ML081130097

From kanterella
Jump to navigation Jump to search
Submittal of NPDES Discharge Monitoring Report for February 2008
ML081130097
Person / Time
Site: Perry  
Issue date: 04/09/2008
From: Bezilla M
FirstEnergy Nuclear Operating Co
To:
Office of Nuclear Reactor Regulation, State of OH, Environmental Protection Agency
References
PY-CEI/OEPA-0485L
Download: ML081130097 (10)


Text

FENOC Perry Nuclear Power Station 10 Center Road FirstEnergy Nuclear Operating Company Perry, Ohio 44081 Mark B. Bezilla 440-280-5382 Vice President Fax: 440-280-8029 April,9, 2008, PY-CEI/QEPA-0485L Ohio,- Environmepta-Protection Agency D'iv)iSi[

of Water Pollution Control Enforcem6ent.Section, ES/DMR

,P.O. Box 10,49.

Colpmbus,iOhio 43216*1 049

SUBJECT:

PerryýNuclear Power Plant, February NPDES Discharge Monitoring Report Enclosed are the Perry Nuclear Power Plant, NPDES monthly report forms for the month of February 2008. No violations occurred during this period.

If you have questions or require additional information, please contact Mrs. Liz Ryan at (440) 280-5536.

Sincerely, Enclosures A Station Code 004 Report B Station,Cobde 094. Report C.Station C8ode0 601 ReportUý D Sta'ation Code 602 Report E Station Code 800 Report cc: NRC Region III-NRC Resident. Inspector NRR Project Manager NRC Document Control Desk (Docket No. 50-440)

iag I

1 i Ohio E'

- Daily Discharge Monitoring Report*

rm 4500 FACILITY:

LOCATION:

COUNTY:

DISTRICT:

FirstEnergy Perry Nuclear Power PIt 10 Center Rd North Perry, 44081 Lake NEDO PERMIT NUMBER:

STATION CODE:

MONITORING PERIOD:

REPORTING LAB:

ANALYST:

NO DISCHARGE INDICATOR:

31BOO016 *ID 004 2008-03-01 To: 2008-03-31 CCB125 Liz Ryan PARAMETER Water Flow Rate pH Zinc, Total Copper, Total Oxidants, Total Chlorine, Total Temperature Recoverable Recoverable Residual Residual PARAMETER CODE 00011 50050 00400 01094 01119 34044 50060 UNITS 4103 4108 6653 4107 4107 4106 4106 FREQUENCY I/Day I

/Day 2/Week 1/Month 1/Month When Disch.

When Disch.

SAMPLING TYPE Continuous Continuous Grab Grab Grab Grab Grab 2008-03-01 45 95.6 AH AA 0.05 2008-03-02 44 96.6 AH AA 0.05 2008-03-03 46 89.5 AH AA 0.05 2008-03-04 44 101.5 8.54 AH AA 0.05 2008-03-05 44 100.4 AH AA 0.05 2008-03-06 43 96.6 AH 0.06 2008-03-07 44 89.1 8.5 AA 8.0 5.89 AH AA 0.05 2008-03-08 44 97.6 AH AA 0.05 2008-03-09 43 93.1 AH AA 0.05 2008-03-10 42 74.0 AH AA 0.05 2008-03-11 41 76.9 8.33 AH AA 0.05 2008-03-12 42 74.8 AH AA 0.05 2008-03-13 41 75.8 AH AA 0.05 2008-03-14 43 81.0 8.36 AH AA 0.05 2008-03-15 42 83.4 AH AA 0.05 2008-03-16 42 86.1 AH AA 0.05 2008-03-17 41 85.4 AH AA 0.05 2008-03-18 42 82.1 8.24 AH AA0.05 2008-03-19 44 81.0 Al AA 0.05 2008-03-20 43 83.9 AH AA 0.05 2008-03-21 42 86.4 8.54 AH AA 0.05 2008-03-22 43 80.8 AH AA 0.05 2008-03-23 43 83.2 AH AA 0.05 2008-03-24 43 83.7 AH AA 0.05 2008-03-25 43 77.9 8.4 AH AA 0.05 2008-03-26 45 76.1 AH AA 6.05 2008-03-27 43 75.6 AH AA 0.05 2008-03-28 42 81.1 853 AH AA 0.05 2008-03-29 43 82.8 AH AA 0.05 2008-03-30 43 80.7 AH AA 0.05 2008-03-31 44 81.5 AH AA 0.05 Name/Title of Responsible I certify under the penalty of law that I have personally examined and am familiar Signature of Date (MM/DD/YY)

