Letter Sequence RAI |
---|
|
|
MONTHYEARML0729801672007-10-24024 October 2007 Proposed License Amendment Request LCO 3.8.7 and 3.8.9 - Shared Components Project stage: Request ML0819004642008-07-0909 July 2008 /2, Request for Additional Information Regarding Proposed License Amendment Request (TAC MD7242 and MD7243) Project stage: RAI ML0822100122008-08-0707 August 2008 Transmittal of Response to Request for Additional Information Proposed License Amendments to Revise LCOs 3.8.7 and 3.8.9 to Support Shared Component Operability on the Opposite Unit Project stage: Response to RAI ML0826201812008-10-0909 October 2008 Issuance of Amendments Nos. 253 & 234 Regarding LCO 3.8.7 and 3.8.9, Shared Components Project stage: Approval 2008-10-09
[Table View] |
|
---|
Category:Letter
MONTHYEARML24032A1112024-02-0101 February 2024 Owner'S Activity Report for North Anna, Unit 2, Refueling Outage N2R29 - First Period of the Fifth ISI Interval ML24032A4662024-01-16016 January 2024 Response to Comments on Draft Vpdes Permit No. VA0052451 ML24017A0802024-01-11011 January 2024 Notification of Licensed Operator Initial Examination 05000338/2024301 and 05000339/2024301 ML24003A8372024-01-0909 January 2024 Letter to Elizabeth Toombs, Thpo, Cherokee Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8412024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8502024-01-0909 January 2024 Letter to Wenonah Haire, Thpo, Catawba Indian Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A7272024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8382024-01-0909 January 2024 Letter to G. Anne Richardson, Chief, Rappahannock Tribe, Inc., Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8482024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8392024-01-0909 January 2024 Letter to Gerald Stewart, Chief, Chickahominy Indian Tribe, Eastern Division Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8472024-01-0909 January 2024 Letter to Tom Jonathan, Chief, Tuscarora Nation, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8492024-01-0909 January 2024 Letter to W. Frank Adams, Chief, Upper Mattaponi Tribe Re Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8462024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8352024-01-0909 January 2024 Letter to Acee Watt, Thpo, United Keetoowah Band of Cherokee Indians in Oklahoma Re Notice of Availability of the Draft Site-Specific Environmental Impact Statement for North Anna Power Station Subsequent License Renewal ML24003A8422024-01-0909 January 2024 Letter to Paul Barton, Thpo, Eastern Shawnee Tribe of Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8432024-01-0909 January 2024 Letter to Robert Gray, Chief, Pamunkey Indian Tribe, Notice of Availability of the Draft Site-Specific EIS for North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8362024-01-0909 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML24003A8442024-01-0909 January 2024 Letter to Russell Townsend, Thpo, Eastern Band of Cherokee Indians ML24003A8402024-01-0909 January 2024 Letter to Katelyn Lucas, Thpo, Delaware Nation, Oklahoma, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML24003A8452024-01-0909 January 2024 Letter to Stephen Adkins, Chief, Chickahominy Indian Tribe, Notice of Availability of Draft Site-Specific Environmental Impact Statement for North Anna Power Station Units 1 and 2, Subsequent License Renewal ML23332A1852024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23332A0872024-01-0404 January 2024 Notice of Availability of the Draft Site-Specific Environmental Impact Statement for the North Anna Power Station, Units 1 and 2, Subsequent License Renewal ML23360A6352024-01-0404 January 2024 Letter to Dominion Availability for North Anna Units 1 and 2 Draft Site Specific Environmental Impact Statement ML23332A1472023-12-21021 December 2023 Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application ML23283A3052023-12-20020 December 2023 Review of Appendix F to DOM-NAF2, Qualification of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion Energy VIPRE-D Computer Code (EPID L-2022-LLT-0003) (Nonproprietary) ML23346A0972023-12-11011 December 2023 License Amendment Request to Revise the Emergency Plan Relocation of the Technical Support Center - Response to NRC Request for Additional Information ML23346A1022023-12-11011 December 2023 2024 North Anna Power Station Brq Inspection Notification Letter ML24012A0942023-12-0707 December 2023 GL Report from Dominion Virginia Power Regarding Transfer of Devices ML24012A0892023-12-0707 December 2023 GL Registration