MONTHYEARML24149A1632024-05-29029 May 2024 Summary of the May 8, 2024 Public Outreach to Discuss the NRC 2023 End-of-Cycle Plant Performance Assessment of Prairie Island Nuclear Generating Plant, Units 1 and 2 ML24088A1012024-03-29029 March 2024 Summary of March 6, 2024, Public Meeting with NSPM Regarding Planned LAR to Modify Technical Specifications Definitions and Incorporate Plant-Specific Methods for Response Time Testing for Prairie Island Nuclear Plant, Units 1 & 2 ML24043A0952024-02-21021 February 2024 Summary of January 31, 2024, Public Meeting with Xcel Energy to Discuss Amendment Application for Prairie Island Independent Spent Fuel Storage Installation ML23184A0862023-07-11011 July 2023 6/23/2023 Summary of Pre Application Public Meeting with Xcel Energy on Prairie Island ISFSI Amendment Application ML23179A2102023-06-28028 June 2023 Summary of June 5, 2023, Public Meeting with Northern States Power Company Regarding Neutron Fluence Values for Reactor Pressure Vessel Welds ML23157A0232023-06-0606 June 2023 Summary of the May 24, 2023, Public Outreach to Discuss the NRC 2022 End-of-Cycle Plant Performance Assessment of Prairie Island Nuclear Generating Plant, Units 1 and 2 ML23123A3942023-05-15015 May 2023 Summary of Public Meeting with Northern States Power Company Regarding Planned License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water System ML22130A7172022-05-10010 May 2022 Summary of the May 3, 2022, Public Outreach to Discuss the NRC 2021 End-Of-Cycle Plant Performance Assessment of Monticello and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML21294A0442021-11-0808 November 2021 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a License Amendment to Extended the Allowed Outage Time for the Vertical Motor Driven Cooling Water System Pump ML21229A1692021-08-23023 August 2021 Summary of August 11, 2021, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned License Amendment Allow Bypass Testing of the Power Range Nuclear Instrumentation System Channels ML21167A1842021-06-16016 June 2021 Summary of the June 9, 2021, Public Outreach to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML21137A1042021-05-20020 May 2021 Summary of May 6, 2021, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned License Amendment to Transition to a 24 Month Operating Cycle ML21040A4612021-02-11011 February 2021 Summary of February 3, 2021, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned License Amendment to Combine the Emergency Plans and Create a Common Emergency Operations Facility ML20296A2382020-11-0303 November 2020 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to the License Amendment to Adopt TSTF-505 Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML20274A2442020-10-16016 October 2020 Summary of 9/23/2020 Meeting with Northern States Power Co., Doing Business as Xcel Energy, on Potential License Exemption Request Related to Biennal Emergency Preparedness Exercise for Prairie Island Nuclear Generating Plant, Units 1 & 2 ML20216A6452020-08-0303 August 2020 Summary of the July 16, 2020, Public Webinar to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of the Prairie Island Generating Plant ML20114E2302020-04-23023 April 2020 Meeting Summary from Call with S. Beimers Mnshpo and NRC January 2020 Prairie Island ISFSI EA ML20111A1322020-04-21021 April 2020 April 9, 2020, Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request Related to Adopt TSTF-569 at Prairie Island Nuclear Generating Plant, Unit 1 and 2 ML20057D3912020-03-0909 March 2020 Summary of February 18, 2020, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Ament Request Related to Low Temperature Overpressurization Protection ML19347D1592020-01-0707 January 2020 Summary of December 12, 2019, Meeting with Northern States Power Co., Doing Business as Xcel Energy, and Tennessee Valley Authority Planned License Amendment Requests for Prairie Island, Units 2 and 2, and Watts Bar, Units 1 and 2 ML19289A5322019-10-28028 October 2019 Summary of September 26, 2019, Teleconference with Northern States Power Company on Potential License Amendment Request to Adopt TSTF-505, Revision 2 ML19210D5432019-08-20020 August 2019 Summary of Teleconference with Northern States Power Company on Potential License Amendment Request to Adopt Probabilistic Risk Assessment Model