ML081770646

From kanterella
Jump to navigation Jump to search

Request for Additional Information, Response to Security Bulletin 2007-01
ML081770646
Person / Time
Site: Millstone, Kewaunee, Surry, North Anna  Dominion icon.png
Issue date: 06/30/2008
From: Sanders C
NRC/NRR/ADRO/DORL/LPLI-2
To: Christian D
Dominion Energy Kewaunee, Dominion Nuclear Connecticut, Virginia Electric & Power Co (VEPCO)
Sandeers, Carleen, NRR/DORL, 415-1603
References
BL-07-001, TAC MD7611, TAC MD7618, TAC MD7619, TAC MD7623, TAC MD7624, TAC MD7657, TAC MD7658
Download: ML081770646 (9)


Text

June 30, 2008 Mr. David A. Christian President and Chief Nuclear Officer Dominion Energy Kewaunee, Inc.

Dominion Nuclear Connecticut, Inc.

Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

KEWAUNEE POWER STATION, MILLSTONE POWER STATION, UNITS 2 AND 3, NORTH ANNA POWER STATION, UNITS 1 AND 2, AND SURRY POWER STATION, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RE: RESPONSE TO SECURITY BULLETIN 2007-01 (TAC NOS. MD7611, MD7618, MD7619, MD7623, MD7624, MD7657, MD7658)

Dear Mr. Christian:

By letter dated February 8, 2008, Dominion Energy Kewaunee, Inc., Dominion Nuclear Connecticut, Inc., and Virginia Electric and Power Company submitted the required written response to Security Bulletin 2007-01 Security Officer Attentiveness for the subject plants in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 50.54(f) or 10 CFR 70.22(d).

The Nuclear Regulatory Commission (NRC) staff has reviewed the February 8, 2008, submittal and has determined that additional information is required to complete the final NRC staff assessment of the Dominion Energy Kewaunee, Inc., Dominion Nuclear Connecticut, Inc., and Virginia Electric and Power Company response to Security Bulletin 2007-01. Security Bulletin 2007-01 requested licensees to provide information regarding administrative and managerial programs and controls established to prevent, identify and correct security personnel inattentiveness, complicity, and failures to implement the behavioral observation program by individuals among licensee security personnel including security contractors and subcontractors.

The NRC staff will use the additional information received to inform the Commission and to determine if further regulatory action is warranted or if additional assessment of the Dominion Energy Kewaunee, Inc., Dominion Nuclear Connecticut, Inc., and Virginia Electric and Power Company program implementation is needed.

The specific information requested is addressed in the enclosure to this letter. The draft questions were sent to Margaret Earle, from your staff, on June 27, 2008, to ensure that the questions were understandable, the regulatory basis for the questions was clear, and to determine if the information was previously docketed. Additionally a response time of within 35 days of the date of this letter was communicated. Your staff did not request a conference call.

Before submitting responses to the NRC, licensees must evaluate them for proprietary, sensitive, safeguards, or classified information and mark such information appropriately.

If circumstances result in the need to revise the requested response date, please contact me at 301-415-1603.

Sincerely,

/RA/

Carleen J. Sanders, Project Manager Plant Licensing Branch I-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-305, 50-336, 50-423, 50-338, 50-339, 50-280 and 50-281

Enclosure:

Request for Additional Information cc w/encl: See next page

ML081770646 OFFICE LPL1-2/PM LPLI-2/LA LPL2-1/BC LPL3-1 LPLI-2/BC NAME CSanders ABaxter MWong LJames HChernoff DATE 06/26/2008 06/26/2008 06/27/2008 06/26/2008 6/30/08

Kewaunee Power Station, Millstone Power Station, Units 2 and 3, North Anna Power Station, Unit Nos. 1 and 2, and Surry Power Station, Unit Nos. 1 and 2 cc:

Mr. David A. Christian President and Chief Nuclear Officer Virginia Electrical and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Ms. Lillian M. Cuoco, Esq.

Senior Counsel Dominion Resources Services, Inc.