Official or Authorized with the information submitted herein and based on my inquiry of those Responsible Official or Representative individuals immediately responsible for obtaining the information, I believe the Authorized submitted information is true, accurate and complete. I am aware that there are Representative significant penalties for submitting false information, including the possibility of

/Y/i/..

i -e

(

fine and imprisonment.

AAJ 0,010/0 When completed mail this report to: EDMR Administrator, EDMR Administrator,,, OH,

/

Page 1 V

https://ebiz.epa.ohio.gov/edwr.web/page/report/viewWithXslt.do?actType=viewWithXslt&f...

4/2/2008

.F agc /- V1 I I Ohio E

- Daily Discharge Monitoring Report, rm 4500 FACILITY:

LOCATION:

COUNTY:

DISTRICT:

FirstEnergy Perry Nuclear Power Pit 10 Center Rd North Perry, 44081 Lake NEDO PERMIT NUMBER:

STATION CODE:

MONITORING PERIOD:

REPORTING LAB:

ANALYST:

NO DISCHARGE INDICATOR:

31BOO016*ID 004 2008-03-01 To: 2008-03-31 CCB125 Liz Ryan Phlorination/Brominatior PARAMETER Drto Duration PARAMETER 78739 CODE UNITS 6655 FREQUENCY When Disch.

SAMPLING TYPE Total 2008-03-01 100 2008-03-02 100 2008-03-03 100 2008-03-04 105 2008-03-05 100 2008-03-06 104 2008-03-07 100 2008-03-08 100 2008-03-09 110 2008-03-10 100 2008-03-11 100 2008-03-12 100 2008-03-13 100 2008-03-14 100 2008-03-15 100 2008-03-16 100 2008-03-17 100 2008-03-18 100 2008-03-19 100 2008-03-20 100 2008-03-21 100 2008-03-22 110 2008-03-23 100 2008-03-24 100 2008-03-25 100 2008-03-26 100 2008-03-27 100 2008-03-28 100 2008-03-29 100 2008-03-30 100 2008-03-31 100 Name/Title of Responsible I certify under the penalty of law that I have personally examined and am familiar Signature of Date (MM/DD/YY)

Official or Authorized with the information submitted herein and based on my inquiry of those Responsible Official or Representative individuals immediately responsible for obtaining the information, I believe the Authorized ubmitted information is true, accurate and complete. I am aware that there are Representative significant penalties for submitting false information, including the possibility of k[i-M tuo ear fine and imprisonment.

/4 4/

, 0 When completed mail this report to: EDMR Administrator, EDMR Administrator,.,, OH, U

Page 2 https://ebiz.epa.ohio.gov/edwr.web/page/reportlviewWithXslt.do?actType=viewWithXslt&f...

4/2/2008

rag" '-1 UI I I Ohio F

- Daily Discharge Monitoring Report "

irm 4500

'FACILITY:

LOCATION:

COUNTY:

DISTRICT:

FirstEnergy Perry Nuclear Power Pit 10 Center Rd North Perry, 44081 Lake NEDO PERMIT NUMBER:

3IB00016*ID STATION CODE:

094 MONITORING PERIOD:

2008-03-01 To: 2008-03-31 REPORTING LAB:

ANALYST:

NO DISCHARGE INDICATOR:

AL Water Zinc, Total Copper, Total Oxidants, Total Chlorine, Total Temperature Recoverable Recoverable Residual Residual PARAMETER CODE 00011 50050 00400 01094 01119 34044 50060 UNITS 4103 4108 6653 4107 4107 4106 4106 FREQUENCY I/Day I/Day 2/Week l/Mbnth 1/Month When Disch.

When Disch.

