July 24, 2007 Mr. Michael Kansler President Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601-1839
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE VERMONT YANKEE NUCLEAR POWER STATION, LICENSE RENEWAL APPLICATION
Dear Mr. Kansler:
By letter dated January 25, 2006, Entergy Nuclear Operations, Inc., submitted an application pursuant to 10 CFR Part 54, to renew the operating license for Vermont Yankee Nuclear Power Station, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.
These requests for additional information were discussed with Michael Hamer, and a mutually agreeable date for the response is within 15 days from the date of this letter. If you have any questions, please contact me at 301-415-4053 or e-mail JGR@nrc.gov.
Sincerely,
/RA/
Jonathan G. Rowley, Project Manager License Renewal Branch B Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-271
Enclosure:
Requests for Additional Information cc w/encl: See next page
ML072000256 OFFICE LA:DLR PM:RLRB:DLR BC:RLRB:DLR NAME SFigueroa JRowley RAuluck (SHoffman for)
DATE 7/24/07 7/24/07 7/24/07
Letter to M. Kansler from J. Rowley Dated July 24, 2007 DISTRIBUTION:
SUBJECT:
REQUESTS FOR ADDITIONAL INFORMATION FOR THE REVIEW OF THE VERMONT YANKEE NUCLEAR POWER STATION, LICENSE RENEWAL APPLICATION HARD COPY DLR RF E-MAIL:
PUBLIC SSmith (srs3)
SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb RidsNrrDci RidsNrrDra RidsNrrDe RidsNrrDeEemb RidsNrrDeEeeb RidsNrrDss RidsOgcMailCenter RidsNrrAdes JRowley RLaufer JShea CAnderson, RI RPowell, RI DScrenci, RI MModes, RI DPelton, SRI MYoung RidsOpaMail
Vermont Yankee Nuclear Power Station cc:
Regional Administrator, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415 Mr. David R. Lewis Pillsbury Winthrop Shaw Pittman, LLP 2300 N Street, N.W.
Washington, DC 20037-1128 Mr. David OBrien, Commissioner Vermont Department of Public Service 112 State Street Montpelier, VT 05620-2601 Mr. James Volz, Chairman Public Service Board State of Vermont 112 State Street Montpelier, VT 05620-2701 Chairman, Board of Selectmen Town of Vernon P.O. Box 116 Vernon, VT 05354-0116 Operating Experience Coordinator Vermont Yankee Nuclear Power Station 320 Governor Hunt Road Vernon, VT 05354 G. Dana Bisbee, Esq.
Deputy Attorney General 33 Capitol Street Concord, NH 03301-6937 Chief, Safety Unit Office of the Attorney General One Ashburton Place, 19th Floor Boston, MA 02108 Ms. Carla A. White, RRPT, CHP Radiological Health Vermont Department of Health P.O. Box 70, Drawer #43 108 Cherry Street Burlington, VT 05402-0070 Mr. David Mannai Manager, Licensing Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Resident Inspector Vermont Yankee Nuclear Power Station U. S. Nuclear Regulatory Commission P.O. Box 176 Vernon, VT 05354 Director, Massachusetts Emergency Management Agency ATTN: James Muckerheide 400 Worcester Rd.
Framingham, MA 01702-5399 Jonathan M. Block, Esq.
Main Street P.O. Box 566 Putney, VT 05346-0566 Mr. John F. McCann Director, Licensing Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Gary J. Taylor Chief Executive Officer Entergy Operations 1340 Echelon Parkway Jackson, MS 39213 Mr. John T. Herron Sr. VP and Chief Operating Officer Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Oscar Limpias Vice President, Engineering Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601
Vermont Yankee Nuclear Power Station cc: Mr. Christopher Schwartz Vice President, Operations Support Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Michael J. Colomb Director of Oversight Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Travis C. McCullough Assistant General Counsel Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Theodore Sullivan Site Vice President Entergy Nuclear Operations, Inc.
Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Mr. James H. Sniezek 5486 Nithsdale Drive Salisbury, MD 21801 Mr. Garrett D. Edwards 814 Waverly Road Kennett Square, PA 19348 Ms. Stacey M. Lousteau Treasury Department Entergy Services, Inc.