from Dominion Virginia Power ML23334A2432023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23362A0602023-11-29029 November 2023 ISFSI, Submittal of Cask Registration for Spent Fuel Storage IR 05000339/20234022023-11-27027 November 2023 Security Baseline Inspection Report 05000338 and 05000339/2023402 IR 05000338/20230032023-11-13013 November 2023 Integrated Inspection Report 05000338/2023003 and 05000339/2023003 ML23311A2042023-10-0909 October 2023 Annual Submittal of Technical Specification Bases Changes Pursuant to Technical Specification 5.5.13.d IR 05000338/20234032023-10-0505 October 2023 Reissue - North Anna Power Station - Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 (Cover Letter) ML23279A0612023-10-0505 October 2023 Paragon Energy Solutions LLC, Part 21 Final Report Re Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23230A0502023-10-0202 October 2023 5 of the Quality Assurance Topical Report - Review of Program Changes ML23275A0992023-09-28028 September 2023 Subsequent License Renewal Application Third 10 CFR 54.21(b) Annual Amendment IR 05000338/20230112023-09-26026 September 2023 Quadrennial Focused Engineering Inspection Commercial Grade Dedication Report 05000338/2023011 and 05000339/2023011 ML23242A3482023-09-11011 September 2023 Cyber Security Inspection Report 05000338/2023403 and 05000339/2023403 - Cover ML23254A0242023-09-0606 September 2023 Paragon Energy Solutions LLC, Potential Defect with Eaton Jd and Hjd Series Molded Case Circuit Breakers (Mccbs) ML23249A2592023-09-0606 September 2023 Core Operating Limits Report Cycle 30, Pattern Ukr, Revision 0 ML23214A2022023-09-0505 September 2023 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information 2024-02-01
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23318A1172023-11-13013 November 2023 NRR E-mail Capture - Formal Issuance of RAIs for North Anna Technical Support Center (TSC) License Amendment Request (LAR) (L-2023-LLA-0006) ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23219A1602023-08-0707 August 2023 003 Radiation Safety Baseline Inspection Information Request ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23081A5282023-04-26026 April 2023 Request for Additional Information - North Anna Subsequent License Renewal Application Environmental Review ML23075A0232023-03-15015 March 2023 NRR E-mail Capture - RAI - License Amend Req (LAR) to Revise Tech Spec (Ts) 3.6.8 Limiting Condition for Operation to Remove Refueling Water Chemical Addition Tank and Replace the Containment Sump Buffer North Anna, 1 and 2 (L-2022-LLA-0162 ML23060A0932023-03-0101 March 2023 NRR E-mail Capture - Formal Issuance of RAIs for Surry/North Anna Emergency Plans LAR ML23059A2282023-02-28028 February 2023 NRR E-mail Capture - Draft RAIs for Containment Buffer Change to Natb (L-2022-LLA-0162) ML22251A1292022-09-0909 September 2022 Request for Additional Information Related to Response to Generic Letter 2004-04 ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22083A2102022-03-24024 March 2022 NRR E-mail Capture - Draft RAI - Relief Request N2-14-LMT-003 Fourth Ten Year Inservice Inspection Interval ML21327A3652021-11-23023 November 2021 NRR E-mail Capture - Draft RAI for TSTF-577 LAR ML21322A0962021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21322A0992021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21256A0672021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21256A0692021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Request for Confirmation of Information ML21238A0942021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21238A0982021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21225A5022021-08-13013 August 2021 Request for Additional Information for North Anna Power Station, Units 1 and 2, Surry Power Station, Units 1 and 2, and Millstone Power Station, Units 2 and 3, Appendix E of Fleet Report Com-Naf-2 (EPID:L02021-LLT-0000) Public Version ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code ML21188A1632021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21188A1652021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21174A1952021-06-23023 June 2021 Safety RAIs - Set Y - Draft - Enclosure ML21166A3512021-06-15015 June 2021 Safety RAIs - Set 4 - Draft ML21123A2972021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - E-mail ML21123A2982021-05-0303 May 2021 Final Request for Additional Information Set 3 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure ML21091A0032021-04-0101 April 2021 Final Request for Additional Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Enclosure 