North Ann, Inspection Plan Report 22, for 09/01/2007 - 03/31/2009
ML072480273
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 08/31/2007
From:
NRC/RGN-II/DRP/RPB5
To:
References
Download: ML072480273 (2)


Text

Page 1 of 2 North Anna 08/31/2007 09:09:48 Inspection / Activity Plan Report 22 09/01/2007 - 03/31/2009 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB3-ISI - U1 INSERVICE INSPECTION 1 1 IP 7111108P Inservice Inspection Activities - PWR 09/17/2007 09/21/2007 Baseline Inspections EB3SGISI - U1 STEAM GENERATOR ISI 1 1 IP 7111108P Inservice Inspection Activities - PWR 09/24/2007 09/28/2007 Baseline Inspections EB1-SUMP - PWR U1 CONTMT SUMP BLOCKAGE TI 2151/166 1 1 IP 2515/166 Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02] 09/30/2007 10/05/2007 Safety Issues OL RQ - REQUAL INSPECTION 3 1, 2 IP 7111111B Licensed Operator Requalification Program 01/14/2008 01/18/2008 Baseline Inspections OL EXAM - INITIAL EXAM PREP 4 1 V23283 NORTH ANNA/JUNE 2008 EXAM AT POWER FACILITIES 05/12/2008 05/16/2008 Not Applicable EB1-MODS - MODIFICATIONS-10CFR50.59 5 1, 2 IP 7111102 Evaluation of Changes, Tests, or Experiments 06/02/2008 06/06/2008 Baseline Inspections 1, 2 IP 7111117B Permanent Plant Modifications 06/02/2008 06/06/2008 Baseline Inspections OL EXAM - INITIAL EXAM - WEEK 1 4 1 V23283 NORTH ANNA/JUNE 2008 EXAM AT POWER FACILITIES 06/02/2008 06/06/2008 Not Applicable OL EXAM - INITIAL EXAM - WEEK 2 4 1 V23283 NORTH ANNA/JUNE 2008 EXAM AT POWER FACILITIES 06/16/2008 06/20/2008 Not Applicable EB3-HS - HEAT SINK 1 1, 2 IP 7111107B Heat Sink Performance 06/23/2008 06/27/2008 Baseline Inspections EB3 - MR - MAINT RULE 1 1, 2 IP 7111112B Maintenance Effectiveness 07/14/2008 07/18/2008 Baseline Inspections PSB1-EP - EP EXERCISE 3 1, 2 IP 7111401 Exercise Evaluation 07/21/2008 07/25/2008 Baseline Inspections 1, 2 IP 7111404 Emergency Action Level and Emergency Plan Changes 07/21/2008 07/25/2008 Baseline Inspections 1, 2 IP 71151-EP01 Drill/Exercise Performance 07/21/2008 07/25/2008 Baseline Inspections 1, 2 IP 71151-EP02 ERO Drill Participation 07/21/2008 07/25/2008 Baseline Inspections 1, 2 IP 71151-EP03 Alert & Notification System 07/21/2008 07/25/2008 Baseline Inspections PSB1-RP - RADIATION PROTECTION PREINSPECTION VISIT 1 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 08/11/2008 08/13/2008 Baseline Inspections PSB1-RP - RADIATION PROTECTION OCCUPATIONAL WK1 3 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 09/15/2008 09/19/2008 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 09/15/2008 09/19/2008 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 09/15/2008 09/19/2008 Baseline Inspections 1, 2 IP 71151-OR01 Occupational Exposure Control Effectiveness 09/15/2008 09/19/2008 Baseline Inspections 1 IP 71151-PR01 RETS/ODCM Radiological Effluent 09/15/2008 09/19/2008 Baseline Inspections This report does not include INPO and OUTAGE activities. Enclsoure This report shows only on-site and announced inspection procedures.

Page 2 of 2 North Anna 08/31/2007 09:09:48 Inspection / Activity Plan Report 22 09/01/2007 - 03/31/2009 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type EB3-ISI - UNIT 2 - ISI 1 2 IP 7111108P Inservice Inspection Activities - PWR 09/22/2008 09/26/2008 Baseline Inspections PSB1-RP - RADIATION PROTECTION OCCUPATIONAL WK2 2 1, 2 IP 7112101 Access Control to Radiologically Significant Areas 09/29/2008 10/03/2008 Baseline Inspections 1, 2 IP 7112102 ALARA Planning and Controls 09/29/2008 10/03/2008 Baseline Inspections 1, 2 IP 7112202 Radioactive Material Processing and Transportation 09/29/2008 10/03/2008 Baseline Inspections 1, 2 IP 71151-OR01 Occupational Exposure Control Effectiveness 09/29/2008 10/03/2008 Baseline Inspections 2 IP 71151-PR01 RETS/ODCM Radiological Effluent 09/29/2008 10/03/2008 Baseline Inspections EB3SGISI - U2 SG ISI 1 2 IP 7111108P Inservice Inspection Activities - PWR 09/29/2008 10/06/2008 Baseline Inspections EB1-CDBI - COMPONENT DESIGN BASIS INSPECTION 8 1, 2 IP 7111121 Component Design Bases Inspection 10/27/2008 10/31/2008 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 11/17/2008 11/21/2008 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 12/01/2008 12/05/2008 Baseline Inspections 1, 2 IP 7111121 Component Design Bases Inspection 12/15/2008 12/19/2008 Baseline Inspections This report does not include INPO and OUTAGE activities. Enclsoure This report shows only on-site and announced inspection procedures.