North Anna Inspection / Activity Plan 09/01/2007 - 03/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/31/2007 09:09:48 Report 22 1
EB3-ISI
- U1 INSERVICE INSPECTION Baseline Inspections 09/17/2007 09/21/2007 1
7111108P IP Inservice Inspection Activities - PWR 1
EB3SGISI
- U1 STEAM GENERATOR ISI Baseline Inspections 09/24/2007 09/28/2007 1
7111108P IP Inservice Inspection Activities - PWR 1
EB1-SUMP
- PWR U1 CONTMT SUMP BLOCKAGE TI 2151/166 Safety Issues 09/30/2007 10/05/2007 1
2515/166 IP Pressurized Water Reactor Containment Sump Blockage [NRC GENERIC LETTER 2004-02]
- REQUAL INSPECTION Baseline Inspections 01/14/2008 01/18/2008 1, 2 7111111B IP Licensed Operator Requalification Program 4
OL EXAM
- INITIAL EXAM PREP Not Applicable 05/12/2008 05/16/2008 1
V23283 NORTH ANNA/JUNE 2008 EXAM AT POWER FACILITIES 5
EB1-MODS
- MODIFICATIONS-10CFR50.59 Baseline Inspections 06/02/2008 06/06/2008 1, 2 7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 06/02/2008 06/06/2008 1, 2 7111117B IP Permanent Plant Modifications 4
OL EXAM
- INITIAL EXAM - WEEK 1 Not Applicable 06/02/2008 06/06/2008 1
V23283 NORTH ANNA/JUNE 2008 EXAM AT POWER FACILITIES 4
OL EXAM
- INITIAL EXAM - WEEK 2 Not Applicable 06/16/2008 06/20/2008 1
V23283 NORTH ANNA/JUNE 2008 EXAM AT POWER FACILITIES 1
EB3-HS
- HEAT SINK Baseline Inspections 06/23/2008 06/27/2008 1, 2 7111107B IP Heat Sink Performance 1
EB3 - MR
- MAINT RULE Baseline Inspections 07/14/2008 07/18/2008 1, 2 7111112B IP Maintenance Effectiveness 3
PSB1-EP
- EP EXERCISE Baseline Inspections 07/21/2008 07/25/2008 1, 2 7111401 IP Exercise Evaluation Baseline Inspections 07/21/2008 07/25/2008 1, 2 7111404 IP Emergency Action Level and Emergency Plan Changes Baseline Inspections 07/21/2008 07/25/2008 1, 2 71151-EP01 IP Drill/Exercise Performance Baseline Inspections 07/21/2008 07/25/2008 1, 2 71151-EP02 IP ERO Drill Participation Baseline Inspections 07/21/2008 07/25/2008 1, 2 71151-EP03 IP Alert & Notification System 1
PSB1-RP
- RADIATION PROTECTION PREINSPECTION VISIT Baseline Inspections 08/11/2008 08/13/2008 1, 2 7112101 IP Access Control to Radiologically Significant Areas 3
PSB1-RP
- RADIATION PROTECTION OCCUPATIONAL WK1 Baseline Inspections 09/15/2008 09/19/2008 1, 2 7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 09/15/2008 09/19/2008 1, 2 7112102 IP ALARA Planning and Controls Baseline Inspections 09/15/2008 09/19/2008 1, 2 7112202 IP Radioactive Material Processing and Transportation Baseline Inspections 09/15/2008 09/19/2008 1, 2 71151-OR01 IP Occupational Exposure Control Effectiveness Baseline Inspections 09/15/2008 09/19/2008 1
71151-PR01 IP RETS/ODCM Radiological Effluent This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Enclsoure
North Anna Inspection / Activity Plan 09/01/2007 - 03/31/2009 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/31/2007 09:09:48 Report 22 1
EB3-ISI
- UNIT 2 - ISI Baseline Inspections 09/22/2008 09/26/2008 2
7111108P IP Inservice Inspection Activities - PWR 2
PSB1-RP
- RADIATION PROTECTION OCCUPATIONAL WK2 Baseline Inspections 09/29/2008 10/03/2008 1, 2 7112101 IP Access Control to Radiologically Significant Areas Baseline Inspections 09/29/2008 10/03/2008 1, 2 7112102 IP ALARA Planning and Controls Baseline Inspections 09/29/2008 10/03/2008 1, 2 7112202 IP Radioactive Material Processing and Transportation Baseline Inspections 09/29/2008 10/03/2008 1, 2 71151-OR01 IP Occupational Exposure Control Effectiveness Baseline Inspections 09/29/2008 10/03/2008 2
71151-PR01 IP RETS/ODCM Radiological Effluent 1
EB3SGISI
- U2 SG ISI Baseline Inspections 09/29/2008 10/06/2008 2
7111108P IP Inservice Inspection Activities - PWR 8
EB1-CDBI
- COMPONENT DESIGN BASIS INSPECTION Baseline Inspections 10/27/2008 10/31/2008 1, 2 7111121 IP Component Design Bases Inspection Baseline Inspections 11/17/2008 11/21/2008 1, 2 7111121 IP Component Design Bases Inspection Baseline Inspections 12/01/2008 12/05/2008 1, 2 7111121 IP Component Design Bases Inspection Baseline Inspections 12/15/2008 12/19/2008 1, 2 7111121 IP Component Design Bases Inspection This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.