NRC Regulatory Issue Summary 2007-17 Correction to Submittal for Preparation and Scheduling of Operator Licensing Examinations
ML072570637
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 09/13/2007
From: Funderburk C
Dominion, Dominion Resources Services
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
07-0517A, RIS-07-017
Download: ML072570637 (3)


Text

Dominion Resources Services, Inc.

i 0 0 o Dornin~onRoulevard, Glen Allen, VA .' trio0 Wch Address: www.dom.com September 13, 2007 United States Nuclear Regulatory Commission Serial No.: 07-0517A Attention: Document Control Desk NLOSIMBB Washington, DC 20555 Docket No.: 50-305 License Nos.: DPR-43 DOMINION ENERGY KEWAUNEE. INC.

KEWAUNEE POWER STATION NRC REGULATORY ISSUE

SUMMARY

2007-17 CORRECTION TO SUBMITTAL FOR PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS On August 16, 2007, Dominion Energy Kewaunee (DEK) submitted the requested NRC Form 536, "Operator Licensing Examination Data" in response to NRC Regulatory Issue Summary 2007-17. The information submitted incorrectly identified all operators scheduled to be tested (i.e. fifteen) rather than the number of examinations to be given (i.e. one) for the row entitled "Estimated Number of Licensee-Prepared Examination."

The actual number of licensee-prepared examinations needed is one for Calendar Years 2009 and 201 1.

Enclosed is the corrected "Operator Licensing Examination Data" form for Kewaunee Power Station. DEK apologizes for any inconvenience this may have caused.

No new commitments are intended by this letter. If you have any questions concerning this information, please contact Mr. David Llewellyn at (804) 273-4314.

Very truly yours, Director - Nuclear Licensing & Operations Support Dominion Resources Services, Inc.

for Dominion Energy Kewaunee, Inc.,

Attachment

SN 07-0517A Scheduling of Operator Licensing Examinations cc page 1 cc: U. S. Nuclear Regulatory Commission Region Ill 2443 Warrenville Road Suite 210 Lisle, IL 60532-4352 Mr. P. D. Milano Project Manager U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockvi lle Pike Mail Stop 8G9a Rockville, MD 20852-2738 Mr. S. C. Burton NRC Senior Resident Inspector Kewaunee Power Station

( KEWAUNEE POWER STATION I IX1 A. PROPOSED EXAMIf ATlON PREPARATION SCHEDULE PROPOSED NUMBER cysa. cyse cy- CYL I ESTIMATED NUMBER OF LICENSEEPREPARED EXAMINATIONS 0 1 0 1 NRC-PREPARED EXAMINATIONS 0 0 0 0

- - I - - - -

B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER -

CY 08 CY- 09 -

CY 10 -

CY 11 NUMBER OF REACTOR OPERATORS 0 5 0 5 NUMBER OF SENIOR REACTOR OPERATORS INSTANT 0 9 0 9 NUMBER OF SENIOR REACTOR OPERATORS UPGRADE 0 1 0 1 NUMBER OF SENIOR REACTOR OPERATORS - LIMITED O 0 0 0 PROPOSEDDATES PRIMARY DATE 04/13/2009 02/07/2011 ALTERNATE DATE 05/04/2009 02/21/2011 C. PROPOSED GENERIC FUNDAMENTALS E)(AMINATION (GFE) SCHEDULE cy 08- cy 09 PROPOSED -

NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBE ESTIMATED NUMBER OF CANDIDATES