1 - RAIs ML21091A0042021-04-0101 April 2021 SLRA Safety Review - Withdrawn Requests for Information (EPID No. L-2020-SLR-0000) - Enclosure 2 ML21076A4622021-03-17017 March 2021 NRR E-mail Capture - Draft RAI for Versatile Internals and Component Program for Reactors Vipre Code Review (L-2021-LLT-0000) ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 ML21063A5602021-03-0404 March 2021 Final Request for Additional Information Set 1 - North Anna SLRA Safety Review (EPID L-2020-SLR-0000) - Enclosure ML21049A0212021-02-17017 February 2021 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000338/2021012 and 05000339/2021012) and Request for Information (RFI) ML21028A3902021-01-29029 January 2021 Request for Additional Information - North Anna Subsequent License Renewal Application Environmental Review (EPID Number: L-2020-SLE-0000) (Docket: 50-338 and 50-339) ML21028A4352021-01-28028 January 2021 Notification of Target Set Inspection and Request for Information (NRC Inspection Report No. 05000338/2021404 and 05000339/2021404) ML21012A3412021-01-22022 January 2021 Requests for Confirmation of Information for the Environmental Review of the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application (EPID Number: L-2020-SLE-0000) (Docket: 50-338 and 50-339) ML21019A4512021-01-19019 January 2021 Notification of Inspection and Request for Information ML20316A0422020-11-10010 November 2020 NRR E-mail Capture - FW: Draft RAI for North Anna Unit 2 Steam Generator Tube Inspection Report (ML19179A075) ML20223A3412020-08-10010 August 2020 003 Radiation Safety Baseline Inspection Information Request ML20218A4282020-08-0505 August 2020 Notification of Inspection and Request for Information ML20125A0762020-05-0101 May 2020 NRR E-mail Capture - Draft RAI Related to Revised Reactor Vessel Material Surveillance Capsule Withdrawal Schedule Dominion Energy Virginia North Anna Power Station Units 1 and 2 (L-2020-LLL-0038) ML20113A5792020-04-21021 April 2020 NRR E-mail Capture - Draft RAI North Anna Fifth 10-year Interval Relief Request (L-2020-LLR-0023) ML19354B6142019-12-20020 December 2019 NRR E-mail Capture - Draft RAI for North Anna Relief Request P-9 ML19317F1042019-11-0707 November 2019 NRR E-mail Capture - Draft RAIs for SB LOCA LAR (Non Prop) ML19191A2512019-07-10010 July 2019 NRR E-mail Capture - Request for Additional Information Open Phase Condition LAR ML19169A0962019-06-17017 June 2019 NRR E-mail Capture - Request for Additional Information Emergency Action Level Scheme Change for Millstone Power Station - Units 1, 2, and 3, North Anna Power Station - Units 1 and 2, and Surry Power Station - Units 1 and 2 ML19162A0052019-06-10010 June 2019 NRR E-mail Capture - Draft RAIs for Dominion EAL Scheme Change ML19108A1902019-04-18018 April 2019 Emergency Preparedness Program Inspection Request for Information ML19060A2432019-03-0101 March 2019 Related to License Amendment Request to Address Open Phase Conditions ML18337A1312018-11-29029 November 2018 NRR E-mail Capture - North Anna SPRA (Fukushima 50.54f) Audit Follow-Up Clarification Question on Plant Modifications 2023-09-14
[Table view] |
Text
July 9, 2008 Mr. David A. Christian President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711
SUBJECT:
NORTH ANNA POWER STATION, UNIT NOS. 1 AND 2, REQUEST FOR ADDITIONAL INFORMATION (RAI) REGARDING PROPOSED LICENSE AMENDMENT REQUEST TO REVISE LIMITING CONDITION FOR OPERATIONS 3.8.7 AND 3.8.9 TO SUPPORT SHARED COMPONENT OPERABILITY ON THE OPPOSITE UNIT (MD7242 AND MD7243)
Dear Mr. Christian:
By letter dated October 24, 2007, Virginia Electric and Power Company submitted an amendment request in the form of changes to the technical specifications (TSs) to Facility Operating License Numbers NPF-4 and NPF-7 for North Anna Power Station, Unit Nos. 1 and 2, respectively. The proposed changes will revise the TSs Limiting Condition for Operations (LCO) 3.8.7 and 3.8.9, pertaining to electrical power systems and distribution associated with the 120 volt AC vital bus inverters. The TS changes are intended to support operability of components shared between Unit 1 and Unit 2. The proposed changes will add new conditions, Required Action statements and Completion Times for LCO 3.8.7 and LCO 3.8.9 to address shared components. The Nuclear Regulatory Commission (NRC) staff is reviewing the submittal and has determined that additional information is required to complete its evaluation.
The NRC staffs RAI is enclosed. The licensee is required to provide a response to the RAI within 30 days.
