Category:Letter
MONTHYEARIR 05000259/20240032024-11-0404 November 2024 Integrated Inspection Report 05000259/2024003 and 05000260/2024003 and 05000296/2024003 CNL-24-043, Application for Subsequent Renewed Operating Licenses, Second Safety Supplement2024-11-0101 November 2024 Application for Subsequent Renewed Operating Licenses, Second Safety Supplement ML24305A1692024-10-31031 October 2024 Site Emergency Plan Implementing Procedure Revision 05000259/LER-2024-003, Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators2024-10-29029 October 2024 Valid Specified System Actuation Caused the Automatic Start of Emergency Diesel Generators 05000259/LER-2024-001-02, Secondary Containment Isolation Valve Inoperable Due to Mechanical Failure2024-10-28028 October 2024 Secondary Containment Isolation Valve Inoperable Due to Mechanical Failure ML24299A2632024-10-25025 October 2024 Response to Apparent Violation in NRC Inspection Report 05000260/2024090, EA-24-075 ML24289A1232024-10-24024 October 2024 Letter to James Barstow Re Environmental Scoping Summary Report for Browns Ferry CNL-24-074, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-10-23023 October 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24308A0042024-10-16016 October 2024 Ahc 24-1578 Environmental Review of the Browns Ferry Nuclear Plant, Units 1, 2 and 3 Subsequent License Renewal Application Limestone County CNL-24-077, Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 12024-10-0909 October 2024 Application for Subsequent Renewed Operating Licenses, Response to Request for Additional Information, Set 1 ML24270A2162024-09-27027 September 2024 Notice of Intentions Regarding Preliminary Finding from NRC Inspection Report 05000260/2024090, EA-24-075 CNL-24-060, Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description2024-09-24024 September 2024 Supplement to Request for Approval of the Tennessee Valley Authority Nuclear Quality Assurance Program Description ML24262A1502024-09-24024 September 2024 Requalification Program Inspection - Browns Ferry Nuclear Plant ML24262A0602024-09-23023 September 2024 Summary of August 19, 2024, Meeting with Tennessee Valley Authority Regarding a Proposed Supplement to the Tennessee Valley Authority Nuclear Quality Assurance Plan ML24263A2952024-09-19019 September 2024 Site Emergency Plan Implementing Procedure Revision CNL-24-065, Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-09-18018 September 2024 Tennessee Valley Authority – Central Emergency Control Center Emergency Plan Implementing Procedure Revisions IR 05000260/20240902024-09-17017 September 2024 NRC Inspection Report 05000260/2024090 and Preliminary White Finding and Apparent Violation - 1 CNL-24-062, Cycle 16 Reload Analysis Report2024-09-16016 September 2024 Cycle 16 Reload Analysis Report ML24255A8862024-09-10010 September 2024 Core Operating Limits Report for Cycle 16 Operation, Revision 0 ML24239A3332024-09-0303 September 2024 Full Audit Plan IR 05000259/20244042024-09-0303 September 2024 Cyber Security Inspection Report 05000259/2024404 and 05000260-2024404 and 05000296/2024404-Cover Letter IR 05000259/20240052024-08-26026 August 2024 Updated Inspection Plan for Browns Ferry Nuclear Plant, Units 1, 2 and 3 - Report 05000259/2024005, 05000260/2024005 and 05000296/2024005 ML24225A1682024-08-16016 August 2024 – Notification of Inspection and Request IR 05000259/20244022024-08-0606 August 2024 Security Baseline Inspection Report 05000259/2024402 and 05000260/2024402 and 05000296/2024402 ML24219A0272024-08-0606 August 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000259/20240022024-08-0202 August 2024 Brown Ferry Nuclear Plant – Integrated Inspection Report05000259/2024002 and 05000260/2024002 and 05000296/2024002 ML24199A0012024-07-22022 July 2024 Clarification and Correction to Exemption from Requirement of 10 CFR 37.11(c)(2) ML24172A1342024-07-15015 July 2024 Exemptions from 10 CFR 37.11(C)(2) (EPID L-2023-LLE-0024) - Letter ML24183A4142024-07-10010 July 2024 – License Renewal Regulatory Limited Scope Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-SLE-0000) (Docket Numbers: 50-259, 50-260, and 50-296) 05000296/LER-2024-003, Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints2024-07-0808 July 2024 Main Steam Relief Valves Lift Settings Outside of Technical Specifications Required Setpoints 05000259/LER-2024-001-01, Inoperability of Unit 3 Diesel Generator Due to Relay Failure2024-07-0303 