Summary of Meeting Between NRC and Nuclear Management Company to Discuss Proposed Combined Emergency Plan for Monticello and Prairie Island
ML080090567
Person / Time
Site: Monticello, Prairie Island  Xcel Energy icon.png
Issue date: 01/23/2008
From: Tam P
NRC/NRR/ADRO/DORL/LPLIII-1
To:
Tam P NRR/415-1451
Shared Package
ML080230 List:
References
TAC MD6294, TAC MD6295, TAC MD6296
Download: ML080090567 (6)


Text

January 23, 2008 LICENSEE: Nuclear Management Company FACILITIES: Monticello Nuclear Generating Plant Prairie Island Nuclear Generating Plant, Units 1 and 2

SUBJECT:

SUMMARY

OF THE JANUARY 9, 2008, MEETING WITH NUCLEAR MANAGEMENT COMPANY TO DISCUSS THE PROPOSED COMBINED EMERGENCY PLAN (TAC NOS. MD6294, MD6295, AND MD6296)

On January 9, 2008, the Nuclear Regulatory Commission (NRC) staff held a Category 1 public meeting with representatives of Nuclear Management Company (NMC) at NRC offices located at 11555 Rockville Pike, Rockville, Maryland. The licensee requested this meeting to discuss with the NRC staff the appropriate, efficient, and timely licensing process within the existing regulatory framework for review and approval of the proposed combined emergency plan (see NMC letter to the NRC, dated August 7, 2007; Agencywide Document Access and Management System (ADAMS) Accession No. ML072200142). A list of attendees is provided as Enclosure 1.

The licensee=s handout material has been docketed and is publicly available at ADAMS Accession No. ML080090524. Licensee personnel followed the handout in their presentation of the issues.

After a caucus, the NRC staff informed NMC that it will review NMCs August 7, 2007, submittal as one that involves a decrease in effectiveness. A provision of 10 CFR 50.54(q) states, in part, [p]roposed changes that decrease the effectiveness of the approved emergency plans may not be implemented without application to and approval by the Commission. Accordingly, the NRC staff will issue a Request for Additional Information when it can specifically identify its need for additional information. The NRC staff indicated that a review of this type cannot be accommodated within the schedule (i.e., complete by August 7, 2008) proposed by NMC. NMC personnel indicated, without giving specifics, that the NRC review can go beyond August 7, 2008, without a significant impact on the activities for Monticello and Prairie Island.

The NRC staff and NMC personnel agreed to work closely to develop the review schedule, and to hold additional future meetings as the need arises to discuss specific issues.

Before the meeting adjourned, members of the public were given the opportunity to communicate with the NRC staff both verbally and through the use of public meeting feedback forms. No comment or feedback was received at this time.

Please direct any inquiries to the undersigned at 301-415-1451, or pst@nrc.gov.

/RA/

Peter S. Tam, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-263, 50-282, 50-306

Enclosure:

List of Attendees cc w/encl: See next page

Before the meeting adjourned, members of the public were given the opportunity to communicate with the NRC staff both verbally and through the use of public meeting feedback forms. No comment or feedback was received at this time.

Please direct any inquiries to the undersigned at 301-415-1451, or pst@nrc.gov.

/RA/

Peter S. Tam, Senior Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-263, 50-282, 50-306

Enclosure:

List of Attendees cc w/encl: See next page DISTRIBUTION:

PUBLIC LPL3-1 r/f RidsNrrDorlLpl3-1 RidsNrrPMPTam RidsNrrLATHarris RidsOgcRp RidsAcrsAcnwMailCenter RidsRgn3Mailcenter KWilliams, NSIR DJohnson, NSIR MChawla, NRR TLiu, NRR HChernoff, NRR MNorris, NSIR DJackson, EDO Rgn 3 Package: ML080230576 Summary Accession No.: ML080090567 Meeting Notice Accession No.: ML073531827 Licensee=s Handout Accession No.: ML080090524 OFFICE LPL3-1/PM LPL3-1/LA NSIR/LIB/BC LPL3-1/BC(A)

NAME PTam THarris* KWilliams* PMilano DATE 1/16/08 1/16/08 1/16/08 1/23/08

  • Concurred by e-mail.

