ML072900460
| ML072900460 | |
| Person / Time | |
|---|---|
| Site: | Pilgrim |
| Issue date: | 10/17/2007 |
| From: | Abramson P, Cole R, Austin Young Atomic Safety and Licensing Board Panel |
| To: | |
| SECY RAS | |
| References | |
| 06-848-02-LR, 50-293-LR, RAS 14456 | |
| Download: ML072900460 (4) | |
Text
1 Order (Establishing Schedule for Proceeding and Addressing Related Matters) at 7 (December 20, 2006).
2 Id.
3 Memorandum and Order (Ruling on Entergys Motion for Summary Disposition of Pilgrim Watch Contention 1, Regarding Adequacy of Aging Management Program for Buried Pipes and Tanks and Potential Need for Monitoring Wells to Supplement Program) (Oct. 17, 2007).
UNITED STATES OF AMERICA DOCKETED 10/17/07 NUCLEAR REGULATORY COMMISSION ATOMIC SAFETY AND LICENSING BOARD PANEL SERVED 10/17/07 Before Administrative Judges:
Ann Marshall Young, Chair Dr. Paul B. Abramson Dr. Richard F. Cole In the Matter of:
ENTERGY NUCLEAR GENERATION COMPANY AND ENTERGY NUCLEAR OPERATIONS, INC.
(Pilgrim Nuclear Power Station)
Docket No. 50-293-LR ASLBP No. 06-848-02-LR October 17, 2007 ORDER (Extending Deadline for Filing Witness Lists Regarding Contention 1)
On December 20, 2006, the Licensing Board issued a scheduling order in the above-referenced proceeding, in which, among other things, we set October 30, 2007, as the deadline for filing final witness lists.1 We stated at that time that this deadline might be extended for good cause shown.2 Having today issued a Memorandum and Order denying Entergys Motion for Summary Disposition of Pilgrim Watch Contention 1,3 we find it appropriate at this time to extend the deadline for filing of final witness lists relating to Contention 1 to November 30, 2007. With regard to any further changes in the schedule, as requested by Intervenors in a motion filed 4 Pilgrim Watchs Motion Requesting That the Order Establishing the Schedule for the Proceedings Be Reset to Extend All Deadlines for Filings at Minimum Thirty (30) Days (Oct. 17, 2007).
5 Copies of this Order were sent this date by Internet e-mail to all counsel or representatives for parties.
today,4 we will defer our ruling until we have received the responses of the other parties to Intervenors motion. With regard to the witness list deadline relating to Contention 3, we will address this and any other scheduling matters relating to it as deemed appropriate, either with our ruling on Entergys Motion for Summary Disposition of that contention, which we expect will be issued in the near future, or after receipt of the responses of the other parties to Intervenors pending motion.
It is so ORDERED.
THE ATOMIC SAFETY AND LICENSING BOARD
_____/RA/__________________________
Ann Marshall Young, Chair ADMINISTRATIVE JUDGE
_____/RA/__________________________
Dr. Paul B. Abramson ADMINISTRATIVE JUDGE
______/RA/_________________________
Dr. Richard F. Cole ADMINISTRATIVE JUDGE Rockville, Maryland October 17, 20075
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of
)
)
ENTERGY NUCLEAR GENERATION CO.
)
AND
)
ENTERGY NUCLEAR OPERATIONS, INC. )
Docket No. 50-293-LR
)
)
(Pilgrim Nuclear Power Station)
)
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing LB ORDER (EXTENDING DEADLINE FOR FILING WITNESS LISTS REGARDING CONTENTION 1) have been served upon the following persons by U.S. mail, first class, or through NRC internal distribution.
Office of Commission Appellate Adjudication U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Administrative Judge Ann Marshall Young, Chair Atomic Safety and Licensing Board Panel Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Administrative Judge Richard F. Cole Atomic Safety and Licensing Board Panel Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Administrative Judge Paul B. Abramson Atomic Safety and Licensing Board Panel Mail Stop - T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Susan L. Uttal, Esq.
Andrea L. Silvia, Esq.
Steven R. Hom, Esq.
Office of the General Counsel Mail Stop - O-15 D21 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 John E. Matthews Morgan, Lewis & Bockius, LLP 1111 Pennsylvania Avenue, NW Washington, DC 20004
2 Docket No. 50-293-LR LB ORDER (EXTENDING DEADLINE FOR FILING WITNESS LISTS REGARDING CONTENTION 1)
John Boska, Project Manager Plant Licensing Branch I-I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail StopO-8-C2 Washington, DC 20555-0001
[Original signed by Evangeline S. Ngbea]
Office of the Secretary of the Commission Dated at Rockville, Maryland this 17th day of October 2007