Summary of Meeting with Entergy, General Electric-Hitachi and Global Nuclear Fuel on Introduction of GNF2 Fuel
ML073340111
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 12/13/2007
From: Boska J
NRC/NRR/ADRO/DORL/LPLI-1
To:
Boska J, NRR, 301-415-2901
References
Download: ML073340111 (5)


Text

December 13, 2007 LICENSEE: Entergy Nuclear Operations, Inc.

FACILITY: James A. FitzPatrick Nuclear Power Plant

SUBJECT:

SUMMARY

OF NOVEMBER 7, 2007, MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC., GENERAL ELECTRIC-HITACHI AND GLOBAL NUCLEAR FUEL ON INTRODUCTION OF GNF2 FUEL On November 7, 2007, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Entergy Nuclear Operations, Inc. (Entergy or the licensee), GE-Hitachi and Global Nuclear Fuel (GNF) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to answer questions and communicate plans for introduction of GNF2 fuel in the James A.

FitzPatrick Nuclear Power Plant (JAFNPP). A list of attendees is provided as Enclosure 1.

The licensee and fuel manufacturer presented information on the plans for introduction of GNF2 fuel in JAFNPP. The presentation started with an overview of the status of the Lead Use Assembly (LUA) Programs currently underway at several boiling-water reactor plants, including Peach Bottom Unit 3, Vermont Yankee, Muhleberg (KKM), and Forsmark. Next, the proposed schedule for final fuel design and core reloading at both plants was reviewed. Then, a presentation of the remaining work scope to be completed prior to introduction of GNF2 into JAFNPP in fall 2008 was made. Please refer to the slides in Enclosure 2.

The significant topics of non-proprietary discussions are presented below. The specific technical details of the fuel design will be the subject of an upcoming audit and are proprietary in nature.

Traversing Incore Probe Data - Data on the neutron flux through the core has been collected and will be provided to the NRC for the audit. Validation of the fuel physics, including local critical values will also be provided.

Debris Screen - The GNF2 fuel proposed for insertion at JAFNPP will have a new design debris screen system called a defender. This design incorporates recent improvements in the debris shield over the LUAs installed at KKM and Forsmark.

Power/Performance - Although the objectives of the recent testing have been to look at mechanical aspects of the fuel, it was noted that during the second cycle at KKM, the GNF2 fuel assemblies were the highest power assemblies in the core. Again, this topic will be further reviewed during the audit.

Schedule - Entergy will be facing a decision point in mid-December regarding whether they should proceed with the current plan for introduction of GNF2 during the core reload in fall 2008.

They are anxious for the NRC to audit the fuel manufacturer to ensure there are no unforeseen issues regarding GNF2 fuel. NRC staff is planning to conduct the audit of the GNF2 fuel development process in several stages to minimize travel costs and maximize staff effectiveness. Plans for the audit will be coordinated with the fuel manufacturer in the near future.

Members of the public were invited to this meeting, but were not in attendance. No Public Meeting Feedback forms were received.

Please direct any inquiries to me at 301-415-2901, or jpb1@nrc.gov.

/RA/

John Boska, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-333

Enclosures:

1. List of Attendees (1 page)
2. Handout GNF2 Introduction at Entergy (4 pages) cc w/encls: See next page

Meeting Summary - ML073340111 Slides - ML073190220 List of Attendees - ML073190061 OFFICE LPL1-1/PM LPL1-1/LA LPL1-1/BC NAME J. Boska S. Little M. Kowal DATE 11/30/07 12/10/07 12/13/07 FitzPatrick Nuclear Power Plant cc:

Mr. Michael R. Kansler Mr. John A. Ventosa President & CEO / CNO GM, Engineering Entergy Nuclear Operations, Inc. Entergy Nuclear Operations, Inc.

1340 Echelon Parkway 440 Hamilton Avenue Jackson, MS 39213 White Plains, NY 10601 Mr. John T. Herron Mr. John F. McCann Sr. Vice President Director, Nuclear Safety & Licensing Entergy Nuclear Operations, Inc. Entergy Nuclear Operations, Inc.

1340 Echelon Parkway 440 Hamilton Avenue Jackson, MS 39213 White Plains, NY 10601 Sr. Vice President Ms. Charlene D. Faison Engineering & Technical Services Manager, Licensing Entergy Nuclear Operations, Inc. Entergy Nuclear Operations, Inc.

1340 Echelon Parkway 440 Hamilton Avenue Jackson, MS 39213 White Plains, NY 10601 Mr. Peter T. Dietrich Mr. Ernest J. Harkness Site Vice President Director, Oversight Entergy Nuclear Operations, Inc. Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant 1340 Echelon Parkway P.O. Box 110 Jackson, MS 39213 Lycoming, NY 13093 Mr. Michael J. Colomb Mr. Kevin J. Mulligan Director of Oversight General Manager, Plant Operations Entergy Nuclear Operations, Inc.

Entergy Nuclear Operations, Inc. 440 Hamilton Avenue James A. FitzPatrick Nuclear Power Plant White Plains, NY 10601 P.O. Box 110 Lycoming, NY 13093 Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.

Mr. Oscar Limpias James A. FitzPatrick Nuclear Power Plant Vice President Engineering P.O. Box 110 Entergy Nuclear Operations, Inc. Lycoming, NY 13093 1340 Echelon Parkway Jackson, MS 39213 Mr. James Costedio Manager, Licensing Mr. Joseph P. DeRoy Entergy Nuclear Operations, Inc.

Vice President, Operations Support James A. FitzPatrick Nuclear Power Plant Entergy Nuclear Operations, Inc. P.O. Box 110 1340 Echelon Parkway Lycoming, NY 13093 Jackson, MS 39213

FitzPatrick Nuclear Power Plant cc:

Mr. William C. Dennis Supervisor Assistant General Counsel Town of Scriba Entergy Nuclear Operations, Inc. Route 8, Box 382 440 Hamilton Avenue Oswego, NY 13126 White Plains, NY 10601 Mr. James H. Sniezek Regional Administrator, Region I BWR SRC Consultant U.S. Nuclear Regulatory Commission 5486 Nithsdale Drive 475 Allendale Road Salisbury, MD 21801-2490 King of Prussia, PA 19406 Mr. Michael D. Lyster Resident Inspector's Office BWR SRC Consultant James A. FitzPatrick Nuclear Power Plant 5931 Barclay Lane U. S. Nuclear Regulatory Commission Naples, FL 34110-7306 P.O. Box 136 Lycoming, NY 13093 Mr. John Doering BWR SRC Consultant Mr. Charles Donaldson, Esquire P.O. Box 189 Assistant Attorney General Parker Ford, PA 19457 New York Department of Law 120 Broadway Mr. Michael A. Balduzzi New York, NY 10271 Sr. Vice President & COO Regional Operations, NE Mr. Paul Tonko Entergy Nuclear Operations, Inc.

President and CEO 440 Hamilton Avenue New York State Energy, Research, and White Plains, NY 10601 Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. John P. Spath New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Paul Eddy New York State Dept. of Public Service 3 Empire State Plaza Albany, NY 12223-1350 Oswego County Administrator Mr. Steven Lyman 46 East Bridge Street Oswego, NY 13126