Sincerely,
/RA/
Siva P. Lingam, Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-338 and 50-339
Enclosure:
RAI cc w/encl: See next page
ML081900464 *transmitted by memo dated OFFICE NRR/LPL2-1/PM NRR/LPD2-1/LA NRR/DE/EEEB/BC NRR/LPL2-1/BC NAME SLingam MOBrien GWilson MWong DATE 7/2/08 7/9/08 6/26/08* 7/9/08 North Anna Power Station, Units 1 & 2 cc:
Mr. David A. Christian Mr. Daniel G. Stoddard President and Chief Nuclear Officer Site Vice President Virginia Electric and Power Company North Anna Power Station Innsbrooks Technical Center Virginia Electric and Power Company 5000 Dominion Boulevard Post Office Box 402 Glen Allen, VA 23060-6711 Mineral, Virginia 23117-0402 Mr. C. Lee Lintecum Dr. Robert B. Stroube, MD, MPH County Administrator State Health Commissioner Louisa County Office of the Commissioner Post Office Box 160 Virginia Department of Health Louisa, Virginia 23093 Post Office Box 2448 Richmond, Virginia 23218 Ms. Lillian M. Cuoco, Esq.
Senior Counsel Mr. Eric Hendrixson, Director Dominion Resources Services, Inc. Nuclear Safety & Licensing 120 Tredegar Street, RS-2 Virginia Electric and Power Company Richmond, VA 23219 North Anna Power Station P.O. Box 402 Dr. W. T. Lough Mineral, VA 23117 Virginia State Corporation Commission Division of Energy Regulation Post Office Box 1197 Richmond, Virginia 23218 Old Dominion Electric Cooperative 4201 Dominion Blvd.
Glen Allen, Virginia 23060 Mr. Chris L. Funderburk, Director Nuclear Licensing & Operations Support Dominion Resources Services, Inc.
Innsbrook Technical Center 5000 Dominion Blvd.
Glen Allen, Virginia 23060-6711 Office of the Attorney General Commonwealth of Virginia 900 East Main Street Richmond, Virginia 23219 Senior Resident Inspector North Anna Power Station U. S. Nuclear Regulatory Commission P. O. Box 490 Mineral, Virginia 23117
REQUEST FOR ADDITIONAL INFORMATION REGARDING REVISION OF TECHNICAL SPECIFICATION ASSOCIATED WITH LIMITING CONDITION FOR OPERATIONS 3.8.7 AND 3.8.9 TO ADDRESS SHARED COMPONENTS NORTH ANNA POWER STATION, UNIT NOS. 1 AND 2 DOCKET NOS. 50-338 AND 50-339 By application dated October 24, 2007 (Agencywide Documents Access and Management System (ADAMS) Accession Number ML072980167), Virginia Electric and Power Company (the licensee) proposed a license amendment to change North Anna Power Station, Unit Nos. 1 and 2 Technical Specifications (TSs). The proposed changes will revise the TSs Limiting Condition for Operations (LCO) 3.8.7 and 3.8.9, pertaining to electrical power systems and distribution associated with the 120 volt AC vital bus inverters. The TS changes are intended to support operability of components shared between Unit 1 and Unit 2. The proposed changes will add new conditions, Required Action statements and Completion Times for LCO 3.8.7 and LCO 3.8.9 to address shared components.
To complete our review of the proposed TS changes, the U. S. Nuclear Regulatory Commission staff requests the licensees response to the following:
- 1. In the proposed TSs, LCO 3.8.7, Action B, it is stated that in case: One or more inverters required by LCO 3.8.7.b inoperable, Declare associated shared components inoperable.
Provide the following information related to the above statement (preferably in the tabular form):
- a. Specific Inverter(s) out.
- b. Specific associated component(s) inoperable.
- c. Describe how this component becomes inoperable. Provide reference drawing number from where this information can be verified, if necessary.
- d. Provide the associated system which becomes inoperable due to the associated component(s) being inoperable. Provide the associated system LCO.
- 2. In the proposed TS, LCO 3.8.9, Action F, it is stated that in case: One of more required LCO 3.8.9.b AC vital electrical power distribution subsystem(s) inoperable, Declare associated shared components inoperable.
Provide the following information related to the above statement (preferably in the tabular form):
- a. Specific AC vital electrical power distribution subsystem(s).
- b. Specific associated component(s) inoperable.
Enclosure
- c. Describe how this component becomes inoperable. Provide reference drawing number from where this information can be verified, if necessary.
- d. Provide the associated system which becomes inoperable due to the associated component(s) being inoperable. Provide the associated system LCO.