SAMPLING TYPE Continuous Continuous Grab Grab Grab Grab Grab 2008-03-01 2008-03-02 2008-03-03 2008-03-04 2008-03-05 2008-03-06 2008-03-07 2008-03-08 2008-03-09 2008-03-10 2008-03-11 2008-03-12 2008-03-13 2008-03-14 2008-03-15 2008-03-16 2008-03-17 2008-03-18 2008-03-19 2008-03-20 2008-03-21 2008-03-22 2008-03-23 2008-03-24 2008 25 2008 26 2008-03-27 2008-03-28 2008-03-29 2008-03-30 2008-03-31 Name/Title of Responsible I certify under the penalty of law that I have personally examined and am familiar Signature of Date (MM/DD/YY)

Official or Authorized with the information submitted herein and based on my inquiry of those Responsible Official or Representative individuals immediately responsible for obtaining the information, I believe the Authorized ubmitted information is true, accurate and complete. I am aware that there are Representative significant penalties for submitting false information, including the possibility of

/',q

./

/1/

VP-o d ea "

fineand imprisonment.

  • /C When completed mail this report to: EDMR Administrator, EDMR Administrator,,, OH, Page 3 https ://ebiz.epa.ohio.gov/edwr.web/page/report/viewWithXslt.do?actType-viewWithXslt&f...

4/2/2008

i o

R 4

Ohio F

- Daily Discharge Momitoring Report!

)rm 4500 rage : ol i FACILITY:

LOCATION:

COUNTY:

DISTRICT:

FirstEnergy Perry Nuclear Power Plt 10 Center Rd North Perry, 44081 Lake NEDO PERMIT NUMBER:

STATION CODE:

MONITORING PERIOD:

REPORTING LAB:

ANALYST:

NO DISCHARGE INDICATOR:

3IB00016*ID 094 2008-03-01 To: 2008-03-31 AL PARAMETER hlorination/Bromination PARAMETER Duration PARAMETER 78739 CODE UNITS 6655 FREQUENCY When Disch.

SAMPLING TYPE Total 2008-03-01 2008-03-02 2008-03-03 2008-03-04 2008-03-05 2008-03-06.

2008-03-07 2008-03-08 2008-03-09 2008-03-10 2008-03-11 2008-03-12 2008-03-13 2008-03-14 2008-03-15 2008-03-16 2008-03-17 2008-03-18 2008-03-19 2008-03-20 2008-03-21 2008-03-22 2008-03-23 2008-03-24 2008-03-25 2008-03-26 2008-03-27 2008-03-28 2008-03-29 2008-03-30 2008-03-31 Name/Title of Responsible I certify under the penalty of law that I have personally examined and am familiar Signature of Date (MM/DD/YY)

Official or Authorized with the information submitted herein and based on my inquiry of those Responsible Official or Representative individuals immediately responsible for obtaining the information, I believe the Authorized submitted information is true, accurate and complete. I am aware that there are Representative

\\IP-k\\

significant penalties fr submitting false information, including the possibility of When completed mail this report to: EDMR Administrator, EDMR Administrator,,, OH,

/

Page 4 https://ebiz.epa.ohio.gov/edwr.web/page/reportlviewWithXslt.do?actType=viewWithXslt&f...

4/2/2008

ragr, I UI 11 Ohio F

- Daily Discharge Monitoring Report/. irm 4500 FACILITY:

LOCATION:

COUNTY:

DISTRICT:

FirstEnergy Perry Nuclear Power Pit 10 Center Rd North Perry, 44081 Lake NEDO PERMIT NUMBER:

STATION CODE:

MONITORING PERIOD:

REPORTING LAB:

ANALYST:

NO DISCHARGE INDICATOR:

3IB00016*ID 601 2008-03-01 To: 2008-03-31 CCB125 Liz Ryan PARAMETER Flow Rate pH Total Suspended Oil and Grease, Solids Total PARAMETER CODE 50050 00400 00530 00550 UNITS 4108 6653 4106 4106 FREQUENCY Continuous 1 /2 Weeks 1 / 2 Weeks 1 / 2 Weeks SAMPLING TYPE 24hr Total Grab Grab Grab 2008-03-01 AH AH AH Ali 2008-03-02

'AH 2008-03-03 AH 2008-03-04 AH 2008-03-05 AH 2008-03-06 AH 2008-03-07 AH 2008-03-08 AH 2008-03-09 AH 2008-03-10 AH 2008-03-11 AH 2008-03-12 AH 2008-03-13 AlH 2008-03-14 AH 2008-03-15 AH

