May 1, 2008 MN-08-019 LICENSEE: PSEG NUCLEAR, LLC (PSEG)

FACILITY: SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2, AND HOPE CREEK GENERATING STATION

SUBJECT:

SUMMARY

OF ANNUAL ASSESSMENT MEETING WITH PSEG NUCLEAR, LLC (PSEG)

On April 30, 2008, at 6:00 p.m., the U. S. Nuclear Regulatory Commission (NRC) conducted an annual assessment meeting with PSEG Nuclear, LLC (PSEG) at the Holiday Inn-Bridgeport, Swedesboro, NJ. The NRC requested the meeting to discuss its assessment of PSEG safety performance at Salem, PSEG, and Hope Creek for the period January 1 through December 31, 2007, as documented in the NRC annual assessment letters for Salem and Hope Creek dated March 3, 2008.

The NRC presentation included a discussion of the Reactor Oversight Process, 2007 performance assessment results, and an overview of the remaining planned inspections at Salem and Hope Creek for calendar year 2008. The NRCs overall assessment was that PSEG operated Salem and Hope Creek in a manner that preserved public health and safety and the environment. PSEG stated that they were in general agreement with the NRCs assessment and discussed planned areas for improvement.

A number of U. S. Congressional staffers, PSEG employees, local media, and the general public observed this meeting and were offered the opportunity to ask the NRC questions regarding PSEGs performance and the role of the agency in ensuring safe plant operations.

The question and answer period accommodated all individuals who desired to speak or ask questions after the business portion of the meeting was completed. Feedback forms submitted by the public following the meeting will be evaluated. The NRCs assessment letters for Salem and Hope Creek can be found in ADAMS with accession numbers ML080610006 and ML080600400. The meeting notice with the attached meeting agenda can be found in ADAMS with accession number ML0812021052, and the meeting slides can be found in ADAMS with accession number ML081260526. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Arthur L. Burritt, Chief Projects Branch 3 Division of Reactor Projects Attachments: Principal Meeting Attendees and Observers

2 April 30, 2008 NRC-PSEG Annual Assessment Meeting Principal Meeting Attendees and Observers NRC Attendees: S. Collins, Regional Administrator J. Clifford, Deputy Director, Division of Reactor Projects A. Burritt, Chief, Projects Branch 3, Division of Reactor Projects D. Schroeder, Senior Resident Inspector, Salem B. Welling, Senior Resident Inspector, Hope Creek H. Balian, Resident Inspector, Salem N. Sieller, Resident Inspector (acting), Hope Creek N. Sheehan, Public Affairs PSEG Energy Attendees: W. Levis, President and Chief Nuclear Officer T. Joyce, Senior Vice President, Operations G. Barnes, Site Vice President, Hope Creek R. Braun, Site Vice President, Salem Observers: A number of other individuals were present including U. S.

Congressional staffers, representatives from PSEG, the state of New Jersey, the local media and members of the general public.

3 S. Collins, RA M. Dapas, DRA D. Lew, DRP J. Clifford, DRP A. Burritt, DRP L. Cline, DRP J. Tomlinson, DRP D. Schroeder, DRP, Sr Resident Inspector, Salem G. Malone, DRP, Sr. Resident Inspector, Hope Creek B. Welling, DRP, Sr. Resident Inspector, Hope Creek H. Balian, DRP, Resident Inspector, Salem K. Venuto, OA S. Williams, RI OEDO R. Nelson, NRR H. Chernoff, NRR E. Miller, PM, NRR N. Sieller, DRP N. Sheehan, PAO Accession No. ML081260336 - Mtg Summary ML081260409 - PSEG Slides SUNSI Review Complete: _ALB_____ (Reviewers Initials)

DOCUMENT NAME: G:\DRP\BRANCH3\COMMUNICATIONS\EXTERNAL\PUBLIC MEETINGS\2008 ANNUAL ASSESSMENT MEETINGS\SALEM AND HOPE CREEK\SALEM HOPE CREEK MEETING

SUMMARY

2008.DOC After declaring this document AAn Official Agency Record@ it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME LCline/ LC ABurritt/ ALB DATE 05/01 /08 05/ 01/08 OFFICIAL RECORD COPY