June 4, 2008 Mr. Theodore A. Sullivan Site Vice President Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station 185 Old Ferry Road P.O. Box 500 Brattleboro, VT 05302-0500
SUBJECT:
REQUALIFICATION PROGRAM INSPECTION - (VERMONT YANKEE)
Dear Mr. Sullivan:
In a telephone conversation on June 4, 2008, Mr. Kevin Stupak, Operations Training Superintendent, and Mr. Joseph DAntonio, Senior Operations Engineer, made arrangements for the U. S. Nuclear Regulatory Commission (NRC) to inspect the licensed operator requalification program at the Vermont Yankee facility. The inspection is planned for the week of July 14, 2008, which coincides with your regularly scheduled requalification examination cycle. The staff at your facility should prepare and conduct the requalification examinations in accordance with your NRC-approved requalification program.
In accordance with 10 CFR 55.59(c), the NRC may request facility licensees to submit their biennial comprehensive requalification written examinations or annual operating tests as necessary to support the NRC's inspection program needs. In order for the NRC to adequately prepare for this inspection, please furnish: 1) an index or summary of condition reports written in the past two years in which licensed operator errors were determined to be the root or contributing cause; 2) an index or summary of condition reports written in the past two years on simulator performance problems; and 3) the examination schedule and operating test scheduled for the week of the inspection to the NRC by July 7, 2008. Mr. Stupak has been advised of this request and provided with the name and address of the NRC lead inspector assigned to this inspection.
This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018, which expires on June 30, 2009.
The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate to the Records and FOIA/Privacy Services Branch (T-5 F52), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to INFOCOLLECTS@NRC.GOV ; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.
Mr. T. Sullivan 2
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC=s document system (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).
Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. Joseph DAntonio at (610) 337-5085.
Sincerely,
/RA/
John Caruso, Chief Operations Branch Division of Reactor Safety Docket No.
50-271 License No.
Mr. T. Sullivan 2
The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless it displays a currently valid OMB control number.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRC=s document system (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).
Thank you for your cooperation in this matter. If you have any questions regarding this inspection, please contact Mr. Joseph DAntonio at (610) 337-5085.
Sincerely,
/RA/
John Caruso, Chief Operations Branch Division of Reactor Safety Docket No.
50-271 License No.
DPR-28 SUNSI Review Complete: JGC (Reviewer=s Initials)
ADAMS PKG: ML081540319 ADAMS ACC#ML081570126 DOCUMENT NAME: G:\\DRS\\Operations Branch\\DANTONIO\\Requal FY08 - VY July'08\\60dayrpi.doc After declaring this document AAn Official Agency Record@ it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRS/OB RI/DRS/OB RI/DRS/OB NAME CJBixler/CJB JMDAntonio/JMD JGCaruso/JGC DATE 06/04/08 06/04/08 06/04/08 OFFICIAL RECORD COPY
Mr. T. Sullivan 3
cc w/encl:
Vice President, Operations, Entergy Nuclear Operations Senior Vice President, Entergy Nuclear Operations Vice President, Oversight, Entergy Nuclear Operations Senior Manager, Nuclear Safety & Licensing, Entergy Nuclear Operations Senior Vice President and COO, Entergy Nuclear Operations Assistant General Counsel, Entergy Nuclear Operations Manager, Licensing, Entergy Nuclear Operations G. Edwards S. Lousteau, Treasury Department, Entergy Services, Inc.
D. O Dowd, Administrator, Radiological Health Section, DPHS, State of New Hampshire W. Irwin, Chief, CHP, Radiological Health, Vermont Department of Health Chief, Safety Unit, Office of the Attorney General, Commonwealth of Mass.
D. Lewis, Pillsbury, Winthrop, Shaw, Pittman LLP G. D. Bisbee, Esquire, Deputy Attorney General, Environmental Protection Bureau J. Block, Esquire J. P. Matteau, Executive Director, Windham Regional Commission D. Katz, Citizens Awareness Network (CAN)
R. Shadis, New England Coalition Staff G. Sachs, President/Staff Person, c/o Stopthesale J. Volz, Chairman, Public Service Board, State of Vermont Chairman, Board of Selectman, Town of Vernon C. Pope, State of New Hampshire, SLO D. O'Brien, State of Vermont, SLO J. Giarrusso, SLO, MEMA, Commonwealth of Massachusetts U. Vanags, State Nuclear Engineer, Vermont Department of Public Service S. Shaw M. Desilets, Manager, Training and Development (Vermont Yankee)
Mr. T. Sullivan 4
Distribution w/encl:
(via E-mail)
S. Collins, RA M. Dapas, DRA M. Gamberoni, DRS R. Powell, DRP B. Norris, DRP N. Sieller, DRP S. Williams, RI OEDO M. Kowal, NRR R. Nelson, NRR J. Kim, PM, NRR J. Boska, Backup PM, NRR S. Hansell, DRS J. Caruso, DRS J. DAntonio, DRS Examiner, DRS R. Fernandes, SRI B. Sienel, DRP, Resident Inspector A. Rancourt, DRP, Resident OA Region I Docket Room (with concurrences)
Distribution w/encl:
DRS Master Exam File (C. Bixler) (w/concurrences)
DRS File