Summary of Meeting with Nuclear Management Company Regarding Future License Amendment Requests for Emergency Diesel Generators (Edgs) for Prairie Island, Units 1 and 2
ML081710147
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 07/01/2008
From: Mahesh Chawla
NRC/NRR/ADRO/DORL/LPLIII-1
To:
Plant Licensing Branch III-2
Chawla M, NRR/DORL, 415-8371
References
TAC MD8761, TAC MD8762
Download: ML081710147 (4)


Text

July 1, 2008 LICENSEE: Nuclear Management Company (NMC)

FACILITY: Prairie Island Nuclear Generating Plant (PINGP), Unit 1 and 2

SUBJECT:

SUMMARY

OF THE JUNE 10, 2008, MEETING WITH THE LICENSEE TO DISCUSS FUTURE LICENSE AMENDMENT REQUESTS FOR EMERGENCY DIESEL GENERATORS (EDGs) FOR PRAIRIE ISLAND NUCLEAR GENERATING PLANT (PINGP), UNITS 1 AND 2 (TAC NOS. MD8761 AND MD8762)

On June 10, 2008, the Nuclear Regulatory Commission (NRC) staff held a Category 1 public meeting with representatives of Nuclear Management Company (NMC) at NRC offices in Rockville, MD. The purpose of this meeting was to discuss future license amendment requests for emergency diesel generators for PINGP, units 1 and 2. A list of attendees is provided as . The licensee=s handout material has been docketed and is publicly available at Agencywide Documents Access and Management System (ADAMS) Accession No. ML081630166.

The licensees presentation, providing the list of future EDG amendments, was outlined by the handout material. The licensee provided an overview of Unit 2 EDG issues and clarification questions were asked by the NRC staff. The presentation focused on improving the reliability of Unit 2 EDGs. The PINGP Unit 2 EDGs units have spare capacity above design loads. The existing tests, based on EDG rating, are stressing the units and the licensee is interested in lowering the Technical Specifications requirements for testing the PINGP Unit 2 EDGs. The power factor and low voltage/frequency issues are NRC identified deficiencies generically applicable to licensees who have not changed their criteria to plant-specific requirements. The fuel oil storage requirements are based on TSTF 501, currently under evaluation. Licensee wants to extend the existing interval for testing the EDG trips that are bypassed in emergency mode to provide flexibility.

There were not any members of the public present at the meeting. No comment or feedback was received at this time. Please direct any inquiries to Mr. Mahesh Chawla, NRC Project Manager for PINGP, at 301-415-8371, or @ Mahesh.chawla@nrc.gov.

Sincerely,

/RA/

Mahesh Chawla, Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306

Enclosure:

List of Attendees cc w/encl: See next page

LICENSEE: Nuclear Management Company (NMC)

FACILITY: Prairie Island Nuclear Generating Plant (PINGP), Unit 1 and 2

SUBJECT:

SUMMARY

OF THE JUNE 10, 2008, MEETING WITH THE LICENSEE TO DISCUSS FUTURE LICENSE AMENDMENT REQUESTS FOR EMERGENCY DIESEL GENERATORS (EDGs) FOR PRAIRIE ISLAND NUCLEAR GENERATING PLANT (PINGP), UNITS 1 AND 2 (TAC NOS. MD8761 AND MD8762)

On June 10, 2008, the Nuclear Regulatory Commission (NRC) staff held a Category 1 public meeting with representatives of Nuclear Management Company (NMC) at NRC offices in Rockville, MD. The purpose of this meeting was to discuss future license amendment requests for emergency diesel generators for PINGP, units 1 and 2. A list of attendees is provided as . The licensee=s handout material has been docketed and is publicly available at Agencywide Documents Access and Management System (ADAMS) Accession No. ML081630166.

