IR 5000275-08-007 and 05000323-08-007, on 04/29/2008, Diablo Canyon Power Plant - Site-Specific Implementation of B.5.B Phase 2 and 3 Mitigating Strategies Draft Temporary Instruction Inspection
ML081230554
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 05/01/2008
From: Ryan Lantz
Operations Branch IV
To: Conway J
Pacific Gas & Electric Co
References
IR-08-007
Download: ML081230554 (3)


See also: IR 05000275/2008007

Text

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

UNITED STATES

NU CLE AR RE GU LATOR Y C O M M I S S I O N

R EGI ON I V

611 R YAN PLAZA D R IV E, SU ITE 400

AR LI N GTON , TEXAS 76011-4005

May 1, 2008

Mr. John T. Conway

Senior Vice President and Chief Nuclear Officer

Pacific Gas and Electric Company

P.O. Box 3

Mail Code B32

San Francisco, CA 94177-0001

SUBJECT: DIABLO CANYON POWER PLANT - SITE-SPECIFIC IMPLEMENTATION

OF B.5.B PHASE 2 AND 3 MITIGATING STRATEGIES DRAFT

TEMPORARY INSTRUCTION INSPECTION (NRC INSPECTION

REPORT 05000275/2008007 AND 05000323/2008007)

Dear Mr. Conway:

In a telephone conversation on April 29, 2008, Messrs. Steven Hamilton and John Kirkland

made arrangements for the NRC to inspect the site-specific implementation of B.5.b Phase 2

and 3 mitigating strategies at the Diablo Canyon Power Plant. The inspection is planned for the

week of June 16, 2008.

In order for the NRC to adequately prepare for this inspection, please furnish the documents

listed in Enclosure 1 to Mr. John Kirkland in electronic format no later than May 23, 2008.

Please have available on site at the beginning of the inspection the arrangements and

documents listed in Enclosure 2. Mr. Steven Hamilton has been advised of this request and

provided with the name and address of the NRC lead inspector and the Office of Nuclear

Reactor Regulation inspector assigned to this inspection.

This letter contains information collections that are subject to the Paperwork Reduction Act of

1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of

Management and Budget, approval number 3150-0018, which expires on June 30, 2009.

The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per

response, including the time for reviewing instructions, gathering and maintaining the data

needed, and completing and reviewing the collection of information. Send comments on any

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

Pacific Gas and Electric Company -2-

aspect of this collection of information, including suggestions for reducing the burden, to the

Information and Records Management Branch (T-5 F53), U.S. Nuclear Regulatory Commission,

Washington, D.C. 20555-0001, or by Internet electronic mail at margie.janney@nrc.gov; and to

the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018),

Office of Management and Budget, Washington, D.C. 20503-0001.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be

available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records System (PARS) component of NRC's Agencywide Documents

Access and Management System (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However,

because of the sensitive information contained in the enclosures, and in accordance with

10 CFR 2.390, a copy of this letters enclosures will not be available for public inspection.

Thank you for your cooperation in this matter. If you have any questions regarding this

inspection, please contact John Kirkland at 402-426-9611, or me at 817 860-8159.

Sincerely,

/RA/

Ryan E. Lantz, Chief

Operations Branch

Division of Reactor Safety

Dockets: 50-275; 50-323

Licenses: DPR-80; DPR-82

Enclosures:

1. Documentation Requested

Prior to the Inspection

2. Arrangements/Documents Requested

To Be Available Onsite during the

Inspection Week

cc w/enclosure:

Steven Hamilton

Diablo Canyon Operations and

Station Director, Pacific Gas and

Electric Company

Diablo Canyon Power Plant

P.O. Box 56

Avila Beach, CA 93424

cc w/o enclosure:

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

Pacific Gas and Electric Company -3-

James R. Becker, Vice President

Diablo Canyon Operations and

Station Director, Pacific Gas and

Electric Company

Diablo Canyon Power Plant

P.O. Box 56

Avila Beach, CA 93424

Jennifer Post, Esq.

Pacific Gas and Electric Company

P.O. Box 7442

San Francisco, CA 94120

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION