Mid-cycle Performance Review & Inspection Plan - Letter
ML072480281
Person / Time
Site: Surry  Dominion icon.png
Issue date: 08/31/2007
From: Eugene Guthrie
NRC/RGN-II/DRP/RPB5
To: Christian D
Virginia Electric & Power Co (VEPCO)
References
Download: ML072480281 (5)


Text

August 31, 2007 Virginia Electric and Power Company ATTN: Mr. David A. Christian Senior Vice President and Chief Nuclear Officer Innsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - SURRY POWER STATION

Dear Mr. Christian:

On August 16, 2007, the NRC staff completed its performance review of the Surry Power Station for the first half of the calendar year 2007 assessment cycle. Our technical staff reviewed performance indicators for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.

This performance review and the enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and a resultant inspection plan.

Overall, Units 1 and 2 operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the Surry Power Station, for the most recent quarter was in the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all performance indicators indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. In addition to the ROP baseline inspections, we plan to conduct non-baseline inspections involving containment sump blockage and inspections of your Independent Spent Fuel Storage Installation.

The enclosed inspection plan details the inspections, less those related to physical protection scheduled through March 31, 2009. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.

The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.

VEPCO 2

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

The NRC is currently evaluating the scope and frequency of all baseline inspection procedures.

If the results of the evaluation, or any other circumstances, causes us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (404) 562-4662 with any questions you may have regarding this letter or the inspection plan.

Sincerely,

/RA/

Eugene F. Guthrie, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket Nos.: 50-280, 50-281 License Nos.: DPR-32, DPR-37

Enclosure:

Surry Inspection/Activity Plan (09/01/07 - 03/31/09) cc w/encl: (See page 3)

OFFICE RII:DRP RII:DRP SIGNATURE

/RA/

/RA/

NAME LGarner EGurthrie DATE 8/29/07 8/31/07 E-MAIL COPY?

YES NO YES NO YES NO YES NO YES NO YES NO YES NO

VEPCO 3

cc w/encl:

Chris L. Funderburk, Director Nuclear Licensing and Operations Support Virginia Electric & Power Company Electronic Mail Distribution Donald E. Jernigan Site Vice President Surry Power Station Virginia Electric & Power Company Electronic Mail Distribution Virginia State Corporation Commission Division of Energy Regulation P. O. Box 1197 Richmond, VA 23209 Lillian M. Cuoco, Esq.

Senior Counsel Dominion Resources Services, Inc.

Electronic Mail Distribution Attorney General Supreme Court Building 900 East Main Street Richmond, VA 23219

VEPCO 4

Distribution w/encl:

S. P. Lingam, NRR Richard Jervey, NRR C. Evans (Part 72 Only)

L. Slack, RII EICS OE Mail (email address if applicable)

RIDSNRRDIRS PUBLIC