Text

ECCS Instrumentation 3.3.5.1 ACTIONS (continued)

CONDITION REQUIRED ACTION COMPLETION TIME B. As required by Required Action A.1 and referenced in B.1 ------- NOTES------

1. Only applicable in MODES 1, 2, I

Table 3,3.5.1-1. and 3.

2. Only applicable for Functions 1.a, 1.b, 2.a and 2.b.

Declare supported 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from feature(s) inoperable discovery of when its redundant loss of feature ECCS initiation initiation capability capability for is inoperable. feature(s) in both divisions AND I B.2 ------- NOTES------

1. Only applicable in MODES 1. 2.

and 3.

2. Only applicable for Functions 3.a and 3.b.

Declare High Pressure 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from Core Spray (HPCS) discovery of System inoperable. loss of HPCS initiation capability AND B.3 Place channel in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> trip.

(continued)

PERRY - UNIT I 3.3-33 Amendment No.147

ECCS Instrumentation 3.3.5.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME C. As required by C.1 -------- NOTES------

Required Action A.1 1. Only applicable and referenced in in MODES 1, 2, Table 3.3.5.1-1. and 3.

2. Only applicable for Functions 1.c, 1.d, i.e.

2.c, and 2.d.

Declare supported 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from feature(s) inoperable discovery of when its redundant loss of feature ECCS initiation initiation capability capability for is inoperable, feature(s) in both divisions AND C.2 Restore channel to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> OPERABLE status.

(continued)

PERRY - UNIT 1 3.3-34 Amendment No. 147 I

ECCS Instrumentation 3.3.5.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME D. As required by D.1 -------- NOTE-------

Required Action A.1 Only applicable if and referenced in HPCS pump suction is Table 3.3.5.1-1. not aligned to the suppression pool.

Declare HPCS System I hour from inoperable, discovery of loss of HPCS initiation capability AND D.2.1 Place channel in 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> trip.

OR D.2.2 Align the HPCS pump 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> suction to the suppression pool.

(continued)

PERRY - UNIT 1 3.3-35 Amendment No.147