MONTHYEARML23320A2472023-11-17017 November 2023 Constellation - Summary of November 14, 2023, Public Pre-Application Meeting with Constellation Energy Generation, LLC on Adoption of TSTF-591 ML23271A2682023-10-0505 October 2023 September 25, 2023, Summary of with Constellation Energy Generation, LLC on Proposed Changes to Emergency Plans ML23263B1062023-09-22022 September 2023 R. E. Ginna Nuclear Power Plant - Constellation - Pre-Application Amse 9/18/2023 Meeting Summary ML23179A0012023-06-28028 June 2023 6/7/2023 - Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - Meeting Summary ML23055A0352023-03-24024 March 2023 Summary of February 23, 2023, with Constellation Energy Generation, LLC on Proposed Changes to Emergency Plans to Revise Emergency Action Levels ML22187A1462022-07-0606 July 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Meeting Summary ML21333A1532021-11-30030 November 2021 Summary of November 16, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Extend the Inservice Inspection Interval ML21237A0412021-08-30030 August 2021 Summary of the July 27, 2021, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Use Case OMN-28, ML21176A0822021-07-0606 July 2021 June 15, 2021, Summary of Meeting with Exelon Generation Company, LLC Vessel Nozzle Repair Related to a Planned Request for an Alternative Related to Reactor Pressure ML21139A1852021-06-22022 June 2021 Summary of Meeting with Exelon Generation Company, LLC Regarding Its Requested Alternative to Eliminate Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting ML21011A2822021-01-21021 January 2021 Summary of January 6, 2021, Presubmittal Meeting Between the NRC and Exelon Generation Company, LLC Regarding Licensing Activities to Support the Planned Early Closures of Byron, Unit Nos. 1 and 2 and Dresden, Units 2 and 3 ML20351A2832020-12-18018 December 2020 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Exemption to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs ML20342A3522020-12-10010 December 2020 Summary of November 13, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alterantive to Certain Documentation Requirements for the Replacement of Pressure Retaining Bolting (EPID-L-2020-LRM-0102) ML20323A0332020-12-0101 December 2020 Summary of November 4, 2020, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Reduce the Frequency of Updates to Its Inservice Testing and Inspection Programs ML20205L3712020-07-23023 July 2020 and R.E. Ginna Nuclear Power Plant Summary of Meeting ML20163A1722020-06-12012 June 2020 Summary of June 9, 2020, Pre-Submittal Meeting with Exelon Generation Company, LLC, Regarding Planned License Amendment Request to Modify Surveillance Requirement 3.6.1.3 ML19326C3582019-12-0303 December 2019 Summary of November 20, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Revise the Quality Assurance Program ML19326A3152019-12-0303 December 2019 Summary of November 18, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request for an Alternative to Supplemental Valve Position Indication Testing Requirements ML19302F8772019-11-0404 November 2019 Summary of the October 28, 2019, Meeting with Exelon Generation Company, LLC, Regarding a Planned Supplement to a License Amendment Request Regarding Revising the Allowable Value for Reactor Water Cleanup System Isolation ML19291A0022019-11-0101 November 2019 10/03-10/08/2019 Summary of Meetings with Exelon Generation Company, LLC, on Emergency Amendment Request Regarding One-Time Extension to Technical Specifications 3.8.1 Action A.3 Completion Time for Inoperable Offsite Source (EPID L-2019-LL ML19302D3152019-10-28028 October 2019 Annual Assessment Meeting for James A. Fitzpatrick Nuclear Power Plant and Nine Mile Point Nuclear Generating Station - Meeting Summary ML19176A0042019-07-15015 July 2019 Summary of Meeting with Exelon Generation Company, LLC, on a Planned License Amendment Request Regarding the Relaxation