Jeffrey B. Archie Vice President, Nuclear Operations 803.345.4214 March 18, 2008 A SCANA COMPANY U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Dear Sir / Madam:

Subject:

VIRGIL C. SUMMER NUCLEAR STATION (VCSNS)DOCKET NO. 50/395 OPERATING LICENSE NO. NPF-12 IDENTIFICATION OF COMMITMENT IN SUPPLEMENTAL RESPONSE TO NRC GENERIC LETTER 2004-02: POTENTIAL IMPACT OF DEBRIS BLOCKAGE ON EMERGENCY RECIRCULATION DURING DESIGN BASIS ACCIDENTS AT PRESSURIZED-WATER REACTORS

Reference:

J. B. Archie to Document Control Desk, Supplemental Response to NRC Generic Letter 2004-02 dated February 29, 2008, RC-08-0031 The referenced document provided South Carolina Electric & Gas Company's (SCE&G's)supplemental response to Generic Letter (GL) 2004-02 on February 29, 2008. The statement in the referenced letter that there were no regulatory commitments did not reflect the intention of SCE&G to apply for Alternate Source Term (AST), as stated on page 75 of the attached response.In Section 3p of the attachment to the February 29, 2008 submittal, SCE&G stated its intention to submit an application for AST. SCE&G has determined that the projected licensing submittal for AST should have been identified as a regulatory commitment in the referenced letter.Therefore, SCE&G is submitting this letter to identify one regulatory commitment due to GL 2004-02 response.

There are no changes associated with the attachment to the February 29, 2008 response to GL 2004-02.Should you have questions, please call Mr. Bruce Thompson at (803) 931-5042.I certify under penalty of perjury that the foregoing is true and correct.Executed on JT/J BA/cm c: K. B. Marsh S. A. Byrne N. S. Cams J. H. Hamilton R. J. White V. M. McCree R. E. Martin AcePresident, Nuclear Operations NRC Resident Inspector K. M. Sutton NSRC RTS (CR-04-02911, CR-08-00854)