Site-Specific Implementation of B.5.B Phase 2 and 3 Mitigating Strategies Draft Temporary Instruction Inspection (NRC IR 05000397-08-006)
ML080880426
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 03/27/2008
From: Ryan Lantz
Operations Branch IV
To: Parrish J
Energy Northwest
References
IR-08-006
Download: ML080880426 (3)


See also: IR 05000397/2008006

Text

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

March 27, 2008

J. V. Parrish (Mail Drop 1023)

Chief Executive Officer

Energy Northwest

P.O. Box 968

Richland, WA 99352-0968

SUBJECT:

COLUMBIA GENERATING STATION - SITE-SPECIFIC IMPLEMENTATION

OF B.5.B PHASE 2 AND 3 MITIGATING STRATEGIES DRAFT

TEMPORARY INSTRUCTION INSPECTION (NRC INSPECTION

REPORT 05000397/2008006)

Dear Mr. Parrish:

In a telephone conversation on March 5, 2008, Messrs. Fred Schill and John Kirkland made

arrangements for the NRC to inspect the site-specific implementation of B.5.b Phase 2 and 3

mitigating strategies at the Columbia Generating Station. The inspection is planned for the

week of May 5, 2008.

In order for the NRC to adequately prepare for this inspection, please furnish the documents

listed in Enclosure 1 to Mr. John Kirkland in electronic format, if possible, at least two weeks

prior to the planned inspection. Please have available on site at the beginning of the inspection

the arrangements and documents listed in Enclosure 2. Mr. Fred Schill has been advised of this

request and provided with the name and address of the NRC lead inspector and the Office of

Nuclear Reactor Regulation inspector assigned to this inspection.

This letter contains information collections that are subject to the Paperwork Reduction Act of

1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of

Management and Budget, approval number 3150-0018, which expires on June 30, 2009.

The public reporting burden for this collection of information is estimated to average 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per

response, including the time for reviewing instructions, gathering and maintaining the data

needed, and completing and reviewing the collection of information. Send comments on any

UNITED STATES

NUCLEAR REGULATORY COMMISSION

R E GI ON I V

611 RYAN PLAZA DRIV E, SUITE 400

ARLINGTON, TEXAS 76011-4005

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

- 2 -

Enclosure 2

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

aspect of this collection of information, including suggestions for reducing the burden, to the

Information and Records Management Branch (T-5 F53), U.S. Nuclear Regulatory Commission,

Washington, D.C. 20555-0001, or by Internet electronic mail at BJS1@NRC.GOV; and to the

Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of

Management and Budget, Washington, D.C. 20503-0001.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be

available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records System (PARS) component of NRC's Agencywide Documents

Access and Management System (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). However,

because of the sensitive information contained in the enclosures, and in accordance with

10 CFR 2.390, a copy of this letters enclosures will not be available for public inspection.

Thank you for your cooperation in this matter. If you have any questions regarding this

inspection, please contact John Kirkland at 402-426-9611, or me at 817 860-8159.

Sincerely,

/RA/

Ryan E. Lantz, Chief

Operations Branch

Division of Reactor Safety

Docket: 50-397

License: NPF-21

Enclosures:

1.

Documentation Requested

Prior To the Inspection

2.

Arrangements/Documents Requested

To Be Available Onsite during the

Inspection Week

cc w/enclosure:

Mr. Fred Schill

Energy Northwest

P.O. Box 968

Richland, WA 99352-0968

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

Energy Northwest

- - 2 - -

OFFICIAL USE ONLY - SECURITY-RELATED INFORMATION

cc w/o enclosure:

Douglas W. Coleman (Mail Drop PE20)

Manager, Regulatory Programs

Energy Northwest

P.O. Box 968

Richland, WA 99352-0968