July 2024 Inoperability of Unit 3 Diesel Generator Due to Relay Failure ML24184A1142024-07-0202 July 2024 Site Emergency Plan Implementing Procedure Revision ML24183A3842024-07-0101 July 2024 Registration of Use of Cask to Store Spent Fuel (MPC-364, -365) ML24179A0282024-06-26026 June 2024 Evaluation of Effects of Out-of-Limits Condition as Described in IWB-3720(a) 05000259/LER-2024-002, Reactor Scram Due to Generator Step-Up Transformer Failure2024-06-24024 June 2024 Reactor Scram Due to Generator Step-Up Transformer Failure ML24175A0042024-06-23023 June 2024 Interim Report of a Deviation or Failure to Comply Associated with a Valve in the Unit 3 High Pressure Coolant Injection System ML24176A1132024-06-23023 June 2024 American Society of Mechanical Engineers, Section XI, Fourth 10 Year Inspection Interval, Inservice Inspection, System Pressure Test, Containment Inspection, and Repair and Replacement Programs, Owner’S Activity Report Cycle 21 Oper ML24089A1152024-06-21021 June 2024 Transmittal Letter, Environmental Assessments and Findings of No Significant Impact Related to Exemption Requests from 10 CFR 37.11(c)(2) ML24155A0042024-06-18018 June 2024 Proposed Alternative to the Requirements of the ASME Code (Revised Alternative Request 0-ISI-47) ML24158A5312024-06-0606 June 2024 Registration of Use of Cask to Store Spent Fuel (MPC-361, -362, -363) ML24071A0292024-06-0505 June 2024 Subsequent License Renewal Application Enclosure 3 - Proprietary Determination Letter ML24068A2612024-06-0505 June 2024 SLRA Fluence Methodology Report - Proprietary Determination Letter IR 05000259/20244032024-05-22022 May 2024 – Security Baseline Report 05000259/2024403 and 05000260/2024403 and 05000296/2024403 05000260/LER-2024-002, High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation2024-05-20020 May 2024 High Pressure Coolant Injection Inoperable Due to Rupture Disc Failure and Resulting System Isolation ML24141A0482024-05-17017 May 2024 EN 56958_1 Ametek Solidstate Controls, Inc ML24136A0702024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000259/20240012024-05-14014 May 2024 Integrated Inspection Report 05000259/2024001, 05000260/2024001, and 05000296/2024001 CNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML24123A2012024-05-0202 May 2024 NRC Cybersecurity Baseline Inspection (NRC Inspection Report 05000259/2024404, 05000260-2024404, 05000296/2024404) and Request for Information ML24122A6852024-05-0101 May 2024 2023 Annual Radioactive Effluent Release Report and Offsite Dose Calculation Manual 2024-09-03
[Table view] Category:License-Operator
MONTHYEARML22290A1482022-10-17017 October 2022 Notification of Licensed Operator Initial Examination 05000259/2023301, 05000260/2023301, 05000296/2023301 ML22161A9392022-06-10010 June 2022 301 Exam Report Items, RO Written Exam ML22132A2542022-05-10010 May 2022 Bf 2022-301 Approval Letter ML22077A1142022-03-18018 March 2022 Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML21277A1432021-10-0404 October 2021 301, Corporate Notification Letter (210-day Ltr) ML21256A2182021-09-13013 September 2021 301 Exam 2B Administrative Items (Normal Release) ML21256A1852021-09-13013 September 2021 301 Exam Administrative Items (2 Year Delayed Release) ML21256A2932021-09-13013 September 2021 301 Exam Final Items (2 Year Delayed Release) (1) ML21174A0802021-06-23023 June 2021 301 Final SRO Written Exam (2-Year Delayed Release) ML21174A0782021-06-23023 June 2021 301 Final RO Written Exam (2-Year Delayed Release) ML21131A0252021-05-10010 May 2021 301 Examaination Approval Letter ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 ML20274A0982020-09-29029 September 2020 Bf 2021-301 Browns Ferry Nuclear Plant - Notification of Licensed Operator Initial Examination 05000259/2021301, 05000260/2021301, 05000296/2021301 ML20007F7572020-01-0707 January 2020 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2020 ML19018A0882019-01-17017 January 2019 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2019 ML18207A2902018-07-26026 July 2018 Updated Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations ML18198A5332018-07-12012 July 2018 Operator Licensing Written Examination Approval 05000259/2018301, 05000260/2018301 and 05000296/2018301 ML18117A1692018-04-27027 April 2018 Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations ML18110A2472018-04-17017 April 2018 March 2018 - Browns Ferry NRC Generic Fundamentals Examination