The licensees presentation, providing the list of future EDG amendments, was outlined by the handout material. The licensee provided an overview of Unit 2 EDG issues and clarification questions were asked by the NRC staff. The presentation focused on improving the reliability of Unit 2 EDGs. The PINGP Unit 2 EDGs units have spare capacity above design loads. The existing tests, based on EDG rating, are stressing the units and the licensee is interested in lowering the Technical Specifications requirements for testing the PINGP Unit 2 EDGs. The power factor and low voltage/frequency issues are NRC identified deficiencies generically applicable to licensees who have not changed their criteria to plant-specific requirements. The fuel oil storage requirements are based on TSTF 501, currently under evaluation. Licensee wants to extend the existing interval for testing the EDG trips that are bypassed in emergency mode to provide flexibility.

There were not any members of the public present at the meeting. No comment or feedback was received at this time. Please direct any inquiries to Mr. Mahesh Chawla, NRC Project Manager for PINGP, at 301-415-8371, or @ Mahesh.chawla@nrc.gov.

Sincerely,

/RA/

Mahesh Chawla, Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306

Enclosure:

List of Attendees cc w/encl: See next page DISTRIBUTION:

PUBLIC RBywater, EDO JHuang, NRR MChawla, NRR LPL3-1 r/f RidsRgn3Mailcenter JMcHale, NRR RElliott, NRR RidsNrrDorlLpl3-1 GWilson, NRR LJames, NRR CSchulten, NRR RidsNrrPMPTam JAdams, NRR GMatharu, NRR RidsNrrLATHarris CTucci, NRR TMcGinty, NRR RidsOgcRp RidsAcrsAcnw&mMailCenter JMcHale, NRR LJames, NRR AKlett, NRR Adams Accession: ML081710147 OFFICE LPL3-1/PM LPL3-1/LA LPL3-1/BC NAME MChawla THarris LJames DATE 06 / 30 / 08 06 / 19 / 08 07 / 01 / 08 OFFICIAL RECORD COPY

MEETING BETWEEN NUCLEAR REGULATORY COMMISSION (NRC) AND NUCLEAR MANAGEMENT COMPANY (NMC)

LIST OF ATTENDEES PINGP UNITS 1 AND 2, EDG FUTURE AMENDMENT REQUESTS June 10, 2008 Name Organization In the order of signing up:

Mahesh (Mac) Chawla NRC/NRR*/Plant Licensing Branch III-1 Lois James NRC/NRR/Plant Licensing Branch III-1 Dale.M.Vincent NMC David Carlisle NMC Jon Anderson NMC Audrey Klett NRR/DIRS/Electrical Branch G Singh Matharu NRR/DE/Electrical Branch Carl Schulten NRC/NRR/Technical Specifications Branch John Huang NRR/DCI/Component Performance and Testing Branch George Wilson NRR/DE/Electrical Branch

  • Office of Nuclear Reactor Regulation

Prairie Island Nuclear Generating Plant, Units 1 and 2 cc:

Peter M. Glass Commissioner Assistant General Counsel Minnesota Department of Commerce Xcel Energy Services, Inc. 85 7th Place East, Suite 500 414 Nicollet Mall (MP4) St. Paul, MN 55101-2198 Minneapolis, MN 55401 Tribal Council Manager, Regulatory Affairs Prairie Island Indian Community Prairie Island Nuclear Generating Plant ATTN: Environmental Department Nuclear Management Company, LLC 5636 Sturgeon Lake Road 1717 Wakonade Drive East Welch, MN 55089 Welch, MN 55089 Nuclear Asset Manager Manager - Environmental Protection Division Xcel Energy, Inc.

Minnesota Attorney General=s Office 414 Nicollet Mall (MP4) 445 Minnesota St., Suite 900 Minneapolis, MN 55401 St. Paul, MN 55101-2127 Dennis L. Koehl U.S. Nuclear Regulatory Commission Chief Nuclear Officer Resident Inspector's Office Nuclear Management Company, LLC 1719 Wakonade Drive East 414 Nicollet Mall (MP4)

Welch, MN 55089-9642 Minneapolis, MN 55401 Administrator Joel P. Sorenson Goodhue County Courthouse Director, Site Operations Box 408 Prairie Island Nuclear Generating Plant Red Wing, MN 55066-0408 Nuclear Management Company, LLC 1717 Wakonade Drive East Mr. Michael D. Wadley Welch, MN 55089 Site Vice President Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Dr.East Welch, MN 55089 July 2006