MONTHYEARML24022A2262024-01-22022 January 2024 (PBAPS) Unit 3 - Submittal of the Inservice Inspection (ISI) Owner'S Activity Report (OAR) for the 24th Refueling Outage for Unit 3 ML23346A2412024-01-17017 January 2024 Staff Assessment of Updated Seismic Hazards Following the NRC Process for the Ongoing Assessment of Natural Hazards Information (EPID L-2019-PMP-0061) - Letter IR 05000277/20234022024-01-11011 January 2024 Security Baseline Inspection Report 05000277/2023402 and 05000278/2023402 and Independent Spent Fuel Storage Installation Security Inspection 07200029/2023401 ML23354A1922024-01-0505 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) ML23355A0622023-12-18018 December 2023 Independent Spent Fuel Storage Installation (Isfsi), Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 ML23334A2502023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums ML23305A3472023-11-0101 November 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) IR 05000277/20230032023-10-30030 October 2023 Integrated Inspection Report 05000277/2023003 and 05000278/2023003 and Exercise of Enforcement Discretion ML23286A0012023-10-13013 October 2023 Reply to a Notice of Violation (NOV) - NOV 05000277, 05000278/2023010-01 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23271A1342023-10-11011 October 2023 Dtf Analysis Letter IR 05000277/20244012023-10-0505 October 2023 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000277/2024401 and 05000278/2024401 ML23265A1502023-09-22022 September 2023 License Amendment Request Revise a License Condition and Certain Technical Specifications to Remove Restrictions in Support of Decommissioning Activities ML23264A8682023-09-21021 September 2023 Independent Spent Fuel Storage Installation Registration of Dry Storage Canister WC-EOS-37PTH-008-B4L, WC-EOS-37PTH-007-B4L, and WC-EOS-37PTH-002-B4L IR 05000277/20230102023-09-15015 September 2023 Biennial Problem Identification and Resolution Inspection Report 05000277/2023010 and 05000278/2023010 and Notice of Violation ML23251A2022023-09-11011 September 2023 Cover Letter W/Report LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement IR 05000277/20230052023-08-31031 August 2023 Updated Inspection Plan for Peach Bottom Atomic Power Station, Units 2 and 3 (Report 05000277/2023005 and 05000278/2023005) ML23158A1952023-08-30030 August 2023 R. E. Ginna - Issuance of Amendments to Adopt TSTF-273-A, Revision 2, Safety Function Determination Program Clarifications ML23232A0012023-08-19019 August 2023 Revision of One Procedure That Implements the Radiological Emergency Response Plan (Rerp). Includes EPP 06-009, Rev. 13 IR 05000277/20230112023-08-15015 August 2023 Comprehensive Engineering Team Inspection Report 05000277/2023011 and 05000278/2023011 ML23226A1112023-08-14014 August 2023 10 CFR 50.46 Annual Report IR 05000277/20230022023-08-0808 August 2023 Integrated Inspection Report 05000277/2023002 and 05000278/2023002 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor IR 05000277/20230402023-07-17017 July 2023 95001 Inspection Supplemental Report 05000277/2023040 and Follow-Up Assessment Letter ML23188A0532023-07-0707 July 2023 Registration of Use of Independent Spent Fuel Storage Installation (ISFSI) Casks ML23186A1272023-07-0606 July 2023 Response to Disputed Non-Cited Violation Documented in Peach Bottom Atomic Power Station, Units 2 and 3, Inspection Report 05000277/2022004 and 05000278/2022004 ML23178A0352023-06-27027 June 2023 Senior Reactor and Reactor Operator Initial License Examinations RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23151A4162023-05-31031 May 2023 Revision of One Form That Implements the Radiological Emergency Response Plan (RERP) for Wolf Creek Generating Station (WCGS) ML23150A2052023-05-30030 May 2023 Independent Spent Fuel Storage Installation (Isfsi), Annual Radiological Environmental Operating Report 80 January 1, 2022 Through December 31, 2022 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23142A1602023-05-23023 May 2023 Summary of April 11, 2023, Public Observation Meeting with Constellation Energy Generation, LLC Re Proposed Exemption Request from Work Hour Requirements ML23132A1582023-05-18018 May 2023 Correction to Technical Specification 3.4.7 (Page 3.4-16) Issued in Amendment No. 337 ML23132A1532023-05-12012 May 2023 Transmittal of 2022 Annual Financial Reports WM 23-0009, Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1)2023-05-10010 May 2023 Financial Assurance Requirements for Decommissioning Nuclear Power Reactors 10 CFR 50.75(f)(1) IR 05000277/20230012023-05-0808 May 2023 Integrated Inspection Report 05000277/2023001 and 05000278/2023001 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI 2024-01-05
[Table view] |
Text
November 28, 2007 Ms. Danielle Brian Executive Director, Project on Government Oversight 666 Eleventh Street, NW, Suite 900 Washington, D.C. 20001
Dear Ms. Brian:
On behalf of the U.S. Nuclear Regulatory Commission (NRC), I am responding to your letters of September 28, 2007 and October 16, 2007, regarding your concerns following a series of investigative reports by WCBS in New York involving video of inattentive security officers at the Peach Bottom Atomic Power Station in eastern Pennsylvania. The NRC is addressing this issue at Peach Bottom, and is taking appropriate action to ensure that similar incidents do not occur at this or any other nuclear power plant.
