From:
John White To:
Marjorie McLaughlin Date:
10/26/2007 1:28:40 PM
Subject:
Fwd: FW: Unit 1 Schedule
>>> "Mayer, Donald M" <dmayer1@entergy.com> 10/26/2007 12:27 PM >>>
John B below is a >resend= of the key milestone information which I had provided in an embedded table.
-Completion of Infrastructure mods, dry run preps and licensing item closures (Crane LAR and Holtec Cask) - May 2008
-Fill Pools and complete NRC observed dry runs - Aug 2008
-Load, Process and transfer all fuel to ISFSI pad (5 casks B 160 fuel elements) - Oct 2008
-Complete draining of fuel pools - Dec 2008 From: Mayer, Donald M Sent: Thursday, October 25, 2007 12:15 PM To: John White (NRC)
Subject:
Unit 1 Schedule John-The key milestones for the removal of the fuel from Unit 1 are as follows: As we have discussed, the mission is to have all the fuel moved to the pad (begin offload summer 2008) and pools drained of water by the end of 2008, thereby physically removing the source term for the leak.It is important to also note that we have;Installed a continuously operating pool water cleanup system which has substantially reduced the pool water source term (and therefore source leak to ground water) and this system will remain in operation throughout the fuel off load and water draining process. We have a long-term monitoring program in operation that will assess the effect of the source removal and natural attenuation going forward. When the pools are drained we will process the water as plant effluent to ensure the final effluent is monitored and meets ALARA principals.
Don MayerDir, Unit 1Entergy NuclearIndian Point Energy Center(w) 914 827-7716 (c) 914 582-6901
Mail Envelope Properties (472223C8.669 : 3 : 26073)
Subject:
Fwd: FW: Unit 1 Schedule Creation Date 10/26/2007 1:28:40 PM From:
John White Created By:
JRW1@nrc.gov Recipients nrc.gov kp1_po.KP_DO MMM3 (Marjorie McLaughlin)
Post Office Route kp1_po.KP_DO nrc.gov Files Size Date & Time MESSAGE 2623 10/26/2007 1:28:40 PM TEXT.htm 10273 IMAGE.x-citrix-gif 3478 Mime.822 18479 10/26/2007 1:28:40 PM Options Expiration Date:
None Priority:
Standard ReplyRequested:
No Return Notification:
None Concealed
Subject:
No Security:
Standard Junk Mail Handling Evaluation Results Message is not eligible for Junk Mail handling Message is from an internal sender Junk Mail settings when this message was delivered Junk Mail handling disabled by User Junk List is not enabled Junk Mail using personal address books is not enabled Block List is not enabled