ML19136A0272019-05-15015 May 2019 Memorandum to C. Regan Summary of March 28, 2019, Public Meeting with Xcel Energy to Discuss Seismic Consideration for a Proposed License Amendment Increasing the Amount of Special Nuclear Material Authorized for Storage at Prairie Island I ML19058A4672019-03-11011 March 2019 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to the Amendment Request to Modify Renewed Facility Operating License Paragraph 2.C(4)(c) ML18065A5582018-03-12012 March 2018 Summary of February 20, 2018, Teleconference with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request to Adopt TSTF-425 ML17341A1292017-12-11011 December 2017 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Changes to the Security Plans at the Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML17261B0362017-09-25025 September 2017 Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential Digital Feedwater Modifications at Prairie Island Nuclear Generating Plant, Units 1 and 2 ML17235B1802017-08-23023 August 2017 Summary of Open House to Discuss the 2016 End-Of-Cycle Plant Performance Assessment of Prairie Island ML17209A1192017-07-17017 July 2017 Summary of July 17, 2017, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request Related to Heavy Lifting Devices L-PI-17-014, Summary of Public Meeting and Plan for NRC Request for Additional Information Regarding License Amendment Request for Spent Fuel Pool Criticality Technical Specification Changes (CAC Nos. MF7121...2017-04-19019 April 2017 Summary of Public Meeting and Plan for NRC Request for Additional Information Regarding License Amendment Request for Spent Fuel Pool Criticality Technical Specification Changes (CAC Nos. MF7121... ML17093A6012017-04-0606 April 2017 March 9, 2017, Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to the Spent Fuel Pool Criticality License Amendment Request ML17034A1202017-02-0909 February 2017 Summary of January 24, 2017, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential Revision to the Emergency Action Level ML16111B1912016-04-28028 April 2016 Summary of Meeting with Northern States Power Company, a Minnesota Corporation, Doing Business as Xcel Energy, on National Fire Protection Association (NFPA) 805 License Amendment Request ML15271A2072015-10-0202 October 2015 July 9, 2015 Summary of Closed Meeting Between Representatives of the U.S. Army Corps of Engineers, U.S, Nuclear Regulatory Commission and Northern States Power Company- Minnesota to Discuss Flood Analysis Associated with Monticello Nuclear ML15141A5092015-05-21021 May 2015 Meeting Summary with Public to Discuss the Results of the 2014 Problem Identification and Resolution Inspection for Prairie Island Nuclear Generating Plant ML15107A0592015-05-15015 May 2015 Summary of the April 14, 2015, Public Meeting with Xcel Energy and Westinghouse to Discuss a Future License Amendment Request Regarding the Use of Ifba Rods in Nuclear Fuel at the Prairie Island Nuclear Generating Plant ML15131A4482015-05-0707 May 2015 Reactor Oversight Process Task Force FAQ Log - April 16, 2015 ML14220A2832014-09-0808 September 2014 Summary of August 5, 2014, Closed Meeting Between Representatives of the U.S. Army Corps of Engineers, NRC, and Northern States Power Company - Minnesota to Discuss Flooding Analysis Associated with Monticello and Prairie Island Nuclear Gen ML14223A8012014-08-11011 August 2014 Public Meeting Summary to Discuss the 2013 Performance of Prairie Island Nuclear Generating Plant Units 1 and 2 ML14227A8852014-07-0202 July 2014 E-mail P Longmire, NRC, Re e-mail Fr Samuel Chesnutt, Xcel Energy, Re Meeting Summary for the June 16, 2014 Prairie Island ISFSI License Renewal Application RAI Discussion ML14153A0252014-06-20020 June 2014 Meeting Summary - Public Meeting on May 16, 2014, to Discuss Xcel Energy'S Flood Hazard Reevaluation Extension Request for the Monticello and Prairie Island Nuclear Generating Plants ML14168A0182014-05-16016 May 2014 Xcel Energy Responses to NRC Questions Regarding Flood Hazard Reevaluation Report Extension Requests ML14056A4942014-03-10010 March 2014 Summary of the February 19, 2014, Pre-Application Meeting to Discuss the Diesel Generator Voltage and Frequency Limits License Request ML13210A3022013-07-29029 July 2013 Summary of Public Meeting with Northern States Power Company to Discuss the 2012 Prairie Island