MONTHYEARIR 05000338/20240052024-08-27027 August 2024 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2024005 and 05000339/2024005) IR 05000338/20230062024-02-28028 February 2024 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2023006 and 05000339/2023006 IR 05000338/20230052023-08-25025 August 2023 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338 2023005 and 05000339 2023005) IR 05000338/20220062023-03-0101 March 2023 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2022006 and 05000339/2022006 ML23046A1952023-02-15015 February 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000338/20220052022-08-30030 August 2022 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 Reports 05000338/2022005 and 05000339/2022005 IR 05000338/20210062022-03-0202 March 2022 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 (Reports No. 05000338/2021006 and 05000339/2021006) IR 05000338/20210052021-08-31031 August 2021 Mid-Cycle Letter Revised Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2021005 and 05000339/2021005) ML21165A1222021-06-14014 June 2021 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML21154A0662021-06-0202 June 2021 Notification of North Anna Power Station, Units 1 & 2 - Design Bases Assurance Inspection (Team) U.S. Nuuclear Regulatory Commission Inspection Report 05000338/2021010 and 05000339/2021010 ML21145A0052021-05-25025 May 2021 2021003 North Anna Nuclear Power Station Document Request Letter ML21075A0032021-03-12012 March 2021 Emergency Preparedness Exercise Inspection Request for Information for - Brunswick, Catawba, North Anna, Oconee, Vogtle 1 & 2 IR 05000338/20200062021-03-0303 March 2021 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 NRC Inspection Reports 05000338/2020006 and 05000339/2020006 ML21028A4352021-01-28028 January 2021 Notification of Target Set Inspection and Request for Information (NRC Inspection Report No. 05000338/2021404 and 05000339/2021404) ML21019A4512021-01-19019 January 2021 Notification of Inspection and Request for Information IR 05000338/20200052020-08-24024 August 2020 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 (Report 05000338/2020005 and 05000339/2020005) ML20223A3412020-08-10010 August 2020 003 Radiation Safety Baseline Inspection Information Request ML20218A4282020-08-0505 August 2020 Notification of Inspection and Request for Information ML20182A0332020-06-30030 June 2020 Notification of Inspection and Request for Information ML20175A5532020-06-23023 June 2020 Emergency Preparedness Exercise Inspection Request for Information IR 05000338/20190062020-03-0303 March 2020 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Reports 05000338/2019006 and 05000339/2019006 ML19326C9882019-11-21021 November 2019 Requalification Program Inspection North Anna Power Station IR 05000338/20190052019-08-27027 August 2019 Updated Inspection Plan for North Anna Power Station, Units 1 and 2, NRC Report 05000338/2019005 and 05000339/2019005 ML19235A1992019-08-23023 August 2019 Baseline Inservice Inspection RFI IR 05000338/20180062019-03-0404 March 2019 Annual Assessment Letter for North Anna, Units 1 and 2; NRC Inspection Report 05000338/2018006 and 05000339/2018006 ML19030A6962019-01-29029 January 2019 ISI RFI IR 05000338/20180052018-08-23023 August 2018 Updated Inspection Plan for North Anna Power Station Units 1 and 2, NRC Report 05000338/2018005 and 05000339/2018005 ML18059A0942018-02-28028 February 2018 EOC Assessment Letter IR 05000338/20170052017-08-21021 August 2017 Updated Inspection Plan for North Anna Power Station, Units 1 and 2 - Report 05000338/2017005 and 05000339/2017005 ML17156A0662017-06-0202 June 2017 Notification of Inspection and Request for Information IR 05000338/20160062017-03-0101 March 2017 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2016006 and 05000339/2016006 IR 05000338/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for North Anna Power Station, Units 1 and 2 - NRC Inspection Report 05000338, 339/2016005 ML16222A9132016-08-0808 August 2016 Notification of Inspection and Request for Information IR 05000338/20150062016-03-0202 March 2016 Annual Assessment Letter for North Anna Power Station Units 1 and 2 - NRC Inspection Report 05000338/2015006 and 05000339/2015006 ML16013A0622016-01-12012 January 2016 North Anna Power Station, Unit 2 - Notification of Inspection and Request for Information IR 05000338/20150052015-09-0101 September 2015 Mid-Cycle Letter for North Anna Power Station, Units 1 and 2 - NRC Assessment Report 05000338/2015005 and 05000339/2015005 IR 05000338/20140012015-03-0404 March 2015 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2014001 and 05000339/2014001 ML14245A1902014-09-0202 September 2014 Mid-Cycle Ltr 2014 IR 05000338/20130012014-03-0404 March 2014 Annual Assessment Letter for North Anna Power Station, Units 1 and 2 - Report 05000338/2013001 and 05000339/2013001 ML14022A0412014-01-21021 January 2014 TI-182 Phase 2 RFI Final ML13246A1322013-09-0303 September 2013 Mid Cycle Assessment Letter IR 