Category:Inspection Plan
MONTHYEARIR 05000317/20240052024-08-29029 August 2024 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2024005 and 05000318/2024005) IR 05000317/20230052023-08-31031 August 2023 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2023005 and 05000318/2023005) IR 05000317/20220062023-03-0101 March 2023 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Reports 05000317/2022006 and 05000318/2022006) ML23047A1022023-02-16016 February 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000317/2023401 and 05000318/2023401 ML23040A0102023-02-0909 February 2023 Notification of Commercial Grade Dedication Inspection (05000317/2023012 and 05000318/2023012) and Request for Information IR 05000317/20220052022-08-31031 August 2022 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2022005 and 05000318/2022005) ML22179A2112022-06-28028 June 2022 Notification of Conduct of a Fire Protection Team Inspection IR 05000317/20210062022-03-0202 March 2022 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Reports 05000317/2021006 and 05000318/2021006) IR 05000317/20210052021-09-0101 September 2021 Updated Inspection Plan for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2021005 and 05000318/2021005) ML21187A2232021-07-29029 July 2021 Temporary Instruction 2515/194 Inspection Documentation Request IR 05000317/20200062021-03-0303 March 2021 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Reports 05000317/2020006 and 05000318/2020006) ML21053A3142021-02-22022 February 2021 Information Request for a Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000317/2021010 and 05000318/2021010 IR 05000317/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000317/2020005 and 05000318/2020005) ML20154K4602020-06-0202 June 2020 Information Request to Support Triennial Baseline Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000317/2020011 and 05000318/2020011 IR 05000317/20190062020-03-0303 March 2020 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2019006 and 05000318/2019006) IR 05000317/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Reports 05000317/2019005 and 05000318/2019005) ML19141A1242019-05-21021 May 2019 Notification of Conduct of a Triennial Fire Protection Baseline Inspection and Request for Information IR 05000317/20180062019-03-0404 March 2019 Annual Assessment Letter for the Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Reports 05000317/2018006 and 05000318/2018006) ML18348A4812018-12-13013 December 2018 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000317/2019403 and 05000318/2019403 IR 05000317/20180052018-08-28028 August 2018 Updated Inspection Plan: Inspection Report 05000317/2018005 and 05000318/2018005 IR 05000317/20170062018-02-28028 February 2018 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2017006 and 05000318/2017006, Report 05000317/2017402 and 05000318/2017402, Report 05000317/2017501 and 05000318/2017501) IR 05000317/20170052017-08-28028 August 2017 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 - Inspection Report 05000317/2017005 and 05000318/2017005 IR 05000317/20160062017-03-0101 March 2017 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2016006 and 05000318/2016006) IR 05000317/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2, Report 05000317/2016005 and 05000318/2016005 IR 05000317/20150062016-03-0202 March 2016 2015 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2015006 and 05000318/2015006) IR 05000317/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317/2015005 and 05000318/2015005) IR 05000317/20140012015-03-0404 March 2015 2014 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2, (Report 05000317/2014001 and 05000318/2014001)(w/Inspection Plan) IR 05000317/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter and Inspection Plan 2014 (ROP-15) - Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317-14-006 and 05000318-14-006) ML14206A9932014-07-25025 July 2014 Conrete Bench-Top Autoclave Experiment Test Plan for Calvert Cliffs Nuclear Power Plant. CCNPP-CHLE-010, Revision 1 IR 05000317/20130012014-03-0404 March 2014 2013 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317/2013001 and 05000318/2013001) (W/Inspection Plan) ML13267A0052013-09-23023 September 2013 Requal Program Inspection 60 Day Letter IR 05000317/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan 2013 (ROP-14) - Calvert Cliffs Nuclear Power Plant Units 1 and 2 (Report 05000317-13-006 and 05000318-13-006) IR 05000317/20120012013-03-0404 March 2013 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 & 2 (Report 05000317-12-001 and 05000318-12-001) ML12244A2032012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - 2013 Calvert Cliffs Nuclear Power Plant Units 1 and 2 IR 05000317/20110012012-03-0505 March 2012 Annual Assessment Letter(Report 05000317/2011001 and 05000318/2011001) ML1124208652011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Calvert Cliffs Nuclear Power Plant Units 1 and 2 IR 