Catherine P. Mccarthy, Ltr Indirect License Transfer of Nuclear Regulatory Commission License Nos. DPR-3, SFGL-13, DPR-36, SFGL-14, DPR-61 and SFGL-16ML080140289 |
Person / Time |
---|
Site: |
Haddam Neck, Yankee Rowe, Maine Yankee |
---|
Issue date: |
02/21/2008 |
---|
From: |
Chang L NRC/FSME/DWMEP/DURLD/SPB |
---|
To: |
Mccarthy C LeBoeuf, Lamb, Greene, & MacRae, LLP |
---|
Kenneth Kline |
References |
---|
Download: ML080140289 (4) |
|
|
---|
Category:Letter
MONTHYEARIR 05000213/20240012024-08-27027 August 2024 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation NRC Inspection Report Nos. 07200039/2024001 and 05000213/2024001 IR 05000309/20240012024-06-26026 June 2024 Company – Independent Spent Fuel Storage Installation NRC Inspection Reports 07200030/2024001 And05000309/2024001 ML24094A0742024-05-30030 May 2024 Issuance of Exemption for Connecticut Yankee Atomic Power Company Regarding Haddam Neck Plant Independent Spent Fuel Storage Installation ML24124A1372024-04-30030 April 2024 Independent Spent Fuel Storage Installation - 2023 Individual Monitoring NRC Form 5 Report ML24117A0602024-04-23023 April 2024 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2023 ML24094A0602024-03-28028 March 2024 Independent Spent Fuel Storage Installation, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for the Maine Yankee Independent Spent Fuel Storage Installation ML24074A3812024-03-11011 March 2024 Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report ML24074A3822024-03-11011 March 2024 Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML24085A2192024-03-11011 March 2024 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML24085A2222024-03-11011 March 2024 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste NG-24-0001, 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update2024-03-0606 March 2024 2024 Annual Decommissioning and Spent Fuel Management Funding Status Report and Independent Spent Fuel Storage Installation (ISFSI) Decommissioning Financial Assurance Update ML24047A0552024-01-15015 January 2024 Independent Spent Fuel Storage Installation, Formal Announcement of Change in ISFSI Manager ML24025A0392024-01-12012 January 2024 Independent Spent Fuel Storage Installation, Property Insurance Coverage ML24057A0212024-01-12012 January 2024 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation - Nuclear Liability Insurance Coverage ML23342A0972024-01-0909 January 2024 Connecticut Yankee Atomic Power Company - Independent Spent Fuel Storage Installation Security Inspection Plan ML23342A1112024-01-0909 January 2024 Company - Independent Spent Fuel Storage Installation Security Inspection Plan CY-23-014, Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI2023-12-0404 December 2023 Biennial Update of the CYAPCO Quality Assurance Program for the Haddam Neck ISFSI IR 07200031/20234012023-10-0404 October 2023 Yankee Atomic Electric Company - Independent Spent Fuel Storage Security Inspection Report 07200031/2023401 ML23157A1012023-05-0404 May 2023 Request for Exemption from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(2) for the Yankee Nuclear Power Station Independent Spent Fuel Storage Installation ML23117A0452023-04-25025 April 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2022 ML23130A1562023-04-24024 April 2023 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2022 ML23124A2012023-04-20020 April 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 2022 ML23113A0052023-03-31031 March 2023 Request for Exemption from 10 CFR 50.82 10 CFR 50.75 for the Maine Yankee Independent Spent Fuel Storage Installation NG-23-0001, 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report2023-03-27027 March 2023 2023 Annual Decommissioning and Spent Fuel Management Funding Status Report CY-23-006, Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report2023-03-0606 March 2023 Independent Spent Fuel Storage Installation - Decommissioning Funding Assurance Status Report ML23068A0132023-03-0606 March 2023 Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML23080A1112023-03-0606 March 2023 Yankee Nuclear Power Plant Independent Spent Fuel Storage Installation, Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML23080A1072023-03-0606 March 2023 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Decommissioning Funding Assurance Status Report CY-23-007, Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste2023-03-0606 March 2023 Independent Spent Fuel Storage Installation - Funding Status Report for Managing Irradiated Fuel and GTCC Waste ML22340A4622023-02-24024 February 2023 Closeout Letter to Maine Yankee Atomic Power Company Regarding 2018 and 2021 Updated DFPs for Maine Yankee ISFSI ML22340A4752023-02-24024 February 2023 Closeout Letter to Yankee Atomic Electric Company Regarding 2018 and 2021 Updated DFPs for Yankee Nuclear Power Station ISFSI ML22340A4922023-02-24024 February 2023 Closeout Letter to Connecticut Yankee Regarding 2018 and 2021 Updated DFPs for Haddam Neck Plant ISFSI IR 07200030/20234012023-01-26026 January 2023 Company - NRC Independent Spent Fuel Storage Security Inspection Report No. 07200030/2023401 (Letter Only) ML23026A0802023-01-17017 January 2023 Company - Property Insurance Coverage CY-23-004, Independent Spent Fuel Storage Installation, Property Insurance Coverage2023-01-17017 January 2023 Independent Spent Fuel Storage Installation, Property Insurance Coverage CY-23-003, Independent Spent Fuel Storage