  • 2008-03-16 AH 2008-03-17 AH 2008-03-18 AH 2008-03-19 0.0164 8.52 12 AA5 2008-03-20 All 2008-03-21 AH 2008-03-22 AH 2008-03-23 AH 2008-03-24 AH 2008-03-25 AH 2008-03-26 AH 2008-03-27 AH 2008-03-28 AH 2008 29 AH AH AlE AH 2008-03-30 AH 2008-03-31 AH Name/Title of Responsible I certify under the penalty.of law that I have personally examined and am familiar Signature of Date (MM/DD/YY)"

Official or Authorized with the information submitted herein and based on my inquiry of those Responsible Official or Representative individuals immediately responsible for obtaining the information, I believe the Authorized submitted information is true, accurate and complete. I am aware that there are Representative significant penalties for submitting false information, including the possibility of adit*'//

C a

fine and imprisonment.

f9 I0tf When completed mail this report to: EDMR Administrator, EDMR Administrator,,, OH,

/

Page 5 https://ebiz.epa.ohio.g-ov/edwr.web/page/report/viewWithXslt.do?actType=viewWithXslt&f...

4/2/2008

Ohio E"

- Daily Discharge Monitoring Report; rm 4500

.ra-.; 0 Ui

1.1 FACILITY

LOCATION:

COUNTY:

DISTRICT:

FirstEnergy Perry Nuclear Power Pit 10 Center Rd North Perry, 44081 Lake NEDO PERMIT NUMBER:

3IB00016*ID STATION CODE:

602 MONITORING PERIOD:

2008-03-01 To: 2008-03-31 REPORTING LAB:

ANALYST:

NO DISCHARGE INDICATOR:

AL Total Suspended Oil and Grease, Iron, Total Copper, Total PARAMETER Flow Rate pH Solids Total Recoverable Recoverable PARAMETER CODE 50050 00400 00530 00550 00980 01119 UNITS 4108 6653 4106 4106 4107 4107 FREQUENCY Continuous 1 2 Weeks I / 2 Weeks 1 /2 Weeks I / 2 Weeks I / 2 Weeks SAMPLING TYPE 24hr Total Grab 24hr Composite Grab 24hr Composite 24hr Composite 2008-03-01 2008-03-02 2008-03-03 2008-03-04 2008-03-05 2008-03-06 2008-03-07 2008-03-08 2008-03-09 2008-03-10 2008-03-I1 2008-03-12 2008-03-13 2008-03-14 2008-03-15 2008-03-16 2008-03-17 2008-03-18 2008-03-19 2008 20 2008-03-21 2008-03-22 2008-03-23 2008-03-24 2008-03-25 2008 26 2008-03 -27 2008-03-28 2008 29 2008-03-30 2008-03-31 Name/Title of Responsible I certify under the penalty of law that I have personally examined and am familiar Signature of Date (MM!DD/YY)

Official or Authorized with the information submitted herein and based on my inquiry of those Responsible Official or Representative individuals immediately responsible for obtaining the information, I believe the Authorized submitted information is true, accurate and complete. I am aware that there are Representative significant penalties for submitting false information, including the possibility of L)

When completed mail this report to: EDMR Administrator, EDMR Administrator,,, OH, Page 6 https ://ebiz.epa.ohio.gov/edwr.web/page/report/viewWithXslt.do? actType=viewWithXslt&f...

4/2/2008

Ohio E

- Daily Discharge Monitoring Report,'

irm 4500 r-agrz Y' Ut. II FACILITY:

LOCATION:

COUNTY:

DISTRICT:

FirstEnergy Perry Nuclear Power Pit 10 Center Rd North Perry, 44081 Lake NEDO PERMIT NUMBER:

STATION CODE:

MONITORING PERIOD:

REPORTING LAB:

ANALYST:

NO DISCHARGE INDICATOR:

