March 11, 2008 Mr. Joseph H. Plona, Assistant Vice President, Nuclear Generation DTE Energy 6400 North Dixie Hwy Newport, MI 48166
SUBJECT:
REPORT OF MARCH 5, 2008 CATEGORY 1 MEETING, FERMI-1, DOCKET 050-00016 (TAC J00334)
Dear Mr. Plona:
Enclosed is the meeting report for the above referenced meeting. I would like to thank you and your staff for providing an update on the status of the Fermi-1 reactor.
If you have any questions regarding this letter or the enclosure, please contact me at (301) 415-6721, or by e-mail, to tbs1@nrc.gov.
In accordance with 10 CFR 2.390 of the U.S. Nuclear Regulatory Commissions (NRC=s) ARules of Practice for Domestic Licensing Proceedings and Issuance of Orders,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC=s Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
Sincerely,
/RA/
Theodore Smith, Project Manager Reactor Decommissioning Branch Decommissioning and Uranium Recovery Licensing Directorate Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs Docket No.: 050-00016
Enclosure:
Meeting Report
March 11, 2008 Mr. Joseph H. Plona, Assistant Vice President, Nuclear Generation DTE Energy 6400 North Dixie Hwy Newport, MI 48166
SUBJECT:
REPORT OF MARCH 5, 2008 CATEGORY 2 MEETING, FERMI-1, DOCKET 050-00016 (TAC J00334)
Dear Mr. Plona:
Enclosed is the meeting report for the above referenced meeting. I would like to thank you and your staff for providing an update on the status of the Fermi-1 reactor.
If you have any questions regarding this letter or the enclosure, please contact me at (301) 415-6721, or by e-mail, to tbs1@nrc.gov.
In accordance with 10 CFR 2.390 of the U.S. Nuclear Regulatory Commissions (NRC=s) ARules of Practice for Domestic Licensing Proceedings and Issuance of Orders,@ a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC=s Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.
Sincerely,
/RA/
Theodore Smith, Project Manager Reactor Decommissioning Branch Decommissioning and Uranium Recovery Licensing Directorate Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs Docket No.: 050-00016
Enclosure:
Meeting Report Distribution:
HFelsher KMcConnell DOrlando RidsRgn3MailCenter Meeting Attendees via E-mail ML080700192 Office DWMEP DWMEP DWMEP Name TSmith TMixon APersinko Date 3/6/08 3/11/08 3/1108 OFFICIAL RECORD COPY
Enclosure MEETING REPORT DATE:
March 5, 2008 TIME:
2:00 p.m. Eastern PLACE:
Two White Flint North, Room T-8C1 U.S. Nuclear Regulatory Commission Headquarters Rockville, Maryland PURPOSE:
To discuss license termination and site decommissioning plans for the Fermi-1 reactor.
ATTENDEES:
SEE ATTACHED LIST BACKGROUND:
The Fermi-1 reactor is located at Lagoona Beach, Frenchtown Township, Michigan. The reactor was shutdown in 1972. DTE Energy has been stabilizing the facility by passivating residual sodium and disposing of plant components and systems. DTE Energy is currently planning to submit a license termination plan in mid-2009, and terminate their license in 2012.
DISCUSSION:
The meeting was publicly noticed on February 12, 2008, by posting on the U.S. Nuclear Regulatory Commission web site. The meeting began at approximately 2:00 p.m. EST. The following issues were discussed during the meeting:
- 1.
NRC (Ted Smith) made introductions and an opening statement, including opportunity to provide meeting feedback utilizing NRC Form 659, which was provided.
- 2.
DTE Energy (Lynne Goodman and Martin Erickson) presented a history of the site, described recent activities at the site, and their conceptual approach for license termination planning.
- a. DTE indicated current plans for decommissioning will leave Fermi-1 buildings in place after license termination under unrestricted release.
- 3. DTE Energy then discussed license termination planning communications, and project schedule and cost.
- a. Between trust funds and guarantees, DTE has sufficient funds to cover the estimated decommissioning costs.
ACTION ITEMS:
NRC agreed to evaluate the relationship between Fermi-2 license termination evaluations for residual radioactivity remaining onsite from a terminated Fermi-1 license.
Enclosure NRC and DTE agreed to a meeting and conference call schedule based on site activities, and reaching key planning milestones.
Attachments:
- 1. Meeting Agenda
- 2. Attendee List
- 3. DTE Energy Meeting Handout
ATTACHMENT 1
AGENDA Public Meeting - NRC & Fermi-1 Status Report on License Termination Planning and Reactor Vessel Classification Date Time Wednesday March 5, 2008 2:00 p.m. - 4:00 p.m.
Session Time Topic Participants 2:00 p.m.
Introductions, clarification of Aground rules@
concerning public portion of meeting and opening remarks NRC/Fermi-1 2:15 p.m.
Fermi-1 staff presentation regarding License Termination Planning, communication protocols, planning approach and schedule Fermi-1 3:45 p.m.
Opportunity for public comment NRC/Public 4:00 p.m.
Adjournment
ATTACHMENT 2
MEETING ATTENDEES Date: March 5, 2008 Topic: Fermi-1 License Termination Planning NAME AFFILIATION Lynne Goodman DTE Martin Erickson DTE Ken Lindsey DTE Ted Smith NRC/FSME Karen Pinkston NRC/FSME Christepher McKenney NRC/FSME Cynthia Barr NRC/FSME Bruce Watson NRC/FSME Andrew Persinko NRC/FSME Keith MCConnell NRC/FSME