Results ML18086B0442018-02-16016 February 2018 Facility Cover Letter - Rii - March 2018 - GFE ML17212B1682017-07-31031 July 2017 Exam Admin Items (Immediate Release) - ADAMS 2D ML17212B1492017-07-31031 July 2017 Exam Final Items - ADAMS 2B - Delay Release 2 Yrs ML17212B1602017-07-31031 July 2017 Exam Admin Items - ADAMS 2C - Delay Release 2 Yrs ML17132A1322017-05-12012 May 2017 Senior Reactor Operator Initial License Operating Examination - Post Examination Response ML17131A2002017-05-11011 May 2017 Final Ro/Sro Written Examination 05000259/2017-301, 05000260/2017-301 and 05000296/2017301 - Delay Release Two Years ML17125A1352017-05-0505 May 2017 Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations ML17125A3412017-04-17017 April 2017 Operator Licensing Written Examination Approval 05000259, 260, 296/2017301 ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 ML16126A3672016-05-0303 May 2016 No Candidates for the Generic Fundamentals Examination Section of the Written Operator Licensing Examination ML16049A0862016-02-18018 February 2016 Initial Exam 2015-302 General Correspondence ML16049A0322016-02-18018 February 2016 Initial Exam 2015-302 Draft Administrative Documents ML16049A0802016-02-18018 February 2016 Initial Exam 2015-302 Final Sim In-plant JPMs ML16049A0772016-02-18018 February 2016 Initial Exam 2015-302 Final Simulator Scenarios ML16049A0712016-02-18018 February 2016 Initial Exam 2015-302 Draft Sim In-plant JPMs ML16049A0702016-02-18018 February 2016 Initial Exam 2015-302 Draft Simulator Scenarios ML16049A0752016-02-18018 February 2016 Initial Exam 2015-302 Final Administrative Documents ML16049A0822016-02-18018 February 2016 Initial Exam 2015-302 Final Administrative JPMs ML16049A0722016-02-18018 February 2016 Initial Exam 2015-302 Draft Administrative JPMs ML15348A0562015-12-14014 December 2015 Forwards Response to Reactor Operator and Senior Reactor Operator Initial License Written Examinations - Post Examination Response ML15351A1182015-12-0808 December 2015 Initial Exam 2015-302 Post Exam Comments ML15342A3732015-12-0707 December 2015 Initial Exam 2015-302 Final SRO Written Exam ML15342A3682015-11-24024 November 2015 Initial Exam 2015-302 Final RO Written Exam ML15280A3432015-10-0505 October 2015 September 2015 NRC Generic Fundamentals Examination Results ML15175A4022015-06-23023 June 2015 Notification of Licensed Operator Initial Examination 05000259/2015302, 05000260/2015302, and 05000296/2015302 ML15079A1252015-03-20020 March 2015 Initial Exam 2015-301 Final Sim_IN-Plant JPMs ML15079A1212015-03-20020 March 2015 Initial Exam 2015-301 Final Simulator Scenarios ML15079A1102015-03-20020 March 2015 Initial Exam 2015-301 Final Administrative Documents ML15079A1062015-03-20020 March 2015 Initial Exam 2015-301 Draft Administrative JPMs ML15079A1042015-03-20020 March 2015 Initial Exam 2015-301 Draft Sim_IN-Plant JPMs ML15079A0982015-03-20020 March 2015 Initial Exam 2015-301 Draft Simulator Scenarios 2022-06-10
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML22290A1482022-10-17017 October 2022 Notification of Licensed Operator Initial Examination 05000259/2023301, 05000260/2023301, 05000296/2023301 ML22161A9392022-06-10010 June 2022 301 Exam Report Items, RO Written Exam ML22132A2542022-05-10010 May 2022 Bf 2022-301 Approval Letter ML22077A1142022-03-18018 March 2022 Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations ML21277A1432021-10-0404 October 2021 301, Corporate Notification Letter (210-day Ltr) ML21256A1852021-09-13013 September 2021 301 Exam Administrative Items (2 Year Delayed Release) ML21256A2182021-09-13013 September 2021 301 Exam 2B Administrative Items (Normal Release) ML21256A2932021-09-13013 September 2021 301 Exam Final Items (2 Year Delayed Release) (1) ML21174A0802021-06-23023 June 2021 301 Final SRO Written Exam (2-Year Delayed Release) ML21174A0782021-06-23023 June 2021 301 Final RO Written Exam (2-Year Delayed Release) ML21131A0252021-05-10010 May 2021 301 Examaination Approval Letter ML21019A3932021-01-11011 January 2021 1 GFE Annual Letter for Fy 2021 ML20274A0982020-09-29029 September 2020 Bf 2021-301 Browns Ferry Nuclear Plant - Notification of Licensed Operator Initial Examination 05000259/2021301, 05000260/2021301, 05000296/2021301 ML18207A2902018-07-26026 July 2018 Updated Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations ML18198A5332018-07-12012 July 2018 Operator Licensing Written Examination Approval 