639 Loyola Avenue New Orleans, LA 70113 Mr. Norman L. Rademacher Director, NSA Vermont Yankee Nuclear Power Station P.O. Box 0500 185 Old Ferry Road Brattleboro, VT 05302-0500 Mr. Raymond Shadis New England Coalition Post Office Box 98 Edgecomb, ME 04556 Mr. James P. Matteau Executive Director Windham Regional Commission 139 Main Street, Suite 505 Brattleboro, VT 05301 Mr. William K. Sherman Vermont Department of Public Service 112 State Street Drawer 20 Montpelier, VT 05620-2601 Mr. Michael D. Lyster 5931 Barclay Lane Naples, FL 34110-7306 Ms. Charlene D. Faison Manager, Licensing 440 Hamilton Avenue White Plains, NY 10601 Ms. Julie Keys Nuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708 Diane Curran, Esq.
Harmon, Curran, Spielberg &
Eisenberg, L.L.P 1726 M Street, NW, Suite 600 Washington, DC 20036 Ronald A. Shems, Esq.
Shems, Dunkiel, Kassel & Saunders, PLLC 91 College Street Burlington, VT 05401 Karen Tyler, Esq.
Shems, Dunkiel, Kassel & Saunders, PLLC 91 College Street Burlington, VT 05401
Vermont Yankee Nuclear Power Station cc: Sarah Hofmann, Esq.
Director of Public Advocacy Department of Public Service 112 State Street - Drawer 20 Montpelier, VT 05620-2601 Jennifer J. Patterson, Esq.
Office of the New Hampshire Attorney General 33 Capitol Street Concord, NH 03301 Matias F. Travieso-Diaz, Esq.
Pillsbury Winthrop Shaw Pittman LLP 2300 N Street, NW Washington, DC 20037-1128 Matthew Brock, Esq.
Assistant Attorney General Office of the Massachusetts Attorney General Environmental Protection Division One Ashburton Place, Room 1813 Boston, MA 02108-1598 Anthony Z. Roisman, Esq.
National Legal Scholars Law Firm 84 East Thetford Rd.
Lyme, NH 03768
Enclosure VERMONT YANKEE NUCLEAR POWER STATION LICENSE RENEWAL APPLICATION REQUESTS FOR ADDITIONAL INFORMATION (RAI)
RAI 4.3.3-1:
The license renewal application (LRA) for the Vermont Yankee Nuclear Power Station listed several reactor coolant pressure boundary components that did not receive a plant-specific metal fatigue analysis and cumulative usage factor (CUF). The applicant generated LRA Commitment No. 27 to address this issue. In the commitment, the applicant committed to take one of the following options or a combination of options to ensure that the time-limited aging analysis (TLAA) on environmentally-assisted fatigue (EAF) of these components, and any other Class 1 components requiring reanalysis for EAF, will be acceptable under 10 CFR 54.21(c)(1) for the period of extended operation:
Option (1): either refine the existing fatigue analyses or perform new fatigue analyses using at least one of four suboptions under this option.
Option (2): manage aging by an aging management program for the period of extended operation.
Option (3): repair or replace the impacted component prior to exceeding a CUF of 1.0.
In order to make a determination on the acceptability of the applicants TLAA on EAF under the requirements of 10 CFR 54.21(c)(1), the staff requests that the applicant provide additional information on the option(s) that will be used for LRA Commitment No. 27. The applicant is requested to describe the methodology that will be used for the chosen option(s) in sufficient detail for staff review. Specifically, the staff requests that:
A.
If Option (1) is chosen, describe the methodology and the process that will be used to ensure that assumptions, transients, cycles, external loadings, Fen values, and analysis methods are valid for the refined or new fatigue analyses.
In the event the refined analyses performed under Option (1) result in CUFs greater than 1.0, describe the option(s) that may be used in addition to Option (1).
B.
If Option (2) is chosen, describe the AMP in sufficient detail with regard to inspection scope, inspection methods, inspection frequency, and inspection qualification techniques.
C.
If Option (3) is chosen, describe how the repair or replacement activity will be implemented in accordance with applicable repair or replacement requirements of the ASME Code Section XI.