3IB0001 6*ID 800 2008-03-01 To: 2008-03-31 CCB125 Liz Ryan PARAMETER Water Zinc, Total Copper, Total Temperature Recoverable Recoverable PARAMETER CODE 00011 01094 01119 UNITS 4103 4107 4107 FREQUENCY I/Day 1/Month 1/Month SAMPLING TYPE Continuous Grab Grab 2008-03-01 36 2008-03-02 35 2008-03-03 34 2008-03-04 34 2008-03-05 34 2008-03-06 34 2008-03-07 35 12.1 2.71 2008-03-08 37 2008-03-09 39 2008-03-10 39 2008-03-11 40 2008-03-12 39 2008-03-13 39 2008-03-14 38 2008-03-15 37 2008-03-16 37 2008-03-17 36 2008-03-18 36 2008-03-19 35 2008-03-20 34 2008-03-21 32 2008-03-22 31 2008-03-23 31 2008-03-24 32 2008-03-25 32 2008-03-26 31 2008-03-27 31 2008-03-28 31 2008-03-29 32 2008-03-30 33 2008-03-31 31 Name/Title of Responsible I certify under the penalty of law that I have personally examined and am familiar Signature of Date (MM/DD/YY)

Official or Authorized with the information submitted herein and based on my inquiry of those Responsible Official or Representative individuals immediately responsible for obtaining the information, I believe the Authorized submitted information is true, accurate and complete. I am aware that there are Representative significant penalties for submitting false information, including the possibility of

/

-V w

ci fine and imprisonment.

l1'lI(-

When completed mail this report to: EDMR Administrator, EDMR Administrator... OH,

/

Page 7 https://ebiz.epa.ohio.gov/edwr.web/page/report/viewWithXslt.do?actType=viewWithXslt&f...

4/2/2008

Ohio E

- Daily Discharge Monitoring Report,'

rm 4500 rage IV 01 1 1 FACILITY:

LOCATION:

FirstEnergy Perry Nuclear Power Plt 10 Center Rd North Perry, 44081 PERMIT NUMBER:

3IB00016*ID MONITORING PERIOD:

2008-03-01 To: 2008-03-31 PARAMETER COMMENTS:

Station Code Parameter Name Parameter Code Date Unit Comment 004 Oxidants, Total Residual 34044 2008-03-01 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-02 4106-No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-03 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-04 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-05 4106 No bromination event this date 004 Oxidants, Total Residual.

34044 2008-03-06 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-07 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-08 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-09 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-10 4106 No bromination event this date 004.

Oxidants, Total Residual 34044 2008-03-11 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-12 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-13 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-14 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-15 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-16 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-17 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-18 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-19 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-20 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-21 4106

-No bromination event this date 004 Oxidants, total Residual 34044 2008-03-22 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-23 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-24 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-25 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-26 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-27 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-28 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-29 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-30 4106 No bromination event this date 004 Oxidants, Total Residual 34044 2008-03-31 4106 No bromination event this date 601 Flow Rate 50050 2008-03-01 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-02 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-03 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-04 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-05 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-06 4108 No discharges performed on this date https://ebiz.epa.ohio.gov/edwr.web/page/reportlviewWithXslt.do?actType=viewWithXslt&f...

4/2/2008

Q 50050 2008-03-07 rage i i Ut i i F"

601 Flow Rate 4108 lischarges performed on this date

-~

a i-f--

601 Flow Rate 50050 2008-03-08 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-09 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-10 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-11 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-12 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-13 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-14 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-15 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-16 4108 No discharges performed on this date 601 Flow Rate *50050 2008-03-17 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-18 4108 No discharges performed on this date 601.

Flow Rate 50050 2008-03-19 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-20 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-21 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-22 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-23 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-24 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-25 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-26 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-27 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-28 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-29 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-30 4108 No discharges performed on this date 601 Flow Rate 50050 2008-03-31 4108 No discharges performed on this date 601 pH 00400 2008-03-01 6653 No discharge performed on this date 601 pH 00400 2008-03-29 6653 No discharge performed on this date 601 Total Suspended Solids 00530 2008-03-01 4106 No discharge performed on this date 601 Total Suspended Solids

.00530 2008-03-29 4106 No discharge performed on this date 601 Oil and Grease, Total 00550 2008-03-01 4106 No discharge performed on this date 60i Oil and Grease, Total 00550 2008-03-29 4106 No discharge performed on this date.

https://ebiz.epa.ohio.gov/edwr.web/page/report/viewWithXslt.do?actType=viewWithXslt&f...

4/2/2008