Nuclear Generating Plant End-of-Cycle Performance Assessment ML13171A2472013-06-20020 June 2013 7/11/2013 - Notice of Public Meeting to Discuss 2012 End-Of-Cycle Performance Assessment for Prairie Island Nuclear Generating Plant, Units 1 and 2 ML13004A3722013-01-11011 January 2013 December 6, 2012, Summary of Meeting to Discuss the Licensee'S Proposed FLEX Strategy in Response to NRC Order EA-12-049 ML12326A9702012-11-21021 November 2012 Summary of October 24, 2012, Meeting with the Northern States Power Company, D/B/A Excel Energy Regarding Security Requirements and Changes Pertaining to Prairie Island TAC L24689 W/ Encl 1 (Attendees) and Encl 2 (Agenda) ML12292A4202012-11-0707 November 2012 September 27, 2012 - Summary of Pre-Application Meeting to Discuss the Diesel Generator Voltage and Frequency Limits License Amendment Request ML12214A2332012-07-31031 July 2012 July 17, 2012 Summary of Public Meeting to Discuss the Prairie Island Nuclear Generating Plant, Units 1 and 2, End-of-Cycle Plant Performance Assessment ML12121A5842012-05-17017 May 2012 Meeting Summary with Northern States Power Co, to Discuss the National Fire Protection Association Standard 805 (NFPA 805) License Amendment Request 2024-05-29
[Table view] |
Text
July 1, 2008 LICENSEE: Nuclear Management Company (NMC)
FACILITY: Prairie Island Nuclear Generating Plant (PINGP), Unit 1 and 2
SUBJECT:
SUMMARY
OF THE JUNE 10, 2008, MEETING WITH THE LICENSEE TO DISCUSS FUTURE LICENSE AMENDMENT REQUESTS FOR EMERGENCY DIESEL GENERATORS (EDGs) FOR PRAIRIE ISLAND NUCLEAR GENERATING PLANT (PINGP), UNITS 1 AND 2 (TAC NOS. MD8761 AND MD8762)
On June 10, 2008, the Nuclear Regulatory Commission (NRC) staff held a Category 1 public meeting with representatives of Nuclear Management Company (NMC) at NRC offices in Rockville, MD. The purpose of this meeting was to discuss future license amendment requests for emergency diesel generators for PINGP, units 1 and 2. A list of attendees is provided as . The licensee=s handout material has been docketed and is publicly available at Agencywide Documents Access and Management System (ADAMS) Accession No. ML081630166.
The licensees presentation, providing the list of future EDG amendments, was outlined by the handout material. The licensee provided an overview of Unit 2 EDG issues and clarification questions were asked by the NRC staff. The presentation focused on improving the reliability of Unit 2 EDGs. The PINGP Unit 2 EDGs units have spare capacity above design loads. The existing tests, based on EDG rating, are stressing the units and the licensee is interested in lowering the Technical Specifications requirements for testing the PINGP Unit 2 EDGs. The power factor and low voltage/frequency issues are NRC identified deficiencies generically applicable to licensees who have not changed their criteria to plant-specific requirements. The fuel oil storage requirements are based on TSTF 501, currently under evaluation. Licensee wants to extend the existing interval for testing the EDG trips that are bypassed in emergency mode to provide flexibility.
There were not any members of the public present at the meeting. No comment or feedback was received at this time. Please direct any inquiries to Mr. Mahesh Chawla, NRC Project Manager for PINGP, at 301-415-8371, or @ Mahesh.chawla@nrc.gov.
Sincerely,
/RA/
Mahesh Chawla, Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306
Enclosure:
List of Attendees cc w/encl: See next page
LICENSEE: Nuclear Management Company (NMC)
FACILITY: Prairie Island Nuclear Generating Plant (PINGP), Unit 1 and 2
SUBJECT:
SUMMARY
OF THE JUNE 10, 2008, MEETING WITH THE LICENSEE TO DISCUSS FUTURE LICENSE AMENDMENT REQUESTS FOR EMERGENCY DIESEL GENERATORS (EDGs) FOR PRAIRIE ISLAND NUCLEAR GENERATING PLANT (PINGP), UNITS 1 AND 2 (TAC NOS. MD8761 AND MD8762)
On June 10, 2008, the Nuclear Regulatory Commission (NRC) staff held a Category 1 public meeting with representatives of Nuclear Management Company (NMC) at NRC offices in Rockville, MD. The purpose of this meeting was to discuss future license amendment requests for emergency diesel generators for PINGP, units 1 and 2. A list of attendees is provided as . The licensee=s handout material has been docketed and is publicly available at Agencywide Documents Access and Management System (ADAMS) Accession No. ML081630166.