120 Tredegar Street, RS-2 Richmond, VA 23219 Mr. Donald E. Jernigan Site Vice President Surry Power Station Virginia Electric and Power Company 5570 Hog Island Road Surry, Virginia 23883-0315 Senior Resident Inspector Surry Power Station U. S. Nuclear Regulatory Commission 5850 Hog Island Road Surry, Virginia 23883 Chairman Board of Supervisors of Surry County Surry County Courthouse Surry, Virginia 23683 Dr. W. T. Lough Virginia State Corporation Commission Division of Energy Regulation Post Office Box 1197 Richmond, Virginia 23218 Dr. Robert B. Stroube, MD, MPH State Health Commissioner Office of the Commissioner Virginia Department of Health Post Office Box 2448 Richmond, Virginia 23218 Office of the Attorney General Commonwealth of Virginia 900 East Main Street Richmond, Virginia 23219 Mr. Chris L. Funderburk, Director Nuclear Licensing & Operations Support Dominion Resources Services, Inc.

Innsbrook Technical Center 5000 Dominion Blvd.

Glen Allen, Virginia 23060-6711 Mr. C. Lee Lintecum County Administrator Louisa County Post Office Box 160 Louisa, Virginia 23093 Old Dominion Electric Cooperative 4201 Dominion Blvd.

Glen Allen, Virginia 23060 Senior Resident Inspector North Anna Power Station U. S. Nuclear Regulatory Commission P. O. Box 490 Mineral, Virginia 23117 Mr. Daniel G. Stoddard Site Vice President North Anna Power Station Virginia Electric and Power Company Post Office Box 402 Mineral, Virginia 23117-0402 Mr. Setphen E. Scace Dominion Energy Kewaunee, Inc.

Kewaunee Power Station N. 490 Highway 42 Kewaunee, WI 54216

Edward L. Wilds, Jr., Ph.D.

Director, Division of Radiation Department of Environmental Protection 79 Elm Street Hartford, CT 06106-5127 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 First Selectmen Town of Waterford 15 Rope Ferry Road Waterford, CT 06385 Charles Brinkman, Director Washington Operations Nuclear Services Westinghouse Electric Company 12300 Twinbrook Pkwy, Suite 330 Rockville, MD 20852 Senior Resident Inspector Millstone Power Station c/o U.S. Nuclear Regulatory Commission P. O. Box 513 Niantic, CT 06357 Mr. J. W. "Bill" Sheehan Co-Chair NEAC 19 Laurel Crest Drive Waterford, CT 06385 Ms. Nancy Burton 147 Cross Highway Redding Ridge, CT 00870 Mr. David A. Sommers Dominion Resource Services, Inc.

5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Nelson K. Martin Manager, Nuclear Fleet Protection Services Innsbrook Technical Center 5000 Dominion Technical Center Glen Allen, VA 23060-6711 Mr. Evan W. Woollacott Co-Chair Nuclear Energy Advisory Council 128 Terrys Plain Road Simsbury, CT 06070 Mr. Joseph Roy Director of Operations Massachusetts Municipal Wholesale Electric Company P.O. Box 426 Ludlow, MA 01056 Mr. William D. Bartron Licensing Supervisor Dominion Nuclear Connecticut, Inc.

Building 475, 5th Floor Roper Ferry Road Waterford, CT 06385 Mr. J. Alan Price Site Vice President Dominion Nuclear Connecticut, Inc.

Building 475, 5th Floor Rope Ferry Road Waterford, CT 06385 Ms. Leslie N. Hartz, Vice President Nuclear Support Services Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Resident Inspectors Office U. S. Nuclear Regulatory Commission N490 Highway 42 Kewaunee, WI 54216-9510

Mr. Thomas L. Breene Dominion Energy Kewaunee, Inc.

Kewaunee Power Station N490 Highway 42 Kewaunee, WI 54216 Mr. Barry Garber Supervisor Nuclear Engineering Surry Power Station 5570 Hog Island Road Surry, VA 23883 Mr. Page Kemp Supervisor Nuclear Engineering North Anna Power Station 1022 Haley Drive Mineral, VA 23117 Mr. Thomas J. Webb, Direcctor Nuclear Safety & Licensing Dominion Energy Kewaunee, Inc.