of Containment Differential Pressure Requirements ML19183A1282019-07-15015 July 2019 Summary of June 20, 2019, Meeting with Exelon Generation Company, LLC, on a Planned License Amendment Request Regarding Main Steam Isolation Valve Leak Rate Increase Utilizing ML19162A0272019-06-21021 June 2019 Summary of June 4, 2019, Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Extend the Test Interval for Safety Relief Valves ML19036A8832019-02-0707 February 2019 Summary of Meeting with Exelon Generation Company, LLC Regarding a Planned Request to Use ASME Code Case N-879 ML18354B1712019-01-0202 January 2019 Summary of December 19, 2018, Meeting with Exelon Generation Company, LLC Regarding the Use of Boiling Water Reactor Vessel and Internals Project Guidelines ML18347B4932019-01-0202 January 2019 Summary of Pre-Application Meeting with Exelon Generation Co., LLC (Exelon) Forthcoming License Amendment Requests to Revise Technical Specification Requirements for Main Steam Isolation Valve Leak Rate Tests ML18325A1712018-11-28028 November 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Planned Fleet License Amendment Request to Revise Technical Specifications for High Radiation Areas ML18304A1662018-11-0606 November 2018 Summary of October 23, 2018, Teleconference with Exelon Generation Co., LLC to Discuss Potential License Amendment Request Ultimate Heat Sink Bar Rack Bar Heaters ML18297A1722018-10-26026 October 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Planned License Amendment Request to Adopt TSTF-427 ML18262A3662018-09-18018 September 2018 August 21, 2018, James A. Fitzpatrick Nuclear Power Plant (Fitzpatrick) and Nine Mile Point Nuclear Generating Station (Nine Mile Point) Summary of Public Meeting ML18163A2682018-06-19019 June 2018 Summary of June 5, 2018, Teleconference with Exelon Generation Company, LLC to Discuss Emergency Plan Changes at James A. Fitzpatrick Nuclear Power Plant and Nine Mile Point Nuclear Station ML18120A1772018-05-0101 May 2018 Summary of Meeting with Exelon Generation Company, LLC Regarding Draft Guidance for Emergency Response Organization Staffing ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML17256A7482017-09-28028 September 2017 Summary of September 5, 2017, Meeting with Exelon Generation Co., LLC to Discuss Potential License Amendment Request Technical Specifications Task Force Traveler TSTF-542, Revision 2, for James A. Fitzpatrick Nuclear Power Plant ML17216A1732017-09-0707 September 2017 Notice of Meeting with Florida Power & Light Company and NextEra Energy to Discuss Closing Out Generic Safety Issue-191 and Generic Letter 2004-02 ML17144A2852017-06-0202 June 2017 Summary Teleconference with Exelon Generation Company, LLC, on Planned Submittals of License Amendment Requests to Change Emergency Action Levels Associated with Lake Ontario Water Level ML17143A3582017-05-23023 May 2017 Summary of Public Meeting for James A. Fitzpatrick and Nine Mile Point ML17143A1902017-05-23023 May 2017 Public Meeting Handouts and Sign in Sheet ML17031A2802017-02-0808 February 2017 Summary of Teleconference with Entergy Nuclear Operations, Inc. Regarding Verbal Authorization for Relief Request RR-21 for the James A. Fitzpatrick Nuclear Power Plant ML16229A4542016-08-16016 August 2016 Summary of Annual Assessment Meeting for James A. Fitzpatrick Nuclear Power Plant ML15197A3332015-07-24024 July 2015 June 29, 2015 Summary of Meeting with Beyond Nuclear, Et. Al., Regarding Its 10 CFR 2.206 Petition Requesting Enforcement Action Against the James A. FitzPatrick Nuclear Power Plant ML15120A0212015-04-28028 April 2015 April 23, 2015, Summary of Annual Assessment Meeting for James A. FitzPatrick Nuclear Power Plant on 4/23/2015 ML14197A5832014-09-18018 September 2014 Summary of the June 19, 2014, Category 1 Public Meeting with Entergy to Discuss Seismic Hazard Reevaluations Associated with Implementation of Japan Lessons-Learned