Requests for Additional Information for the Review of the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application
ML072850255
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 10/24/2007
From: Gettys E
NRC/NRR/ADRO/DLR/RLRA
To: Mckinney B
Susquehanna
Gettys Evelyn, NRR/DLR/RLRA 415-4029
References
Download: ML072850255 (7)


Text

October 24, 2007 Mr. Britt T. McKinney Sr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467

SUBJECT:

REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION

Dear Mr. McKinney:

By letter dated September 13, 2006, PPL Susquehanna, LLC submitted an application pursuant to 10 CFR Part 54, to renew the operating licenses for Susquehanna Steam Electric Station, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.

These requests for additional information were discussed with Duane Filchner, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-4029 or e-mail ehg2@nrc.gov.

Sincerely,

/RA/

Evelyn Gettys, Project Manager License Renewal Branch A Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-387 and 50-388

Enclosure:

Requests for Additional Information cc w/encl: See next page

ML072850255 OFFICE LA:DLR PM:RLRA:DLR BC:RLRA:DLR NAME IKing EGettys LLund DATE 10/15/07 10/21/07 10/24/07

Enclosure SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2 LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION (RAIs)

RAI 2.3.1-1 In Table 2.3.1-1 of the license renewal application (LRA), the nozzle N9 and cap for N9 are listed as in scope as a pressure boundary. Drawing M-141-2 depicts nozzle N9 as out of scope.

Please confirm N9 nozzle and cap are in scope.

RAI 2.3.1-2 Drawing M-146 of the LRA depicts the valve 146-F004, and associate piping for a drive water pressure control station as out of scope. However, isolation valves between the out of scope and in scope piping are not shown. The staff believes that this bypass line and valve should be in scope of license renewal as a pressure boundary. The staff requests the applicant to clarify whether the subject components are in scope requiring an aging management review (AMR) and justify if excluded.

RAI 2.3.2.2-1 Drawings M-150 and -2150 of the LRA depict the piping between the reactor core isolation cooling vacuum tank and the barometric condenser vacuum pump as not in scope. However, Table 2.3.2-2 lists piping and piping components function (under the vacuum tank) as structural integrity. Additionally, Tanks 1/2T219 are depicted as in scope in Drawing 150-1; however, they are not listed in Table 2.3.2-2. Please confirm the connecting piping is included within the scope of license renewal and subject to AMR as structural boundary or justify its exclusion. Modify Table 2.3.2-2 to reflect your response.

RAI 2.3.2.4-1 In Drawing 156-1 of the LRA, the drive shaft from the high-pressure coolant injection (HPCI) turbine to the HPCI pump is shown in-scope, however, the drive shaft between the HPCI pump and booster pump is not. The staff requests the applicant to clarify whether the drive shafts are in scope requiring an AMR and justify, if excluded.

RAI 2.3.3.25-1 The Drawing 123-12 of the LRA depicts multiple Ainsulated couplings or unions,@ clarify how these components are included in Table 2.3.3-24 for components subject to an AMR as a pressure boundary and justify, if excluded.

RAI 2.3.3.32-1 In Drawing 48-1 of the LRA, the ventilation lines from the test tanks and storage tanks are depicted as not in scope. The staff requests the applicant to clarify whether the lines are in scope requiring an AMR and justify, if the lines are excluded.

RAI 2.3.3.32-2 In Drawing 148-1 of the LRA, the SLC storage tank (1T204) appears to include a hatch. It is unclear whether the hatch and closure mechanism is included as part of the tank. The staff believes these components should be included as a pressure boundary. Clarify whether the tank hatches and closure mechanisms are in scope requiring an AMR and justify, if the components are excluded. Modify Table 2.3.3-31, if necessary, to reflect your response or explain under what component they are included.

Letter to B. McKinney from E. Gettys dated October 24, 2007 DISTRIBUTION:

SUBJECT:

REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION HARD COPY:

DLR RF E-MAIL:

PUBLIC SSmith (srs3)

SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDciCvib RidsNrrDciCpnb RidsNrrDraAfpb RidsNrrDeEmcb RidsNrrDeEeeb RidsNrrDssSrxb RidsNrrDssSbpb RidsNrrDssScvb RidsOgcMailCenter YDiaz RGuzman BRogers EGettys

Susquehanna Steam Electric Station, Units 1 and 2 cc:

Cornelius J. Gannon Vice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467 Robert M. Paley General Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467 Rocco R. Sgarro Manager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Walter E. Morrissey Supervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Michael H. Crowthers Supervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Ronald E. Smith General Manager - Site Preparedness and Services PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467 Steven M. Cook Manager - Quality Assurance PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467 Luis A. Ramos Community Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467 Bryan A. Snapp, Esq.

Associate General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179 Supervisor - Document Control Services PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179 Richard W. Osborne Allegheny Electric Cooperative, Inc.

212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266 Director, Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469

Susquehanna Steam Electric Station, Units 1 and 2 cc:

Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4 Berwick, PA 18603-0035 Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Board of Supervisors Salem Township P.O. Box 405 Berwick, PA 18603-0035 Dr. Judith Johnsrud National Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803