Docket Nos. 50-266; 50-301;72-005 License Nos. DPR-24; DPR-27 DISTRIBUTION:

See next page

Letter to L. Meyer from M. Kunowski dated September 4, 2008

SUBJECT:

PUBLIC MEETING TO DISCUSS CROSS-CUTTING ISSUES, NUCLEAR SAFETY CULTURE ASSESSMENT, AND CONFIRMATORY ORDER EA-06-178 AT POINT BEACH NUCLEAR PLANT cc: M. Nazar, Senior Vice President and Nuclear, Chief Operating Officer J. Stall, Executive Vice President, Nuclear and Chief Nuclear Officer A. Khanpour, Vice President, Engineering Support Licensing Manager, Point Beach Nuclear Plant M. Warner, Vice President, Nuclear Plant Support M. Ross, Managing Attorney A. Fernandez, Senior Attorney M. Gettler, Vice President, New Nuclear Projects W. Maher, Licensing Director, New Nuclear Projects K. Duveneck, Town Chairman, Town of Two Creeks Chairperson, Public Service Commission of Wisconsin J. Kitsembel, Electric Division, Public Service Commission of Wisconsin P. Schmidt, State Liaison Officer Chairman, Manitowoc County Board County Executive, Manitowoc Director, Manitowoc County Emergency Management Agency Chairman, Kewaunee County Board Mayor of Kewaunee City Manager, Two Rivers Director, Kewaunee County Emergency Management Agency President, Village of Mishicot Chairman, Village of Two Creeks G. Mortensen, INPO

September 4, 2008 EA-06-178 Mr. Larry Meyer Site Vice President FPL Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241

SUBJECT:

PUBLIC MEETING TO DISCUSS CROSS-CUTTING ISSUES, NUCLEAR SAFETY CULTURE ASSESSMENT, AND CONFIRMATORY ORDER EA-06-178 AT THE POINT BEACH NUCLEAR PLANT

Dear Mr. Meyer:

This letter confirms the plans, as discussed between you and Cynthia Pederson on Friday, August 22, 2008, to hold a public meeting on your actions to address substantive cross-cutting issues at the Point Beach Nuclear Plant, Units 1 and 2. This meeting is a follow-up to the 2007 end-of-cycle public meeting held on July 16, 2008. The discussion at that earlier meeting did not provide sufficient detail for us to understand the full scope of your actions.

In addition, you and Ms. Pederson agreed that you would provide information on the preliminary results of the 2008 culture survey assessment and on the status of actions taken in response to Confirmatory Order EA-06-0178, issued on January 3, 2007.

The meeting is scheduled for Wednesday, September 24, 2008, at 9:30 a.m. (CDT), at the Region III office, 2443 Warrenville Road, Suite 210, Lisle, Illinois. The meeting is open to the public. The public is invited to observe this meeting and will have an opportunity to communicate with the NRC after the business portion, but before the meeting is adjourned.

If you have any questions regarding this meeting, please contact me at (630) 829-9618.

Sincerely,

/RA/

Michael A. Kunowski, Chief Branch 5 Division of Reactor Projects Docket Nos. 50-266; 50-301;72-005 License Nos. DPR-24; DPR-27 DISTRIBUTION:

See next page DOCUMENT NAME: G:\1-SECY\1-WORK IN PROGRESS\PTBH 092408 MEETING LETTER.DOC G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" =

Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME MKunowski:cms MKunowski for DBetancourt DATE 9/4/08 9/4/08 OFFICIAL RECORD COPY

Letter to L. Meyer from M. Kunowski dated September 4. 2008

SUBJECT:

PUBLIC MEETING TO DISCUSS CROSS-CUTTING ISSUES, NUCLEAR SAFETY CULTURE ASSESSMENT, AND CONFIRMATORY ORDER EA-06-178 AT THE POINT BEACH NUCLEAR PLANT DISTRIBUTION:

RidsNrrDorlLpl3-1 RidsNrrPMPointBeach RidsNrrDirslpab Resource James Caldwell Mark Satorius Kenneth Obrien Jared Heck Allan Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports@nrc.gov