Installation, Nuclear Liability Insurance Coverage2023-01-17017 January 2023 Independent Spent Fuel Storage Installation, Nuclear Liability Insurance Coverage CY-23-002, Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments2023-01-0505 January 2023 Independent Spent Fuel Storage Installation, Report of 10 CFR 72.48 Changes, Tests, and Experiments ML23041A1122023-01-0505 January 2023 Independent Spent Fuel Storage Installation, 10 CFR 50.59 Changes, Tests, and Experiments Report ML23041A1132023-01-0505 January 2023 Yankee Atomic Electric Company - Report of 10 CFR 72.48 Changes, Tests, and Experiments CY-23-001, Independent Spent Fuel Storage Installation, Report of 10 CFR 50.59 Changes, Tests, and Experiments2023-01-0505 January 2023 Independent Spent Fuel Storage Installation, Report of 10 CFR 50.59 Changes, Tests, and Experiments ML22347A2802022-12-21021 December 2022 Yankee Atomic Electric Company - Independent Spent Fuel Storage Installation Security Inspection Plan Dated December 21, 2022 IR 07200030/20224012022-10-11011 October 2022 Company - NRC Independent Spent Fuel Storage Security Inspection Report No. 07200030/2022401 IR 07200039/20224012022-10-0505 October 2022 Connecticut Yankee Atomic Power Company - NRC Independent Spent Fuel Storage Security Inspection Report No. 07200039/2022401 CY-22-012, Independent Spent Fuel Storage Installation, Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan2022-08-0303 August 2022 Independent Spent Fuel Storage Installation, Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML22237A0632022-08-0303 August 2022 Yankee Atomic Electric Company - Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan ML22216A0682022-07-28028 July 2022 Independent Spent Fuel Storage Installation, Supplemental Information for the Three-Year Update to the Independent Spent Fuel Storage Installation Decommissioning Funding Plan CY-22-010, Connecticut Yankee Atomic Power Company Haddam Neck Plant Independent Spent Fuel Storage Installation, Formal Announcement of New ISFSI Manager2022-05-25025 May 2022 Connecticut Yankee Atomic Power Company Haddam Neck Plant Independent Spent Fuel Storage Installation, Formal Announcement of New ISFSI Manager ML22136A1562022-04-28028 April 2022 Yankee Nuclear Power Station Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Off-Site Dose Calculation Manual for 2021 CY-22-006, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 20212022-04-25025 April 2022 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report, Annual Radiological Environmental Operating Report, and Changes to the Offsite Dose Calculation Manual for 2021 ML22119A2112022-04-18018 April 2022 Independent Spent Fuel Storage Installation - Yankee Atomic Electric Company Adoption of NAC-MPC System, Amendment 8 Certificate of Compliance and Canister Registration 2024-08-27
[Table view] |
Text
February 21, 2008 Catherine P. McCarthy LeBoeuf, Lamb, Greene and MacRae, L.L.P.
1101 New York Avenue, NW Suite 1100 Washington, DC 20005-4213700
SUBJECT:
INDIRECT LICENSE TRANSFER OF U. S. NUCLEAR REGULATORY COMMISSION LICENSE NOS.: DPR-3, SFGL-13, DPR-36, SFGL-14, DPR-61 AND SFGL-16
Dear Ms. McCarthy:
This is in regard to Mr. Behrends letter dated August 7, 2007, on behalf of Energy East Corporation, requesting to the extent necessary, the consent of the U.S. Nuclear Regulatory Commission (NRC) under Section 50.80 of Title 10 of the Code of Federal Regulations (10 CFR) to the indirect transfer of the licenses for Maine Yankee Atomic Power Company, Yankee Atomic Electric Company and Connecticut Yankee Atomic Power Company (collectively the Yankee Companies). The request for the license transfer approvals is related to the pending merger of a wholly-owned subsidiary of IBERDROLA, S.A., with and into Energy East, with Energy East being the surviving corporation.
The NRC staff has done a threshold review of the facts and circumstances set forth in your letter, and has considered how the merger will be implemented. The staff concluded that no NRC approval for the indirect license transfers are required under 10 CFR 50.80 with respect to the subject licensees.
C. McCarthy 2 This letter documents the conclusion of NRC activities related to the indirect license transfer requests for the subject plants.
Sincerely,
/RA/
Lydia W. Chang, Branch Chief Special Projects Branch Decommissioning and Uranium Recovery Licensing Directorate Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs License Nos.:
DPR-3, SFGL-13, DPR-36, SFGL-14, DPR-61, SFGL-16 cc:
M. Douglas Dunn Milbank, Tweed, Hadley & McCloy LLP 1 Chase Manhattan Plaza New York, NY 10005 Steven M. Kramer Milbank, Tweed, Hadley & McCloy LLP 1 Chase Manhattan Plaza New York, NY 10005
C. McCarthy 2 This letter documents the conclusion of NRC activities related to the indirect license transfer requests for the subject plants.
Sincerely,
/RA/
Lydia W. Chang, Branch Chief Special Projects Branch Decommissioning and Uranium Recovery Licensing Directorate Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs License Nos.:
DPR-3, SFGL-13, DPR-36, SFGL-14, DPR-61, SFGL-16 cc:
M. Douglas Dunn Milbank, Tweed, Hadley & McCloy LLP 1 Chase Manhattan Plaza New York, NY 10005 Steven M. Kramer Milbank, Tweed, Hadley & McCloy LLP 1 Chase Manhattan Plaza New York, NY 10005 DISTRIBUTION:
S. Hom ML080140289 OFFICE DURLD DURLD OGC DURLD NAME K. Kline TSmith S. Uttal L. Chang DATE 1/6/08 1/23/08 02/09/08 2/21/08 OFFICIAL RECORD COPY