05000259/2018301, 05000260/2018301 and 05000296/2018301 ML18117A1692018-04-27027 April 2018 Response to NRC Regulatory Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examinations ML18110A2472018-04-17017 April 2018 March 2018 - Browns Ferry NRC Generic Fundamentals Examination Results ML17212B1602017-07-31031 July 2017 Exam Admin Items - ADAMS 2C - Delay Release 2 Yrs ML17212B1492017-07-31031 July 2017 Exam Final Items - ADAMS 2B - Delay Release 2 Yrs ML17212B1682017-07-31031 July 2017 Exam Admin Items (Immediate Release) - ADAMS 2D ML17132A1322017-05-12012 May 2017 Senior Reactor Operator Initial License Operating Examination - Post Examination Response ML17125A1352017-05-0505 May 2017 Response to NRC Regulatory Issue Summary 2017-03, Preparation and Scheduling of Operator Licensing Examinations ML17125A3412017-04-17017 April 2017 Operator Licensing Written Examination Approval 05000259, 260, 296/2017301 ML17032A2792017-01-27027 January 2017 Annual Letter - Generic Fundamentals Examination (GFE) Section of the Written Operator Licensing Examination for 2017 ML16049A0722016-02-18018 February 2016 Initial Exam 2015-302 Draft Administrative JPMs ML16049A0702016-02-18018 February 2016 Initial Exam 2015-302 Draft Simulator Scenarios ML16049A0712016-02-18018 February 2016 Initial Exam 2015-302 Draft Sim In-plant JPMs ML16049A0752016-02-18018 February 2016 Initial Exam 2015-302 Final Administrative Documents ML16049A0772016-02-18018 February 2016 Initial Exam 2015-302 Final Simulator Scenarios ML16049A0802016-02-18018 February 2016 Initial Exam 2015-302 Final Sim In-plant JPMs ML16049A0862016-02-18018 February 2016 Initial Exam 2015-302 General Correspondence ML16049A0322016-02-18018 February 2016 Initial Exam 2015-302 Draft Administrative Documents ML16049A0822016-02-18018 February 2016 Initial Exam 2015-302 Final Administrative JPMs ML15348A0562015-12-14014 December 2015 Forwards Response to Reactor Operator and Senior Reactor Operator Initial License Written Examinations - Post Examination Response ML15351A1182015-12-0808 December 2015 Initial Exam 2015-302 Post Exam Comments ML15342A3732015-12-0707 December 2015 Initial Exam 2015-302 Final SRO Written Exam ML15342A3682015-11-24024 November 2015 Initial Exam 2015-302 Final RO Written Exam ML15280A3432015-10-0505 October 2015 September 2015 NRC Generic Fundamentals Examination Results ML15175A4022015-06-23023 June 2015 Notification of Licensed Operator Initial Examination 05000259/2015302, 05000260/2015302, and 05000296/2015302 ML15079A1102015-03-20020 March 2015 Initial Exam 2015-301 Final Administrative Documents ML15079A0742015-03-20020 March 2015 Initial Exam 2015-301 Draft Administrative Documents ML15079A0822015-03-20020 March 2015 Initial Exam 2015-301 Draft RO Written Exam ML15079A0932015-03-20020 March 2015 Initial Exam 2015-301 Draft SRO Written Exam ML15079A0982015-03-20020 March 2015 Initial Exam 2015-301 Draft Simulator Scenarios ML15079A1042015-03-20020 March 2015 Initial Exam 2015-301 Draft Sim_IN-Plant JPMs ML15079A1062015-03-20020 March 2015 Initial Exam 2015-301 Draft Administrative JPMs ML15079A1212015-03-20020 March 2015 Initial Exam 2015-301 Final Simulator Scenarios ML15079A1252015-03-20020 March 2015 Initial Exam 2015-301 Final Sim_IN-Plant JPMs ML15079A1282015-03-20020 March 2015 Initial Exam 2015-301 Final Administrative JPMs ML15079A1332015-03-20020 March 2015 Initial Exam 2015-301 General Correspondence and Miscellaneous Documents 2022-06-10
[Table view] |
Text
August 20, 2007 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Stop: OWFN P1-35 Washington, D.C. 20555-0001
Dear Sir:
In the Matter of ) Docket Nos. 50-259 Tennessee Valley Authority ) 50-260 50-296 BROWNS FERRY NUCLEAR PLANT (BFN) - REPLY TO NRC REGULATORY ISSUE
SUMMARY
(RIS) 2007-17, PREPARATION AND SCHEDULING OF OPERATOR LICENSING EXAMINATIONS This letter responds to the subject NRC RIS dated July 12, 2007. In the RIS, NRC requested specific information related to: (A) proposed examination preparation schedule for the number of examinations that need to be prepared during calendar years (CY) 2008-2011, (B) schedule for initial operator license examinations, including the number of applicants to be tested and the proposed primary and alternate dates of the examinations, through CY 2011 and (C) proposed generic fundamentals examination (GFE) schedule, including the number of candidates that plan to take the GFE in CY 2008 and CY 2009.
