J on athanRowley- Re: *VY SER issuance... ,age.-

From: Jonathan Rowley To: Michael Modes; Richard Conte Date: 07/25/2007 5:45:36 PM

Subject:

Re: VY SER issuance Attached is a mini-communications plan/briefing sheet for use by anyone who might be asked questions about the issuance of the final SER for VY.

>>> Richard Conte 07/25/2007 5:28:19 PM >>>

does this mean the ser will be final.

are there any key messages like summary of open issues from draft and essence of how got resolved.

>>> Jonathan Rowley 07/25/2007 5:21 PM >>>

On Wednesday August 1, 2007, the DLR will issue the Safety Evaluation Report Related to the License Renewal of Vermont Yankee Nuclear Power Station.

I had previously mentioned that there would be an Open Item that we would not be able to resolve by August 1, thus having to issue and Updated SER with Open Items. Hard work and diligence by both the staff and the applicant has proven otherwise. The RAI is resolved and there will be no Open Item.

Therefore, the original schedule is back in effect.

CC: David McIntyre; Diane Screnci; Glenn Meyer; Marjorie McLaughlin; Pao-Tsin Kuo; Rajender Auluck; Raymond Powell; Samson Lee

c:\ternp\GW}00008.TMPPaei .Page 1.1 Mail Envelope Properties (46A7C480.615 : 12 : 35182)

Subject:

Re: VY SER issuance Creation Date 07/25/2007 5:45:36 PM From: Jonathan Rowley Created By: JGR(inrc.gov Recipients Action Date & Time nrc.gov OWGWPOO1.HQGWDOOI Delivered 07/25/2007 5:45:42 PM RCA CC (Rajender Auluck) Opened 07/26/2007 7:27:22 AM nrc.gov OWGWPOO4.HQGWDOOI Delivered 07/25/2007 5:45:45 PM PTK CC (Pao-Tsin Kuo) Opened 07/26/2007 7:40:04 AM nrc.gov TWGWPO01.HQGWDO01 Delivered 07/25/2007 5:45:42 PM DTM CC (David McIntyre)

SSLI CC (Samson Lee) Opened 07/26/2007 6:10:39 AM nrc.gov kpl_po.KPDO Delivered 07/25/2007 5:45:52 PM DPS CC (Diane Screnci) Opened 07/26/2007 8:09:13 AM GWM CC (Glenn Meyer) Opened 07/26/2007 7:27:58 AM MCM (Michael Modes) Opened 07/25/2007 8:45:47 PM MMM3 CC (Marjorie McLaughlin) Opened 07/26/2007 6:46:16 AM RJC (Richard Conte) Opened 07/26/2007 10:17:36 PM RJP CC (Raymond Powell) Opened 07/26/2007 6:36:44 AM

I c:temp\GW)}00008.TMP -Pýage2 !1 Page" Post Office Delivered Route OWGWPO0I.HQGWDO0I 07/25/2007 5:45:42 PM nrc.gov OWGWPOO4.HQGWDO0I 07/25/2007 5:45:45 PM nrc.gov TWGWPOO1 .HQGWDOO1 07/25/2007 5:45:42 PM nrc.gov kp Ipo.KPDO 07/25/2007 5:45:52 PM nrc.gov Files Size Date & Time MESSAGE 1441 07/25/2007 5:45:35 PM TEXT.htm 1160 Communication plan for Issuance of Vermont Yankee SER.wpd 9103 07/25/2007 5:43:06 PM Options Auto Delete: No Expiration Date: None Notify Recipients: Yes Priority: Standard ReplyRequested: No Return Notification:

Send Notification when Opened Concealed

Subject:

No Security: Standard To Be Delivered: Immediate Status Tracking: Delivered & Opened

Jonathan Rowley - Communication plan for Issuance of Vermont Yankee SER.wpd Page.

.Pagel .,j Communication plan for Issuance of Vermont Yankee SER for license renewal Final Safety Evaluation Report for license renewal at Vermont Yankee will be issued on August 1, 2007; OPA will issue a press release; key personnel in Region I and OCA will also be notified On the basis of its evaluation of the LRA, supplements to the LRA, and responses to RAIs, the NRC staff concluded that the requirements of 10 CFR 54.29(a) have been met

  • The draft SER was issued on March 30, 2007 In the draft SER, there where no open items and six confirmatory items that required resolution prior to the staff making its final conclusion. The six confirmatory items have been resolved. There was an additional RAI on metal fatigue TLAA that resulted from the ACRS sub-committee meeting in June 2007. That RAI was resolved prior to issuance of the final SER The Atomic Safety and Licensing Board plans to visit the site on October 10, 2007; listen to public limited appearances on October 11, 2007; and begin hearings in January-February 2008 Three safety contentions have been accepted related to aging management programs for steam dryers, metal fatigue, and flow-accelerated corrosion For more information on the Vermont Yankee Nuclear Power Station safety review, contact Jonathan Rowley, jgr@nrc.gov or 301-415-4053