05000317/20100012011-03-0404 March 2011 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant-05000317/2010001 and 05000318/2010001 ML1031402312010-11-10010 November 2010 Pre-Inspection Cover Sheet and Inspection Plan (12/6/10 - 12/10/10) ML1024402082010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Calvert Cliffs Nuclear Power Plant ML1016600082010-06-15015 June 2010 Pre-Inspection Cover Sheet and Inspection Plan (6/7 - 6/11/10) ML1006208092010-03-0303 March 2010 Annual Assessment Letter ML0924402772009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Calvert Cliffs Nuclear Power Plant, Dated 09/01/2009 IR 05000317/20090012009-03-0404 March 2009 IR 05000317-09-001 and 05000318-09-001, on 01/01/2009 - 12/31/2008, Calvert Cliffs Nuclear Power Plant Annual Assessment Report IR 05000317/20080012008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan, Calvert Cliffs, (IR 05000317-08-001 and 05000318-08-001) ML0806100132008-03-0303 March 2008 (05000317-08-001, 05000318-08-001, )Annual Assessment Letter EOC 2007 ROP8 ML0734707242007-12-13013 December 2007 ROP8 - Change to the Inspection Plan for the Calvert Cliffs Nuclear Power Plant ML0724309302007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - Calvert Cliffs Nuclear Power Plant IR 05000317/20070012007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Calvert Cliffs Station (IR 05000317-07-001 and 05000318-07-001) ML0624304482006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan - Calvert Cliffs Nuclear Power Plant ML0606203372006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Calvert Cliffs Nuclear Power Plant (Report 05-317/2006001 and 05-318/2006001) 2024-08-29
[Table view] Category:Letter
MONTHYEARIR 05000336/20240032024-11-0707 November 2024 Integrated Inspection Report 05000336/2024003 and 05000423/2024003 and Apparent Violation and Independent Spent Fuel Storage Installation Inspection Report 07200008/2024001 IR 05000318/20240072024-11-0606 November 2024 Assessment Follow-Up Letter for Calvert Cliffs Nuclear Power Plant, Unit 2 (Report 05000318/2024007) IR 05000317/20240032024-10-22022 October 2024 Integrated Inspection Report 05000317/2024003, 05000318/2024003, and Independent Spent Fuel Storage Installation Report 07200008/2024001 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24283A0012024-10-0909 October 2024 Senior Reactor and Reactor Operator Initial License Examinations IR 05000317/20245012024-10-0707 October 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000317/2024501 and 05000318/2024501 ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification IR 05000317/20240052024-08-29029 August 2024 Updated Inspection Plan for Calvert Cliffs Nuclear Power Plant, Units 1 and 2 (Report 05000317/2024005 and 05000318/2024005) ML24240A2462024-08-27027 August 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report ML24240A1112024-08-27027 August 2024 Registration of Use of Casks to Store Spent Fuel ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000317/20240022024-08-0606 August 2024 Integrated Inspection Report 05000317/2024002 and 05000318/2024002 IR 05000317/20240102024-07-31031 July 2024 Age-Related Degradation Inspection Report 05000317/2024010 and 05000318/2024010 ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24198A0442024-07-16016 July 2024 Inservice Inspection Report IR 05000317/20244012024-07-0909 July 2024 Security Baseline Inspection Report 05000317/2024401 and 05000318/2024401 ML24177A1832024-06-25025 June 2024 Inservice Inspection Report RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24161A0012024-06-0909 June 2024 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report ML24150A0522024-05-29029 May 2024 Operator Licensing Examination Approval ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24136A1962024-05-15015 May 2024 Independent Spent Fuel Storage Installation - Annual Radiological Environmental Operating Report IR 05000317/20240012024-05-0707 May 2024 Integrated Inspection Report 05000317/2024001 and 05000318/2024001 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests 05000317/LER-2024-002, Emergency Diesel Generators Automatic Start Due to Loss of a 13kV Bus2024-04-29029 April 2024 Emergency Diesel Generators Automatic Start Due to Loss of a 13kV Bus 05000318/LER-2024-001, Manual Reactor Trip Due to 22 Steam Generator Feed Pump Trip2024-04-24024 April 2024 Manual Reactor Trip Due to 22 Steam Generator Feed Pump Trip ML24101A1942024-04-22022 April 2024 Closeout Letter for GL 2004-02 ML24114A0182024-04-18018 April 2024 Electronic Reporting of Occupational Exposure Reporting 05000318/LER-2023-004-01, Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer2024-04-12012 April 2024 Automatic Reactor Trip from Reactor Protection System Actuation Due to Loss of Unit Service Transformer ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000317/20240402024-04-11011 April 2024 95001 Supplemental Inspection Report 05000317/2024040 and Follow-Up Assessment Letter RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24082A0082024-03-22022 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 ML24078A1152024-03-18018 March 2024 10 CFR 50.46 Annual Report ML24059A0632024-03-15015 March 2024 Authorization and Safety Evaluation for Alternative Request ISI-05-021 (EPID L-2023-LLR-0006) - Non-Proprietary IR 05000317/20230062024-02-28028 February 2024 Annual Assessment Letter for Calvert Cliffs Nuclear Power Plant, Units 1 and 2, (Reports 05000317/2023006 and 05000318/2023006 ML24052A0072024-02-14014 February 2024 Core Operating Limits Report for Unit 1, Cycle 27, Revision 0 ML24040A0962024-02-0909 February 2024 Notification of Readiness for NRC 95001 Inspection ML24040A1492024-02-0909 February 2024 Response to NRC Request for Additional Information Regarding Final Response to Generic Letter 2004-02 IR 05000317/20230042024-02-0101 February 2024 Integrated Inspection Report 05000317/2023004 and 05000318/2023004 ML24029A0102024-01-29029 January 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000317/2024010 and 05000318/2024010 ML24003A8872024-01-19019 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0033 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML24011A0732024-01-11011 January 2024 Proposed Alternative to the Requirements for Repair/Replacement of Saltwater (SW) System Buried Piping 05000318/LER-2023-003, Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip2024-01-0808 January 2024 Forward LER 2023-003-00 for Calvert Cliffs Nuclear Power Plant, Unit 2, Manual Actuation of Auxiliary Feedwater System Due to 22 Steam Generator Feedwater Pump Trip ML24005A0222024-01-0505 January 2024 Revised Steam Generator Tube Inspection Reports ML23304A0642024-01-0202 January 2024 Issuance of Amendment No. 349 to Modify the Long-Term Coupon Surveillance Program RS-23-125, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) ML23331A2992023-11-27027 November 2023 Submittal of Condition Prohibited by Technical Specifications Due to Failure to Sample Diesel Generator Fuel Oil Storage Tank IR 05000317/20230102023-11-20020 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000317/2023010 and 05000318/2023010 2024-09-06
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PA 19406 December 13, 2007 Mr. James A. Spina, Vice President Calvert Cliffs Nuclear Power Plant, Inc.
1650 Calvert Cliffs Parkway Lusby, Maryland 20657-4702
SUBJECT:
CHANGE TO THE INSPECTION PLAN FOR THE CALVERT CLIFFS NUCLEAR POWER PLANT
Dear Mr. Spina:
As part of a periodic self-assessment, the Nuclear Regulatory Commission (NRC) thoroughly reviewed the inspection procedures to ensure the continued effective application of inspection resources. The main objective of the review was to determine the appropriate inspection scope for the majority of the inspection procedures in the reactor oversight process (ROP). The result of this effort (designated ROP realignment) created changes to both inspection scope and/or inspection frequency for selected inspection procedures in the ROP. The purpose of this letter is to update the schedule of future inspection activities at your facility that was provided with the mid-cycle assessment letter in August 2007. Please note that there were no changes made to inspection procedures in the security, emergency preparedness, and health physics areas.
The enclosed inspection plan details the inspections (less those related to physical protection) scheduled for calendar year 2008. The inspection plan is provided to resolve any scheduling and/or personnel availability issues well in advance of the inspector(s) arrival onsite. Routine resident inspections are not listed due to their continuous nature.
In accordance with 10 CFR 2.390 of the NRCs Rules and Practices a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of the NRCs document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (The Public Electronic Reading Room).
J. Spina 2 Please contact me at 610-337-5233 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Mr. Glenn T. Dentel, Chief Projects Branch 1 Division of Reactor Projects Docket Nos. 50-317, 50-318 License No. DPR-53, DPR-69
Enclosures:
Calvert Cliffs Nuclear Power Plant Inspection/Activity Plans cc w/encl:
M. J. Wallace, President, Constellation Generation J. M. Heffley, Senior Vice President and Chief Nuclear Officer President, Calvert County Board of Commissioners C. W. Fleming, Esq., Senior Counsel, Nuclear Generation Group J. Gaines, Director, Licensing Director, Nuclear Regulatory Matters R. McLean, Manager, Nuclear Programs K. Burger, Esquire, Maryland People's Counsel R. Hickok, NRC Technical Training Center S. Patterson, SLO (2)
J. Spina 2 Please contact me at 610-337-5233 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Mr. Glenn T. Dentel, Chief Projects Branch 1 Division of Reactor Projects, Region I Docket Nos. 50-317, 50-318 License No. DPR-53, DPR-69
Enclosures:
Calvert Cliffs Nuclear Power Plant Inspection/Activity Plans cc w/encl:
