Request for Information Containment Sump Inspection
ML080630150
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 03/03/2008
From: Ann Marie Stone
NRC/RGN-III/DRS/EB2
To: Christian D
Virginia Electric & Power Co (VEPCO)
References
IR-08-002
Download: ML080630150 (4)


Text

March 3, 2008 Mr. David A. Christian President and Chief Nuclear Officer Virginia Electric and Power Company Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

SUBJECT:

KEWAUNEE POWER STATION REQUEST FOR INFORMATION NRC INSPECTION ASSOCIATED WITH CONTAINMENT SUMP 05000305/2008002(DRS)

Dear Mr. Christian:

On March 24, 2008, the NRC will begin an inspection at the Kewaunee Power Station. One inspector will perform this 1-week inspection in accordance with NRC Temporary Instruction (TI) 2525/166, Pressurized Water Reactor Containment Sump Blockage. This inspection focuses on commitments made by Kewaunee Power Station in response to Generic Letter (GL) 2004-02, Potential Impact of Debris Blockage on Emergency Sump Recirculation at Pressurized Water Reactors (PWRs).

In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for documents needed for the inspection. These documents have been divided into two groups. The first group is required prior to the inspection to ensure that the inspector is adequately prepared. This information should be provided to the Regional Office no later than March 17, 2008.

The second group of requested documents contains additional items that the inspector will review, or need access to, during the inspection, and should be available by the first day of the on-site inspection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection.

The inspector for this inspection is Ronald Langstaff. If there are any questions about the inspection or the material requested, please contact the inspector at (630) 829-9747 or via e-mail at RAL4@nrc.gov.

D. Christian In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 50-305 License Nos. DPR-43

Enclosure:

INFORMATION REQUEST FOR GENERIC NUCLEAR POWER PLANT TEMPORARY INSTRUCTION (TI) 2525/166 INSPECTION cc w/encl: S. Scace, Site Vice President T. Webb, Director, Nuclear Safety and Licensing C. Funderburk, Director, Nuclear Licensing and Operations Support T. Breene, Manager, Nuclear Licensing L. Cuoco, Esq., Senior Counsel D. Zellner, Chairman, Town of Carlton J. Kitsembel, Public Service Commission of Wisconsin P. Schmidt, State Liaison Officer, State of Wisconsin

D. Christian In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely, Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 50-305 License Nos. DPR-43

Enclosure:

INFORMATION REQUEST FOR GENERIC NUCLEAR POWER PLANT TEMPORARY INSTRUCTION (TI) 2525/166 INSPECTION cc w/encl: S. Scace, Site Vice President T. Webb, Director, Nuclear Safety and Licensing C. Funderburk, Director, Nuclear Licensing and Operations Support T. Breene, Manager, Nuclear Licensing L. Cuoco, Esq., Senior Counsel D. Zellner, Chairman, Town of Carlton J. Kitsembel, Public Service Commission of Wisconsin P. Schmidt, State Liaison Officer, State of Wisconsin DISTRIBUTION:

DXC1 TEB PDM RidsNrrDirsIrib MAS KGO JKH3 SXB3 CAA1 DRPIII DRSIII PLB1 TXN ROPreports@nrc.gov DOCUMENT NAME: G:\DRS\Work in Progress\Ltr 02__08 Kewaunee Generic TI RFI NAF.doc 9 Publicly Available 9 Non-Publicly Available 9 Sensitive 9 Non-Sensitive To receive a copy of this document, indicate in the concurrence box C = Copy without attach/encl; E = Copy with attach/encl N = No copy OFFICE RIII RIII RIII RIII NAME RLangstaff: ls AMStone DATE 03/03/08 03/03/08 OFFICIAL RECORD COPY

INFORMATION REQUEST FOR GENERIC NUCLEAR POWER PLANT TEMPORARY INSTRUCTION (TI) 2525/166 INSPECTION Inspection Report: 05000305/2008002(DRS)

Inspection Dates: March 24, 2008 - March 28, 2008 Inspection Procedures: TI 2525/166, Pressurized Water Reactor Containment Sump Blockage IP 71111.17, Changes, Tests, or Experiments, and Permanent Plant Modifications (reference)

Inspector: Ronald Langstaff, Reactor Inspector (630) 829-9747 (RAL4@nrc.gov)

I. Information Requested for Our In-office Preparation Week The following information is requested by March 17, 2008, or sooner, to facilitate inspection preparation. If you have any questions regarding this information, please call the inspector as soon as possible. (Please provide the information electronically in pdf files, Excel, or other searchable formats, preferably on CDROM. The CDROM should contain descriptive names to facilitate ease of use.)

1. A list of all correspondences to/from the site related to GL 2004-02. This list should include the addressor, addressee, subject matter, and date of correspondence.
2. A list of modifications, procedure changes or other commitments made in response to GL 2004-02 as documented in the Item 1 responses. (For the purpose of this inspection, modifications include permanent plant changes, design changes, set point changes, equivalency evaluations, suitability analyses, and commercial grade dedications.)
3. Name(s) and phone numbers for the regulatory and technical contacts.

II. Information Requested to be Available on First Day of Inspection (March 24, 2008)

1. Copies of the modifications and procedure changes made in response to GL 2004-02 or committed to in the documents from Item I. Modification documents should include a design description, records showing date of completion and 10 CFR 50.59 applicability determination, screening, or evaluation.

1 Enclosure

INFORMATION REQUEST FOR GENERIC NUCLEAR POWER PLANT TEMPORARY INSTRUCTION (TI) 2525/166 INSPECTION

2. Please ensure that other supporting documents for the selected items have been located and are readily retrievable as the inspector will likely be requesting these documents during the inspections. Examples of supporting documents are:
a. Drawings supporting the modifications;
b. Calculations related to the modifications;
c. Procedures affected by the modifications; and
d. UFSAR change papers generated due to a 10 CFR 50.59 evaluation.
3. List of related calculation changes that have been issued for use.
4. List of any related corrective action documents (open and closed).
5. Copies of procedures addressing the following: modifications, design changes, set point changes, equivalency evaluations or suitability analyses, commercial grade dedications, post-modification testing, 10 CFR 50.59 evaluation and screenings, and UFSAR updates.
6. Copy of the UFSAR change log (or a synopsis of changes). This should include all of the changes made to the UFSAR that were incorporated in the last 10 CFR 50.71(e)(4) submittal and any approved changes to the current UFSAR.

If you have questions regarding the information requested, please contact the lead inspector.