Enclosed is a completed NRC Form 536, Operator Licensing Examination Data, which provides BFNs current schedules for the specific information requested in the RIS. In calendar year 2010, TVA plans to conduct two examinations.
BFN plans to prepare the written examinations during calendar years 2008 to 2011.
Nuclear Regulatory Commission Page 2 August 20, 2007 If you have any questions concerning these schedules for the graded written examinations or the proposed examination schedules, please contact E. R. Scillian at (256) 729-3439.
Sincerely, Original signed by:
D. T. Langley Manager of Site Licensing and Industry Affairs Enclosure cc: See page 3
U.S. Nuclear Regulatory Commission Page 3 August 20, 2007 Enclosure cc (Enclosure):
Dr. William D. Travers, Regional Administrator U.S. Nuclear Regulatory Commission Sam Nunn Atlanta Federal Center 61 Forsyth Street S.W., Suite 23T85 Atlanta, Georgia 30303-8931 Mr. Robert C. Haag, Chief Operator Licensing and Human Performance Branch U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street S.W., Suite 23T85 Atlanta, Georgia 30303-8931 Mr. James H. Moorman, III, Branch Chief U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street S.W., Suite 23T85 Atlanta, Georgia 30303-8931 NRC Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, Alabama 35611-6970
U.S. Nuclear Regulatory Commission Page 4 August 20, 2007 JEE:JEW:BAB Enclosure cc(Enclosure):
T. D. Elms, POB 2E-BFN D. C. Matherly, BFT 3A-BFN EDMS-K s:lic/submit/operator/ris 2007-17.doc
ENCLOSURE Enclosure Operator Licensing Examination Data (Data as defined on NRC Form 536)
FACILITY BROWNS FERRY NUCLEAR PLANT NRC REGION II A. PROPOSED EXAMINATION PREPARATION SCHEDULE PROPOSED NUMBER CY-2008 CY-2009 CY-2010 CY-2011 ESTIMATED NUMBER OF 1 1 2 1 LICENSEE PREPARED EXAMINATIONS ESTIMATED NUMBER OF 0 0 0 0 NRC PREPARED EXAMINATIONS B. INITIAL OPERATOR LICENSE EXAMINATIONS PROPOSED NUMBER CY-2008 CY-2009 CY-2010 CY-2011 NUMBER OF REACTOR 12 6 6 - 6 6 OPERATORS NUMBER OF SENIOR REACTOR 2 5 3 - 3 3 OPERATORS - INSTANT NUMBER OF SENIOR REACTOR 2 1 3 - 3 3 OPERATORS - UPGRADE NUMBER OF SENIOR REACTOR 0 0 0 0 OPERATORS - LIMITED PROPOSED DATES PRIMARY DATE 10/20/2008 4/20/2009 4/19/2010 - 10/25/2010 10/24/2011 ALTERNATE DATE 11/03/2008 05/04/2009 05/3/2010 - 11/8/2010 11/7/2011 C. PROPOSED GENERIC FUNDAMENTALS EXAMINATION (GFE) SCHEDULE CY-2008 CY-2009 PROPOSED NUMBER MARCH JUNE SEPTEMBER DECEMBER MARCH JUNE SEPTEMBER DECEMBER ESTIMATED 11 0 0 0 9 0 9 0 NUMBER OF CANDIDATES