ML072330086

From kanterella
Jump to navigation Jump to search
Preparation and Scheduling of Operator Licensing Examination - NRC Regulatory Issue Summary (RIS) 2006-15
ML072330086
Person / Time
Site: Sequoyah  Tennessee Valley Authority icon.png
Issue date: 08/20/2007
From: Morris G
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RIS-06-015, RIS-07-017
Download: ML072330086 (4)


Text

August 20, 2007 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:

In the Matter of ) Docket Nos. 50-327 Tennessee Valley Authority ) 50-328 SEQUOYAH NUCLEAR PLANT (SQN) - PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS - NRC REGULATORY ISSUE

SUMMARY

(RIS) 2006-15 This letter is in response to the NRC RIS 2007-17 dated July 12, 2007. The enclosure provides the requested information.

If you have any questions, please call me at (423) 843-6672.

Sincerely, Original signed by James W. Proffitt Glenn W. Morris Manager, Site Licensing and Industry Affairs Enclosure cc (Enclosure):

Dr. William D. Travers Regional Administrator, Region II ATTN: J. H. Moorman U.S. Nuclear Regulatory Commission Sam Nunn Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, Georgia 30303-8931

ENCLOSURE SEQUOYAHNUCLEARPLANT PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS

NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 08/31/2008 (82005)

Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for operator examinations. Send comments regarding burden OPERATOR LICENSING estimate to the Records and FOIAIPrivacy Services Branch IT-5 F53), U.S.

Nuclear Regulatory Commission, Washington, DC 20555000 , or by Internet e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information EXAMINATION DATA and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

FACILITY NRC REGION Sequoyah Nuclear Plant RII A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER -

CY 08 CY 09 CY 09 CY 09 ESTIMATED NUMBER OF LICENSEE-PREPARED 1 1 1 1 EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED O O O O EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER -

CY 08 -

CY 09 -

CY 09 -

CY 09 1

NUMBER OF REACTOR 1 5 0 4 OPERATORS NUMBER OF SENIOR REACTOR 5 8 8 OPERATORS - INSTANT 6

NUMBER OF SENIOR REACTOR OPERATORS - UPGRADE I 0 0 0 NUMBER OF SENIOR REACTOR 0 0 0 0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE 01/28/2008 01/26/2009 06/0112009 12/07/2009 ALTERNATE DATE 0211112008 03/03/2009 07/06/2009 01/25/2010 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY 08 cy 09 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF 0 0 12 0 0 12 0 0 CANDIDATES NRC FORM 536 (b2005) PRINTED ON RECYCLED PAPER

L NRC FORM 536 U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB: NO. 3150-0131 EXPIRES: 08131/2008 (82005)

Estimated burden per response to comply with this voluntary information collection request: 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br />. This information collection is used to plan budgets and resources for operator examinations. Send comments regarding burden OPERATOR LICENSING Nuclear Regulatory estimate to the Records Commission, and FOINPrivacy Washington, Services DC 20555000 , or F53),

Branch (T-5 by Internet U.S.

e-mail to infocollects@nrc.gov, and to the Desk Officer, Office of Information EXAMINATION DATA and Regulatory Affairs, NEOB-10202, (3150-0131), Office of Management and Budget, Wash~ngton,DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, h e NRC may not conduct or sponsor, and a person is not required to respond to, the information collectton.

FACILITY NRC REGION Sequoyah Nuclear Plant RII A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER -

CY 10 -

CY 11 CY - CY -

ESTIMATED NUMBER OF LICENSEE-PREPARED I I EXAMINATIONS ESTIMATED NUMBER OF NRC-PREPARED 0 0 EXAMINATIONS

6. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER -

CY 10 -

CY 11 CY - CY -

NUMBER OF REACTOR 4 4 OPERATORS NUMBER OF SENIOR REACTOR 8 8

OPERATORS - INSTANT NUMBER OF SENIOR REACTOR 0 0 OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR 0 0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE 08/26/20 10 08/22/2011 ALTERNATE DATE 0911312010 0911a201 1 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY CY PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED NUMBER OF CANDIDATES NRC FORM 536 (8-2005) PRINTED ON RECYCLED PAPER