Near-Tear Task Force Recommendation 2.1 ML14086A1532014-03-26026 March 2014 Summary of Annual Assessment Meeting for Nine Mile Point Nuclear Station and James A. FitzPatrick Nuclear Power Plant on 3/18/2014 ML13100A1172013-04-10010 April 2013 Summary of Public Meeting Regarding Nine Mile Point Nuclear Station and James A. Fitzpatrick Nuclear Power Plant ML13162A5812012-07-19019 July 2012 PRB Closed Meeting Notes - 07/19/12 Gunter Et Al. 2.206 Requesting Enforcement Action Against James A. Fitzpatrick Plant ML13162A5802012-05-29029 May 2012 PRB Closed Meeting Notes - 05/29/12 Gunter Et Al. 2.206 Requesting Enforcement Action Against James A. Fitzpatrick Plant ML12102A1752012-04-11011 April 2012 and James A. FitzPatrick Nuclear Power Plant - Summary of Public Meeting on March 22, 2012 ML13162A6282012-03-20020 March 2012 by Larry Doerflein: PRB Notes Attached-Dial-In Provided 2023-09-22
[Table view] |
Text
December 13, 2007 LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: James A. FitzPatrick Nuclear Power Plant
SUBJECT:
SUMMARY
OF NOVEMBER 7, 2007, MEETING WITH ENTERGY NUCLEAR OPERATIONS, INC., GENERAL ELECTRIC-HITACHI AND GLOBAL NUCLEAR FUEL ON INTRODUCTION OF GNF2 FUEL On November 7, 2007, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Entergy Nuclear Operations, Inc. (Entergy or the licensee), GE-Hitachi and Global Nuclear Fuel (GNF) at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to answer questions and communicate plans for introduction of GNF2 fuel in the James A.
FitzPatrick Nuclear Power Plant (JAFNPP). A list of attendees is provided as Enclosure 1.
The licensee and fuel manufacturer presented information on the plans for introduction of GNF2 fuel in JAFNPP. The presentation started with an overview of the status of the Lead Use Assembly (LUA) Programs currently underway at several boiling-water reactor plants, including Peach Bottom Unit 3, Vermont Yankee, Muhleberg (KKM), and Forsmark. Next, the proposed schedule for final fuel design and core reloading at both plants was reviewed. Then, a presentation of the remaining work scope to be completed prior to introduction of GNF2 into JAFNPP in fall 2008 was made. Please refer to the slides in Enclosure 2.
The significant topics of non-proprietary discussions are presented below. The specific technical details of the fuel design will be the subject of an upcoming audit and are proprietary in nature.
Traversing Incore Probe Data - Data on the neutron flux through the core has been collected and will be provided to the NRC for the audit. Validation of the fuel physics, including local critical values will also be provided.
Debris Screen - The GNF2 fuel proposed for insertion at JAFNPP will have a new design debris screen system called a defender. This design incorporates recent improvements in the debris shield over the LUAs installed at KKM and Forsmark.
Power/Performance - Although the objectives of the recent testing have been to look at mechanical aspects of the fuel, it was noted that during the second cycle at KKM, the GNF2 fuel assemblies were the highest power assemblies in the core. Again, this topic will be further reviewed during the audit.
Schedule - Entergy will be facing a decision point in mid-December regarding whether they should proceed with the current plan for introduction of GNF2 during the core reload in fall 2008.
They are anxious for the NRC to audit the fuel manufacturer to ensure there are no unforeseen issues regarding GNF2 fuel. NRC staff is planning to conduct the audit of the GNF2 fuel development process in several stages to minimize travel costs and maximize staff effectiveness. Plans for the audit will be coordinated with the fuel manufacturer in the near future.
Members of the public were invited to this meeting, but were not in attendance. No Public Meeting Feedback forms were received.
Please direct any inquiries to me at 301-415-2901, or jpb1@nrc.gov.