The licensees presentation, providing the list of future EDG amendments, was outlined by the handout material. The licensee provided an overview of Unit 2 EDG issues and clarification questions were asked by the NRC staff. The presentation focused on improving the reliability of Unit 2 EDGs. The PINGP Unit 2 EDGs units have spare capacity above design loads. The existing tests, based on EDG rating, are stressing the units and the licensee is interested in lowering the Technical Specifications requirements for testing the PINGP Unit 2 EDGs. The power factor and low voltage/frequency issues are NRC identified deficiencies generically applicable to licensees who have not changed their criteria to plant-specific requirements. The fuel oil storage requirements are based on TSTF 501, currently under evaluation. Licensee wants to extend the existing interval for testing the EDG trips that are bypassed in emergency mode to provide flexibility.
There were not any members of the public present at the meeting. No comment or feedback was received at this time. Please direct any inquiries to Mr. Mahesh Chawla, NRC Project Manager for PINGP, at 301-415-8371, or @ Mahesh.chawla@nrc.gov.
Sincerely,
/RA/
Mahesh Chawla, Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306
Enclosure:
List of Attendees cc w/encl: See next page DISTRIBUTION:
PUBLIC RBywater, EDO JHuang, NRR MChawla, NRR LPL3-1 r/f RidsRgn3Mailcenter JMcHale, NRR RElliott, NRR RidsNrrDorlLpl3-1 GWilson, NRR LJames, NRR CSchulten, NRR RidsNrrPMPTam JAdams, NRR GMatharu, NRR RidsNrrLATHarris CTucci, NRR TMcGinty, NRR RidsOgcRp RidsAcrsAcnw&mMailCenter JMcHale, NRR LJames, NRR AKlett, NRR Adams Accession: ML081710147 OFFICE LPL3-1/PM LPL3-1/LA LPL3-1/BC NAME MChawla THarris LJames DATE 06 / 30 / 08 06 / 19 / 08 07 / 01 / 08 OFFICIAL RECORD COPY
MEETING BETWEEN NUCLEAR REGULATORY COMMISSION (NRC) AND NUCLEAR MANAGEMENT COMPANY (NMC)
LIST OF ATTENDEES PINGP UNITS 1 AND 2, EDG FUTURE AMENDMENT REQUESTS June 10, 2008 Name Organization In the order of signing up:
Mahesh (Mac) Chawla NRC/NRR*/Plant Licensing Branch III-1 Lois James NRC/NRR/Plant Licensing Branch III-1 Dale.M.Vincent NMC David Carlisle NMC Jon Anderson NMC Audrey Klett NRR/DIRS/Electrical Branch G Singh Matharu NRR/DE/Electrical Branch Carl Schulten NRC/NRR/Technical Specifications Branch John Huang NRR/DCI/Component Performance and Testing Branch George Wilson NRR/DE/Electrical Branch
- Office of Nuclear Reactor Regulation
Prairie Island Nuclear Generating Plant, Units 1 and 2 cc:
Peter M. Glass Commissioner Assistant General Counsel Minnesota Department of Commerce Xcel Energy Services, Inc. 85 7th Place East, Suite 500 414 Nicollet Mall (MP4) St. Paul, MN 55101-2198 Minneapolis, MN 55401 Tribal Council Manager, Regulatory Affairs Prairie Island Indian Community Prairie Island Nuclear Generating Plant ATTN: Environmental Department Nuclear Management Company, LLC 5636 Sturgeon Lake Road 1717 Wakonade Drive East Welch, MN 55089 Welch, MN 55089 Nuclear Asset Manager Manager - Environmental Protection Division Xcel Energy, Inc.
Minnesota Attorney General=s Office 414 Nicollet Mall (MP4) 445 Minnesota St., Suite 900 Minneapolis, MN 55401 St. Paul, MN 55101-2127 Dennis L. Koehl U.S. Nuclear Regulatory Commission Chief Nuclear Officer Resident Inspector's Office Nuclear Management Company, LLC 1719 Wakonade Drive East 414 Nicollet Mall (MP4)
Welch, MN 55089-9642 Minneapolis, MN 55401 Administrator Joel P. Sorenson Goodhue County Courthouse Director, Site Operations Box 408 Prairie Island Nuclear Generating Plant Red Wing, MN 55066-0408 Nuclear Management Company, LLC 1717 Wakonade Drive East Mr. Michael D. Wadley Welch, MN 55089 Site Vice President Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Dr.East Welch, MN 55089 July 2006