M. J. Wallace, President, Constellation Generation J. M. Heffley, Senior Vice President and Chief Nuclear Officer President, Calvert County Board of Commissioners C. W. Fleming, Esq., Senior Counsel, Nuclear Generation Group J. Gaines, Director, Licensing Director, Nuclear Regulatory Matters R. McLean, Manager, Nuclear Programs K. Burger, Esquire, Maryland People's Counsel R. Hickok, NRC Technical Training Center S. Patterson, SLO (2)
Distribution: see next page SUNSI Review Complete: BAB4 (Reviewer=s Initials)
DOCUMENT NAME: T:\DRP\BRANCH1\ROP 8 Letters\Rop8 Letter - CC.doc After declaring this document AAn Official Agency Record@ it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP NAME BBickett/BAB4 GDentel/GTD DATE 12/06/07 12/06/07 OFFICIAL RECORD COPY
J. Spina 3 Distribution w/encl: J. Trapp, DRS S. Collins, RA J. Rogge, DRS M. Dapas, DRA M. Sykes, DRS G. West, RI OEDO (Acting) J. White, DRS J. Lubinski, NRR L. Doerflein, DRS D. Pickett, PM, NRR R. Conte, DRS M. David, PM, NRR L. Scholl, DRS G. Dentel, DRP P. Frechette, DRS B. Bickett, DRP D. Silk, DRS S. Kennedy, DRP, SRI D. Screnci, PAO M. Davis, DRP, RI N. Sheehan, PAO C. Newgent, DRP, Resident OA R. Barkley, ORA Region I Docket Room (with concurrences) D. Holody, ORA J. Thompson, NRR (JWT1@nrc.gov)
Page 1 of 2 Calvert Cliffs 12/11/2007 14:25:40 Inspection / Activity Plan Report 22 01/01/2008 - 12/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 5/19 EXM - INITIAL OPERATOR LICENSING EXAMS 4 1 U01633 CALVERT CLIFFS UNIT 1 & 2 INITIAL EXAM (FY08) 05/19/2008 05/23/2008 Not Applicable 1 U01633 CALVERT CLIFFS UNIT 1 & 2 INITIAL EXAM (FY08) 06/16/2008 06/20/2008 Not Applicable 7111108P - U1 INSERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 02/18/2008 02/22/2008 Baseline Inspections 1 IP 7111108P Inservice Inspection Activities - PWR 02/25/2008 02/29/2008 Baseline Inspections 71121 - OCC RAD SAFETY 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 02/25/2008 02/29/2008 Baseline Inspections 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 02/25/2008 02/29/2008 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 02/25/2008 02/29/2008 Baseline Inspections TI-166 - CONTAINMENT SUMP MODIFICATION INSPECTION 1 1 IP 2515/166 Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02] 03/03/2008 03/09/2008 Safety Issues 7112103 - OCC RAD SAFETY - INSTRUMENTS 1 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 03/17/2008 03/21/2008 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 03/17/2008 03/21/2008 Baseline Inspections ISFSI - ISFSI - ANNUAL SAMPLE 1 1 IP 60855 Operation Of An ISFSI 04/01/2008 06/30/2008 Other Routine 71121 - OCC RAD SAFETY 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 05/19/2008 05/23/2008 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 05/19/2008 05/23/2008 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 05/19/2008 05/23/2008 Baseline Inspections 7111121 - CDBI 10 1, 2 IP 7111121 Component Design Bases Inspection 06/02/2008 06/06/2008 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 06/16/2008 06/20/2008 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 06/23/2008 06/27/2008 Baseline Inspections 7112201 - PUB RAD SAFETY - RETS 1 1, 2 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 06/16/2008 06/20/2008 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 06/16/2008 06/20/2008 Baseline Inspections 71121 - OCC RAD SAFETY 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 08/25/2008 08/29/2008 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 08/25/2008 08/29/2008 Baseline Inspections 1, 2 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 08/25/2008 08/29/2008 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 08/25/2008 08/29/2008 Baseline Inspections 71121 - OCC RAD SAFETY 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 11/03/2008 11/07/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Calvert Cliffs 12/11/2007 14:25:40 Inspection / Activity Plan Report 22 01/01/2008 - 12/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71121 - OCC RAD SAFETY 1 1, 2 IP 7112102 ALARA Planning and Controls 11/03/2008 11/07/2008 Baseline Inspections 1, 2 IP 71151 Performance Indicator Verification 11/03/2008 11/07/2008 Baseline Inspections EP - EP PROGRAM INSP 2 1, 2 IP 7111402 Alert and Notification System Testing 11/17/2008 11/21/2008 EP Baseline Inspectio 1, 2 IP 7111403 Emergency Response Organization Augmentation Testing 11/17/2008 11/21/2008 EP Baseline Inspectio 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 11/17/2008 11/21/2008 EP Baseline Inspectio 1, 2 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 11/17/2008 11/21/2008 EP Baseline Inspectio 1, 2 IP 71151-EP01 Drill/Exercise Performance 11/17/2008 11/21/2008 Baseline Inspections 1, 2 IP 71151-EP02 ERO Drill Participation 11/17/2008 11/21/2008 Baseline Inspections 1, 2 IP 71151-EP03 Alert & Notification System 11/17/2008 11/21/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.