You also questioned the NRC Region I offices handling of a March 2007 allegation about inattentive security officers at Peach Bottom. Your concerns regarding this allegation have been referred to the NRCs Office of the Inspector General.
On March 27, 2007, upon receipt of the allegation concerning inattentive security personnel at Peach Bottom, the NRC established an Allegation Review Board (ARB) to screen the allegation for safety concerns that would have an immediate impact on the safe operation of the facility. Based on the information available at the time, the NRC determined that the allegation did not raise an immediate issue for safe operation of the plant. On March 29, 2007, the ARB met to review the allegation together with insights provided by NRC staff regarding the validity of the concern. On April 4, 2007, the ARB conducted a second meeting to discuss the information necessary for evaluating and rendering a conclusion on the allegation, including technical review and inspection by NRC personnel and a written response from the licensee. At this meeting, the ARB determined that a written response from the licensee documenting their evaluation of the concern raised was appropriate.
In response to the ARB referral, the licensee reviewed its records of reported concerns and other documents, including security training and procedures, shift schedules, Corrective Action Program records, and work hour records for the period January 2006 through April 2007.
No instances of individual work hours or group average work hours exceeded the limits as defined in the 2003 NRC Order on worker fatigue. The licensee also interviewed security management and security personnel. On the basis of its review and the interviews, the licensee concluded that the allegation could not be substantiated. After reviewing the licensees response, NRC requested additional information from the licensee concerning how checks of the security officers on duty were conducted. Once these questions were resolved, the NRC determined that the investigation conducted by the licensee was comprehensive.
When the NRC became aware of the video in late September 2007, NRC immediately took steps to provide additional inspection at the site and dispatched an NRC Augmented Inspection Team (AIT) to collect, analyze, and document factual information and evidence sufficient to determine the causes, conditions, and circumstances pertaining to the event. On October 9, 2007, the AIT conducted a public meeting in the vicinity of Peach Bottom, during which the details of the inspection were discussed and the NRC responded to numerous questions from the public. The results of the AIT efforts were documented in an inspection report issued November 5, 2007.
The NRC continues to examine the issues of inattentive security officers at Peach Bottom. The NRC has the authority to administer oaths and affirmations or to issue subpoenas to require any individual to appear and testify, or appear and produce documents or evidence to assist in the evaluation. To date, the NRC staff has exercised its authority to administer oaths to several individuals with pertinent information and will continue to do so as necessary.
In an effort to prevent similar incidents and to re-emphasize licensee roles and responsibilities in this area, the NRC issued a security advisory to all reactor licensees nationwide on September 27, 2007. The security advisory re-emphasized NRC requirements regarding security officers attentiveness while on duty. In addition, NRC resident inspector oversight of the security forces at all nuclear power plants has been enhanced through additional random checks and unannounced drop-ins at security posts, including weekend and backshifts. The NRC continues to monitor security force performance at all sites.
I want to assure you that security at nuclear power plants is of the utmost importance to the NRC and that the ongoing review of the issues at Peach Bottom will be thorough and comprehensive. The NRC is currently evaluating previous allegations and findings at NRC-licensed facilities in relation to inattentive security officers and will take appropriate action as needed. The NRC will not hesitate to sanction any licensee for actions or failures that weaken defensive capabilities at nuclear facilities and will not tolerate retaliation against employees who raise concerns about these or other issues involving plant safety and security.
I also want to thank you for meeting with Roy Zimmerman, Director, Office of Nuclear Security and Incident Response, on October 17, 2007, to discuss your concerns and NRC activities. If you have any additional questions or comments, I would be willing to meet with you separately to listen to your views.
Sincerely,
/RA/
Dale E. Klein