June 11, 2008 ORGANIZATION: Nuclear Energy Institute

SUBJECT:

SUMMARY

OF THE LICENSE RENEWAL MEETING HELD BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION STAFF AND THE NUCLEAR ENERGY INSTITUTE The U.S. Nuclear Regulatory Commission (NRC or the staff) and the Nuclear Energy Institute (NEI) met on May 21, 2008, to discuss generic license renewal topics and license renewal process improvements. Enclosure 1 provides a listing of the meeting participants and contains the meeting agenda. A summary of the discussion follows:

1. Station blackout scoping NEI asked for a separate meeting with NRR senior managers in attendance to allow NEI to go through each of the comments they submitted on the draft interim staff guidance (ISG)

LR-ISG-2008-01, Staff Guidance Regarding the Station Blackout Rule 10 Code of Federal Regulation 50.63 (10 CFR 50.63) Associated with License Renewal Applications. The NRC staff agreed to arrange this meeting.

2. Metal fatigue NEI stated that they are providing comments on the draft Regulatory Issue Summary (RIS) on Fatigue Analysis of Nuclear Power Plant Components.
3. Audit process The NRC staff indicated that from their perspective the on-site audits for aging management were going well. There may only be a need to conduct one audit, since the focus is now on consistency with the Generic Aging Lessons Learned (GALL) Report. NEI agreed that recent audits went smoothly and the focus remained where it should. NEI indicated that interactions between the NRC and applicant were open and positive. Staff informed NEI that there will be fewer audits than previously performed because the focus of the audits will be primarily confirmation of the consistency with the GALL Report. Detailed reviews of other items will be performed at headquarters which will increase the number of requests for additional information (RAIs). NEI expressed their desire for staff to consider staggering the RAIs to better respond to the increase in RAIs.
4. Other topics
a. Environmental Review Issues The NRC staff stated that the License Renewal Generic Environmental Impact Statement (GEIS) update was progressing. The staff is targeting January 2009 to issue a draft for public comment. The GEIS, proposed rule, Standard Review Plan, and Regulatory Guide are planned to go out for comment as one package. Similar to the past GEIS update, the staff plans to conduct public workshops in Washington DC, Boston, Atlanta, Chicago, and Los Angeles.
b. License Renewal Guidance Update The staff plans to update the license renewal guidance documents. NEI indicated that they would like to provide comments on areas to be considered for updating. The staff encouraged NEI to provide specific suggestions as markups of the license renewal guidance documents for staff consideration.
c. ISG procedure revision The NRC staff stated that it was updating the ISG procedure to include environmental review issues and to incorporate RIS-07-16, Implementation of the Requirements of 10 CFR 54.37(b) for Holders of Renewed Licenses. The staff expects to issue the draft procedure for public comment by September 2008.
d. American Society of Mechanical Engineers (ASME) proposed ISG The NRC staff and ASME held a public teleconference on April 14, 2008, to discuss ASMEs proposed ISG on use of the ASME Boiler and Pressure Vessel (B&PV) Code,Section XI, Rules for Inservice Inspection of Nuclear Power Plant Components, as it applies to Title 10, Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants, of the Code of Federal Regulations (10 CFR Part 54), and as specifically referenced in NUREG-1801, Revision 1, Generic Aging Lessons Learned (GALL) Report. The meeting summary is available in the NRCs Agencywide Documents Access and Management System (ADAMS); see accession number ML081340300.
e. Inspection Procedure (IP) 71003, Post-Approval Site Inspection For License Renewal NEI had 4 follow-up questions from the IP 71003 sessions that were conducted during the 2008 Regulatory Information Conference. See ADAMS accession number ML081580496. The NRC staff will evaluate the questions and get back to NEI.
f. NFPA 805 During the April 2, 2008 license renewal public meeting, the NRC staff provided a handout (ADAMS Accession Number ML080990402) that lists several options for approaching concurrent reviews of a (LRA) and a license amendment request to adopt NFPA 805. The staff requested comments from industry.
5. Participation None

\RA\

David J. Wrona, Acting Chief Program Operations Branch Division of License Renewal Office of Nuclear Reactor Regulation Project No. 690

Enclosures:

As stated cc w/encls: See next page

ML081820017 OFFICE (A)BC:RPOB:DLR LA:DLR (A)BC:RER1:DLR BC:RER2:DLR (A)BC:RERB:DLR NAME DWrona SFigueroa JDozier RAuluck JRikhoff DATE 7/9/08 7/8/08 7/10/08 7/11/08 7/10/08

List of Participants License Renewal Meeting Between the NRC Staff and the Nuclear Energy Institute May 21, 2008 PARTICIPANTS AFFILIATIONS Samson Lee U.S. Nuclear Regulatory Commission (NRC)

Raj Auluck NRC Eric Benner NRC Jerry Dozier NRC Rani Franovich NRC Louise Lund NRC Dave Wrona NRC Yeon-Ki Chung NRC Duc Nguyen NRC John Fair NRC Ann Marie Stone NRC Jonathan Rowley NRC Evelyn Gettys NRC John Butler Nuclear Energy Institute (NEI)

Julie Keys NEI Massoud Tafazzoli AREVA Michael Fallin Constellation Mike Semmler Duke Energy Garry Young Entergy Alan Cox Entergy Fred Polaski Exelon Cliff Custer FENOC Roy Kuyler Morgan Lewis Gene Eckholt NMC Donna Latwaitis NPPD David Flyte PPL Susquehanna Michael Heath Progress Energy Ali Fakhar PSEG Loyd Wright SCE Paul Crawley STARS Deann Raleigh LIS, Scientech Steve Daly PLATTS Enclosure 1

Agenda U.S. NRC Staff and the Nuclear Energy Institute Meeting May 21, 2008 Generic License Renewal - Topics Lead

1. Station blackout scoping NRC/NEI
2. Metal fatigue NRC/NEI
3. Audit Process NRC
4. New Topics NRC/NEI
5. Public participation All Enclosure 2

Letter to Nuclear Energy Institute, from D. Wrona, dated July 11, 2008

SUBJECT:

SUMMARY

OF THE LICENSE RENEWAL MEETING HELD BETWEEN THE U.S. NUCLEAR REGULATORY COMMISSION STAFF AND THE NUCLEAR ENERGY INSTITUTE DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDci RidsNrrDra RidsNrrDe RidsNrrDeEemb RidsNrrDeEeeb RidsNrrDss RidsOgcMailCenter RidsNrrAdes


MModes, RI LLake, RII AStone, RIII LSmith, RIV

Nuclear Energy Institute Project No. 690 Ms. Christine S. Salembier, Commissioner Mary Olson State Liaison Officer Nuclear Information & Resource Service Department of Public Service Southeast Office 112 State St., Drawer 20 P.O. Box 7586 Montipelier, VT 05620-2601 Asheville, NC 28802 Ms. Julie Keys Mr. Garry G. Young Nuclear Energy Institute Manager, License Renewal Services 1776 I St., N.W., Suite 400 1448 SR 333, N-GSB-45 Washington, DC 20006-3708 Russellville, AR 72802 Mr. Frederick W. Polaski Robert A. Vincent Manager License Renewal Licensing Lead - License Renewal Project Exelon Corporation Palisades Nuclear Plant 200 Exelon Way 27780 Blue Star Memorial Highway Kennett Square, PA 19348 Covert, MI 49043 Mr. Clifford I. Custer Lorrie Bell, Project Manager Project Manager, License Renewal Wolf Creek Nuclear Operating Corporation FirstEnergy Nuclear Operating Company P.O. Box 411 P.O. Box 4 Burlington, KS 66839 Route 168 (Mail Stop SIM-2)

Shippingport, PA 15077 Roger Stewart Progress Energy Carolinas, Inc.

Mr. Paul Gunter, Director 3581 West Entrance Road Reactor Watchdog Project RNP A9 Nuclear Information & Resource Service Hartsville, SC 29550 6930 Carroll Avenue, Suite 340 Takoma Park, MD 20912 Michael H. Crowthers, Supervisor Nuclear Regulatory Affairs Mr. Hugh Jackson PPL Susquehanna, LLC Public Citizen's Critical Mass Energy & Two North Ninth Street (GENPL4)

Environment Program Allentown, PA 18101-1179 215 Pennsylvania Ave., SE Washington, DC 20003