OFFICIAL RECORD COPY

MEETING BETWEEN NRC AND NUCLEAR MANAGEMENT COMPANY PROPOSED COMBINED MONTICELLO AND PRAIRIE ISLAND EMERGENCY PLAN LIST OF ATTENDEES JANUARY 9, 2008 Name Organization Mahesh (Mac) Chawla NRC/NRR*/Plant Licensing Branch III-1 (Project Manager for Prairie Island and Palisades)

Harold Chernoff NRC/NRR*/Chief, Plant Licensing Branch I-2 Don Johnson NRC/NSIR**/Licensing & Inspection Branch A. Clem Morgan NMC Michael Norris NRC/NSIR**/Team Leader, Licensing and Inspection Branch Monica Ray FPL Energy Point Beach Peter Tam NRC/NRR*/Plant Licensing Branch III-1 (Project Manager for Monticello and D. C. Cook)

Edward Weinkam NMC Kevin Williams NRC/NSIR**/Chief, Licensing & Inspection Branch

  • Office of Nuclear Reactor Regulation
    • Office of Nuclear Security and Incident Response

Monticello Nuclear Generating Plant cc:

Jonathan Rogoff, Esquire Commissioner Vice President, Counsel & Secretary Minnesota Department of Commerce Nuclear Management Company, LLC 85 7th Place East, Suite 500 700 First Street St. Paul, MN 55101-2198 Hudson, WI 54016 Manager - Environmental Protection U.S. Nuclear Regulatory Commission Division Resident Inspector's Office Minnesota Attorney General=s Office 2807 W. County Road 75 445 Minnesota St., Suite 900 Monticello, MN 55362 St. Paul, MN 55101-2127 Manager, Nuclear Safety Assessment Michael B. Sellman Monticello Nuclear Generating Plant President and Chief Executive Officer Nuclear Management Company, LLC Nuclear Management Company, LLC 2807 West County Road 75 700 First Street Monticello, MN 55362-9637 Hudson, MI 54016 Commissioner Nuclear Asset Manager Minnesota Pollution Control Agency Xcel Energy, Inc.

520 Lafayette Road 414 Nicollet Mall, R.S. 8 St. Paul, MN 55155-4194 Minneapolis, MN 55401 Commissioner Dennis L. Koehl Minnesota Department of Health Chief Nuclear Officer 717 Delaware Street, S. E. Nuclear Management Company, LLC Minneapolis, MN 55440 700 First Street Hudson, WI 54016 Douglas M. Gruber, Auditor/Treasurer Wright County Government Center Mr. Timothy J. O=Connor 10 NW Second Street Site Vice President Buffalo, MN 55313 Monticello Nuclear Generating Plant Nuclear Management Company, LLC 2807 West County Road 75 Monticello, MN 55362-9637

Prairie Island Nuclear Generating Plant, Units 1 and 2 cc:

Jonathan Rogoff, Esquire Tribal Council Vice President, Counsel & Secretary Prairie Island Indian Community Nuclear Management Company, LLC ATTN: Environmental Department 700 First Street 5636 Sturgeon Lake Road Hudson, WI 54016 Welch, MN 55089 Manager, Regulatory Affairs Nuclear Asset Manager Prairie Island Nuclear Generating Plant Xcel Energy, Inc.

Nuclear Management Company, LLC 414 Nicollet Mall, R.S. 8 1717 Wakonade Drive East Minneapolis, MN 55401 Welch, MN 55089 Michael B. Sellman Manager - Environmental Protection Division President and Chief Executive Officer Minnesota Attorney General=s Office Nuclear Management Company, LLC 445 Minnesota St., Suite 900 700 First Street St. Paul, MN 55101-2127 Hudson, MI 54016 U.S. Nuclear Regulatory Commission Dennis L. Koehl Resident Inspector's Office Chief Nuclear Officer 1719 Wakonade Drive East Nuclear Management Company, LLC Welch, MN 55089-9642 700 First Street Hudson, WI 54016 Administrator Goodhue County Courthouse Joel P. Sorenson Box 408 Director, Site Operations Red Wing, MN 55066-0408 Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC Commissioner 1717 Wakonade Drive East Minnesota Department of Commerce Welch, MN 55089 85 7th Place East, Suite 500 St. Paul, MN 55101-2198 Mr. Michael D. Wadley Site Vice President Prairie Island Nuclear Generating Plant Nuclear Management Company, LLC 1717 Wakonade Drive East Welch, MN 55089