Kewaunee Power Station N490 Highway 42 Kewaunee, WI 54216 Mr. Martin L. Smith, Project Director Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Curtis G. Luffman Manager, Nuclear Protection Services Surry Power Station 5570 Hog Island Road Surry, VA 23883 Mr. Matt Adams, Director Nuclear Safety and Licensing Virginia Electric and Power Company Surry Power Station 5570 Hog Island Road Surry, VA 23883 Mr. Mark D. Sartain, Director Nuclear Safety and Licensing Virginia Elecric and Power Company North Anna Power Station P.O. Box 402 Mineral, VA 23117 Mr. Eugene S. Grecheck, Vice President Nuclear Development Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Timothy Maddy Manager Nuclear Proection Services North Anna Power Station 1022 Haley Drive Mineral, VA 23117

Enclosure REQUEST FOR ADDITIONAL INFORMATION REVIEW OF SECURITY BULLETIN RESPONSES SUBMITTED IN RESPONSE TO SECURITY BULLETIN 2007-01 KEWAUNEE POWER STATION, MILLSTONE POWER STATION, UNITS 2 AND 3, NORTH ANNA POWER STATION, UNITS 1 AND 2, AND SURRY POWER STATION, UNITS 1 AND 2 In responding to each of the following questions, the licensee should provide information that addresses measures that are currently in place, and any additional planned actions with expected completion dates:

The NRC staff reviewed your response to Question 1b. and requests the following additional information:

1. Describe any licensee processes or programs that are in place to identify problems in climate controlled security areas. What methods are used to track, inspect, and ensure timely repairs are completed?

Include the following information in your response:

A description of how the security areas are maintained including, but not limited to: (1) a discussion of the maintenance and/or preventive maintenance process and programs in place for these security areas including an overview and brief discussion on routine inspection schedules by maintenance personnel; (2) a discussion on the process a security officer can follow to report concerns with the up-keep and maintenance of his or her post; and (3) a discussion on the timeliness of repairs and any follow-up actions taken by the licensee to ensure the repairs are completed and resolved adequately.

The NRC staff reviewed your response to Question 1c. and requests the following additional information:

2. What is the level of involvement from management who do not have direct responsibility for the security program (including executive and corporate management) in conducting behavior observations of security personnel?

Include the following information in your response:

A description of any processes in place for licensee and/or contract management, who work day-to-day at the site or visit the site on a routine basis from a corporate office or other applicable offsite location, for conducting behavior observations of security personnel while on duty at their assigned posts. Examples should include, but are not limited to, a discussion of random or scheduled observations conducted by licensee and/or contract management such as the Plant Operations Shift Managers or other Plant Operations Shift Supervisors, Plant Maintenance Supervisors (licensee and contractor), or Quality Assurance Supervisors, etc. The discussion should include whether these random or scheduled observations are proceduralized and the required or recommended level of licensee and/or contract management involvement.

The NRC staff reviewed your response to Question 1 and requests the following additional information:

3. Are security personnel provided opportunities to participate in any personnel surveys regarding the work environment? If so, what is the frequency of the surveys, the average participation rate of security personnel as compared to the general site average, and the process for providing feedback and addressing the results from the survey?
4. How is the licensees policy regarding site employee attentiveness and/or inattentiveness communicated to personnel, both licensee and contractor, and at what frequency?

The NRC staff reviewed your response to Question 2 and requests the following additional information:

5. Describe the process for employees to file reports through the site corrective action program (CAP). Can employees file CAP reports without prior supervisory/management review or approval?

Include the following information in your response:

Describe the process for employees to file reports through the CAP. Discuss the supervisor/management review and/or approval process including, but not limited to: (1) does a supervisor/manager have the authority to reject a report before entering it into the CAP without additional management review and approval; and (2) does a supervisor/manager have the authority to modify the report before such report has been entered into the CAP.

6. Can the employees view the status and disposition of reports directly, or must this information be requested? If yes, please describe the process.

The NRC staff reviewed your response to Question 4 and requests the following additional information:

7. Are formal assessments of the security program conducted by organizations/individuals that do not have direct responsibility for the security program? If so, provide information on the process, including, but not limited to, the organizations and levels of management involved, the frequency of such activities, and any tracking of how findings are resolved.
8. How are self-assessment findings and relevant operating experience information communicated to the security force? Describe those processes including, but not limited to, information such as the criteria by which such information is identified, the frequency of such communications, the responsible department(s) or position(s) for such communications, and the recipients of such communications.

Include the following information in your response:

Describe the process including, but not limited to: (1) formal or informal communication methods; (2) procedures that ensure availability of the policy to staff; and (3) training opportunities for staff to read and understand the policy.