Revision of Schedule for the Conduct of Review of the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application
ML080110291
Person / Time
Site: Susquehanna  
(DPR-014, DPR-022)
Issue date: 01/22/2008
From: Gettys E
NRC/NRR/ADRO/DLR
To: Mckinney B
Susquehanna
Gettys Evelyn, NRR/DLR/RLRA 415-4029
References
Download: ML080110291 (6)


Text

January 22, 2008 Mr. Britt T. McKinney Sr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION

Dear Mr. McKinney:

Enclosed is a revised schedule for the review of the Susquehanna Steam Electric Station, Units 1 and 2, license renewal application. This schedule has been revised to reflect changes in the dates for the safety audits, the inspections, and the draft Supplemental Environmental Impact Statement. If you have any questions on the revised schedule, please contact me by telephone at 301-415-4029 or via e-mail at ehg2@nrc.gov.

Sincerely,

/RA/

Evelyn Gettys, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388

Enclosure:

As stated cc w/encl: See next page

ML080110291 OFFICE PM:RPB1:DLR LA:DLR BC:RPB1:DLR BC:RPB1:DLR NAME EGettys IKing DStuyvenberg LLund DATE 01/14/08 1/14/08 1/14/08 1/22/08

SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REVISION OF SCHEDULE Milestone Schedule Actual Receive license renewal application (LRA) 09/15/06 09/13/06 Publish Federal Register Notice (FRN) - LRA receipt and availability 09/25/06 09/26/06 Publish FRN - LRA acceptability, environmental scoping period, and opportunity for hearing 10/30/06 10/30/06 Public Meeting - license renewal process and environmental scoping 11/15/06 11/15/06 Audit - scoping and screening methodology 12/11-15/06 12/11-15/06 Environmental scoping periods ends 01/02/07 01/02/07 Audit - aging management programs (AMPs)

TBD Audit - environmental 05/14-18/07 05/15-17/07 Audit - aging management reviews (AMRs)

TBD Audit (optional)

TBD Issue environmental requests for additional information (RAIs) 07/13/07 07/13/07 Issue safety RAIs TBD Receive responses for environmental RAIs 08/13/07 08/01/2007 Receive responses for safety RAIs TBD Inspection - scoping, screening, and AMPs TBD Inspection (optional)

TBD Issue draft supplemental environmental impact statement (SEIS)

TBD Publish FRN - availability and comment on draft SEIS TBD Public Meeting - draft SEIS TBD Issue safety evaluation report (SER) with open item(s)

TBD End of comment period for the draft SEIS TBD Advisory Committee on Reactor Safeguards (ACRS) subcommittee meeting on SER with open item(s)

TBD Receive responses related to the SER with open item(s)

TBD Issue Regional Administrator's letter TBD Issue final SEIS TBD Issue SER TBD Publish FRN - availability of final SEIS TBD ACRS full committee meeting on SER TBD Issue ACRS letter TBD Issue staff recommendation to NRRs Director TBD NRR decision (license issued, if approved and no hearing is granted -

22 th )

TBD Commission decision (if hearing is granted - 30 months)

TBD ENCLOSURE

Letter to B. McKinney from E. Gettys, dated January 22, 2008

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC SSmith (srs3)

SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSrxb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter YDiaz RGuzman BRogers EGettys

Susquehanna Steam Electric Station, Units 1 and 2 cc:

Cornelius J. Gannon Vice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467 Robert M. Paley General Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467 Rocco R. Sgarro Manager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Supervisor - Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Michael H. Crowthers Supervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Ronald E. Smith General Manager - Site Preparedness and Services PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Manager - Quality Assurance PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467 Luis A. Ramos Community Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467 Bryan A. Snapp, Esq.

Associate General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179 Supervisor - Document Control Services PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Richard W. Osborne Allegheny Electric Cooperative, Inc.

212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266 Director, Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4 Berwick, PA 18603-0035 Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406

Susquehanna Steam Electric Station, Units 1 and 2 cc:

Board of Supervisors Salem Township P.O. Box 405 Berwick, PA 18603-0035