05000338/20120012013-03-0404 March 2013 Annual Assessment Letter North Anna, Units 1 and 2, 05000338/2012001 and 05000339/2012001 ML13037A1712013-02-0101 February 2013 Notification of Inspection and Request for Information ML13032A5532013-02-0101 February 2013 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML12248A1102012-09-0404 September 2012 Mid Cycle Assessment Letter North Anna 2012 ML12235A2912012-08-17017 August 2012 IR 05000338-12-012, 05000339-12-012, on 10/28/2011, North Anna Power Station, Units 1 & 2 - Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML1206506412012-03-0505 March 2012 End of Cycle Assessment Report 22 ML1124400992011-09-0101 September 2011 Report 22, Inspection/Activity Plan ML1106303432011-03-0404 March 2011 Inspection/Activity Plan 03/01/2011 - 06/30/2012, EOC Report 22 ML1024402812010-09-0101 September 2010 Report 22 - 2010 Mid Cycle Inspection/Activity Plan 2024-08-27
[Table view] |
Text
Page 1 of 2 North Anna 08/31/2007 09:09:48 Inspection / Activity Plan Report 22 09/01/2007 - 03/31/2009 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB3-ISI - U1 INSERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 09/17/2007 09/21/2007 Baseline Inspections EB3SGISI - U1 STEAM GENERATOR ISI 1 1 IP 7111108P Inservice Inspection Activities - PWR 09/24/2007 09/28/2007 Baseline Inspections EB1-SUMP - PWR U1 CONTMT SUMP BLOCKAGE TI 2151/166 1 1 IP 2515/166 Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02] 09/30/2007 10/05/2007 Safety Issues OL RQ - REQUAL INSPECTION 3 1, 2 IP 7111111B Licensed Operator Requalification Program 01/14/2008 01/18/2008 Baseline Inspections OL EXAM - INITIAL EXAM PREP 4 1 V23283 NORTH ANNA/JUNE 2008 EXAM AT POWER FACILITIES 05/12/2008 05/16/2008 Not Applicable EB1-MODS - MODIFICATIONS-10CFR50.59 5 1, 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 06/02/2008 06/06/2008 Baseline Inspections 1, 2 IP 7111117B Permanent Plant Modifications 06/02/2008 06/06/2008 Baseline Inspections OL EXAM - INITIAL EXAM - WEEK 1 4 1 V23283 NORTH ANNA/JUNE 2008 EXAM AT POWER FACILITIES 06/02/2008 06/06/2008 Not Applicable OL EXAM - INITIAL EXAM - WEEK 2 4 1 V23283 NORTH ANNA/JUNE 2008 EXAM AT POWER FACILITIES 06/16/2008 06/20/2008 Not Applicable EB3-HS - HEAT SINK 1 1, 2 IP 7111107B Heat Sink Performance 06/23/2008 06/27/2008 Baseline Inspections EB3 - MR - MAINT RULE 1 1, 2 IP 7111112B Maintenance Effectiveness 07/14/2008 07/18/2008 Baseline Inspections PSB1-EP - EP EXERCISE 3 1, 2 IP 7111401 Exercise Evaluation 07/21/2008 07/25/2008 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 07/21/2008 07/25/2008 Baseline Inspections 1, 2 IP 71151-EP01 Drill/Exercise Performance 07/21/2008 07/25/2008 Baseline Inspections 1, 2 IP 71151-EP02 ERO Drill Participation 07/21/2008 07/25/2008 Baseline Inspections 1, 2 IP 71151-EP03 Alert & Notification System 07/21/2008 07/25/2008 Baseline Inspections PSB1-RP - RADIATION PROTECTION PREINSPECTION VISIT 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 08/11/2008 08/13/2008 Baseline Inspections PSB1-RP - RADIATION PROTECTION OCCUPATIONAL WK1 3 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 09/15/2008 09/19/2008 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 09/15/2008 09/19/2008 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 09/15/2008 09/19/2008 Baseline Inspections 1, 2 IP 71151-OR01 Occupational Exposure Control Effectiveness 09/15/2008 09/19/2008 Baseline Inspections 1 IP 71151-PR01 RETS/ODCM Radiological Effluent 09/15/2008 09/19/2008 Baseline Inspections This report does not include INPO and OUTAGE activities. Enclsoure This report shows only on-site and announced inspection procedures.
Page 2 of 2 North Anna 08/31/2007 09:09:48 Inspection / Activity Plan Report 22 09/01/2007 - 03/31/2009 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB3-ISI - UNIT 2 - ISI 1 2 IP 7111108P Inservice Inspection Activities - PWR 09/22/2008 09/26/2008 Baseline Inspections PSB1-RP - RADIATION PROTECTION OCCUPATIONAL WK2 2 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 09/29/2008 10/03/2008 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 09/29/2008 10/03/2008 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 09/29/2008 10/03/2008 Baseline Inspections 1, 2 IP 71151-OR01 Occupational Exposure Control Effectiveness 09/29/2008 10/03/2008 Baseline Inspections 2 IP 71151-PR01 RETS/ODCM Radiological Effluent 09/29/2008 10/03/2008 Baseline Inspections EB3SGISI - U2 SG ISI 1 2 IP 7111108P Inservice Inspection Activities - PWR 09/29/2008 10/06/2008 Baseline Inspections EB1-CDBI - COMPONENT DESIGN BASIS INSPECTION 8 1, 2 IP 7111121 Component Design Bases Inspection 10/27/2008 10/31/2008 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 11/17/2008 11/21/2008 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 12/01/2008 12/05/2008 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 12/15/2008 12/19/2008 Baseline Inspections This report does not include INPO and OUTAGE activities. Enclsoure This report shows only on-site and announced inspection procedures.