Text
Committed to Nuclear Excellence /
Nuclear Management Company, LLC January 15,2008 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Prairie Island Nuclear Generating Plant Monticello Nuclear Generating Plant Units I and 2 Docket No. 50-263 Dockets 50-282 and 50-306 License No. DPR-22 License Nos. DPR-42 and DPR-60 Generic Letter 2003-01. "Control Room Habitability", Commitment Change
References:
I )
NRC Issuance of Generic Letter 2003-01, Control Room Habitability, dated June 12, 2003.
- 2)
NMC to NRC, Generic Letter 2003-01, Design Bases, Licensing Bases and In-leakage Testing Results for Monticello Nuclear Generating Plant, dated November 18,2004.
- 3)
NMC to NRC, Response to Generic Letter 2003-01, "Control Room Habitability" for Prairie Island Nuclear Generating Plant.
- 4)
NMC to NRC letter, Generic Letter 2003-01, "Control Room Habitability", Commitment Change, dated July 3, 2007.
- 5)
NMC to NRC letter, Generic Letter 2003-01, "Control Room Habitability", Commitment Change, dated November 14, 2007.
On June 12,2003, the U.S. Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 2003-01, "Control Room Habitability," requesting information on this subject (Reference 1). In response to this NRC request, NMC submitted the requested information for Monticello Nuclear Generating Plant (MNGP) on November 18, 2004 (L-MT-4-049) (Reference 2) and for Prairie Island Nuclear Generating Plant (PINGP) on December 9,2003 (L-PI-03-114) (Reference 3). As part of these responses, NMC committed to submit corresponding Technical Specification (TS) changes to incorporate a Control Room Integrity Program within 180 days from the NRC issuance of TSTF-448 for adoption. On July 3,2007 and on November 14,2007 (References 4 and 5 respectively) NMC notified the NRC of commitment changes to submit TSTF-448 related TS changes for PINGP and MNGP.
Due to several current activities related to the reorganization and restructuring of the operation of the NMC plants, NMC is notifying the NRC staff of a revised commitment date for the respective license amendment requests (LAR) submittals for PINGP and MNGP. The revised commitment is to submit the TSTF-448 related LARS following the guidance of the consolidated line item improvement process (CLIIP) by April 6,2008.
This change in commitment has been discussed with the respective NRR Project Managers.
700 First Street Hudson, Wisconsin 54016 Telephone: 715.377.3300
Document Control Desk Page 2 Summary of Commitments This letter contains one revised commitment for MNGP and PINGP.
"The revised commitment is to submit the TSTF-448, Revision 3 related LARS following the guidance of the CLIIP by April 6, 2008".
Sincerely, Affairs and Emergency Planning Company, LLC cc:
Regional Administrator, USNRC Region Ill Project Manager, Prairie Island Nuclear Generating Plant, USNRC, NRR Resident Inspector, Prairie Island Nuclear Generating Plant, USNRC Project Manager, Monticello Nuclear Generating Plant, USNRC, NRR Resident Inspector, Monticello Nuclear Generating Plant, USNRC