/RA/
John Boska, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-333
Enclosures:
- 1. List of Attendees (1 page)
- 2. Handout GNF2 Introduction at Entergy (4 pages) cc w/encls: See next page
Meeting Summary - ML073340111 Slides - ML073190220 List of Attendees - ML073190061 OFFICE LPL1-1/PM LPL1-1/LA LPL1-1/BC NAME J. Boska S. Little M. Kowal DATE 11/30/07 12/10/07 12/13/07 FitzPatrick Nuclear Power Plant cc:
Mr. Michael R. Kansler Mr. John A. Ventosa President & CEO / CNO GM, Engineering Entergy Nuclear Operations, Inc. Entergy Nuclear Operations, Inc.
1340 Echelon Parkway 440 Hamilton Avenue Jackson, MS 39213 White Plains, NY 10601 Mr. John T. Herron Mr. John F. McCann Sr. Vice President Director, Nuclear Safety & Licensing Entergy Nuclear Operations, Inc. Entergy Nuclear Operations, Inc.
1340 Echelon Parkway 440 Hamilton Avenue Jackson, MS 39213 White Plains, NY 10601 Sr. Vice President Ms. Charlene D. Faison Engineering & Technical Services Manager, Licensing Entergy Nuclear Operations, Inc. Entergy Nuclear Operations, Inc.
1340 Echelon Parkway 440 Hamilton Avenue Jackson, MS 39213 White Plains, NY 10601 Mr. Peter T. Dietrich Mr. Ernest J. Harkness Site Vice President Director, Oversight Entergy Nuclear Operations, Inc. Entergy Nuclear Operations, Inc.
James A. FitzPatrick Nuclear Power Plant 1340 Echelon Parkway P.O. Box 110 Jackson, MS 39213 Lycoming, NY 13093 Mr. Michael J. Colomb Mr. Kevin J. Mulligan Director of Oversight General Manager, Plant Operations Entergy Nuclear Operations, Inc.
Entergy Nuclear Operations, Inc. 440 Hamilton Avenue James A. FitzPatrick Nuclear Power Plant White Plains, NY 10601 P.O. Box 110 Lycoming, NY 13093 Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.
Mr. Oscar Limpias James A. FitzPatrick Nuclear Power Plant Vice President Engineering P.O. Box 110 Entergy Nuclear Operations, Inc. Lycoming, NY 13093 1340 Echelon Parkway Jackson, MS 39213 Mr. James Costedio Manager, Licensing Mr. Joseph P. DeRoy Entergy Nuclear Operations, Inc.
Vice President, Operations Support James A. FitzPatrick Nuclear Power Plant Entergy Nuclear Operations, Inc. P.O. Box 110 1340 Echelon Parkway Lycoming, NY 13093 Jackson, MS 39213
FitzPatrick Nuclear Power Plant cc:
Mr. William C. Dennis Supervisor Assistant General Counsel Town of Scriba Entergy Nuclear Operations, Inc. Route 8, Box 382 440 Hamilton Avenue Oswego, NY 13126 White Plains, NY 10601 Mr. James H. Sniezek Regional Administrator, Region I BWR SRC Consultant U.S. Nuclear Regulatory Commission 5486 Nithsdale Drive 475 Allendale Road Salisbury, MD 21801-2490 King of Prussia, PA 19406 Mr. Michael D. Lyster Resident Inspector's Office BWR SRC Consultant James A. FitzPatrick Nuclear Power Plant 5931 Barclay Lane U. S. Nuclear Regulatory Commission Naples, FL 34110-7306 P.O. Box 136 Lycoming, NY 13093 Mr. John Doering BWR SRC Consultant Mr. Charles Donaldson, Esquire P.O. Box 189 Assistant Attorney General Parker Ford, PA 19457 New York Department of Law 120 Broadway Mr. Michael A. Balduzzi New York, NY 10271 Sr. Vice President & COO Regional Operations, NE Mr. Paul Tonko Entergy Nuclear Operations, Inc.
President and CEO 440 Hamilton Avenue New York State Energy, Research, and White Plains, NY 10601 Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. John P. Spath New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Paul Eddy New York State Dept. of Public Service 3 Empire State Plaza Albany, NY 12223-1350 Oswego County Administrator Mr. Steven Lyman 46 East Bridge Street Oswego, NY 13126