Category:Letter
MONTHYEARIR 07200051/20244022024-11-20020 November 2024 NRC Independent Spent Fuel Storage Security Inspection Report No. 07200051/2024402 (Public) ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status IR 05000003/20240022024-08-0606 August 2024 NRC Inspection Report 05000003/2024002, 05000247/2024002, 05000286/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 ML24171A0122024-06-18018 June 2024 Reply to a Notice of Violation EA-24-037 ML24156A1162024-06-0404 June 2024 Correction - Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000003/20240052024-05-21021 May 2024 And 3 - NRC Inspection Report Nos. 05000003/2024005, 05000247/2024005, 05000286/2024005, 07200051/2024001, and Notice of Violation ML24128A0632024-05-0707 May 2024 Submittal of 2023 Annual Radiological Environmental Operating Report L-24-009, HDI Annual Occupational Radiation Exposure Data Reports - 20232024-04-29029 April 2024 HDI Annual Occupational Radiation Exposure Data Reports - 2023 ML24116A2412024-04-25025 April 2024 Annual Environmental Protection Plan Report ML24114A2282024-04-23023 April 2024 Annual Radioactive Effluent Release Report L-24-007, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI)2024-03-29029 March 2024 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations – Holtec Decommissioning International, LLC (HDI) IR 05000003/20240012024-03-20020 March 2024 NRC Inspection Report Nos. 05000003/2024001, 05000247/2024001, and 05000286/2024001 (Cover Letter Only) ML24080A1722024-03-20020 March 2024 Reply to a Notice of Violation EA-2024-010 ML24045A0882024-02-22022 February 2024 Correction to the Technical Specifications to Reflect Appropriate Pages Removed and Retained by Previous License Amendments ML24053A0642024-02-22022 February 2024 2023 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report IR 05000003/20230042024-02-22022 February 2024 NRC Inspection Report Nos. 05000003/2023004, 05000247/2023004, 05000286/2023004, and 07200051/2023004 and Notice of Violation ML24011A1982024-01-12012 January 2024 ISFSI, Notice of Organization Change for Site Vice President ML23342A1082024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23353A1742023-12-19019 December 2023 ISFSI, Emergency Plan, Revision 23-04 L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 ML23326A1322023-12-0505 December 2023 Issuance of Amendment No. 67, 300 & 276 to Implement the Independent Spent Fuel Storage Installation Only Emergency Plan ML23339A0442023-12-0505 December 2023 Issuance of Amendment No. 68, 301 and 277 Regarding Changes to Implement the Independent Spent Fuel Storage Installation Physical Security Plan ML23338A2262023-12-0404 December 2023 Signed Amendment No. 27 to Indemnity Agreement No. B-19 ML23356A0212023-12-0101 December 2023 American Nuclear Insurers, Secondary Financial Protection (SFP) Program ML23242A2772023-11-30030 November 2023 NRC Letter Issuance - IP LAR for Units 2 and 3 Renewed Facility Licenses and PDTS to Reflect Permanent Removal of Spent Fuel from SFPs ML23338A0482023-11-30030 November 2023 ISFSI, Report of Changes to Physical Security, Training and Qualification, Safeguards Contingency Plan, and ISFSI Security Program, Revision 28 ML22339A1572023-11-27027 November 2023 Letter - Indian Point - Ea/Fonsi Request for Exemptions from Certain Emergency Planning Requirements for 10 CFR 50.47 and 10 CFR Part 50, Appendix E IR 05000003/20230032023-11-21021 November 2023 NRC Inspection Report Nos. 05000003/2023003, 05000247/2023003, 05000286/2023003, and 07200051/2023003 ML23100A1252023-11-17017 November 2023 Letter and Enclosure 1 - Issuance Indian Point Energy Center Units 1, 2, and 3 Exemption for Offsite Primary and Secondary Liability Insurance Indemnity Agreement ML23050A0032023-11-17017 November 2023 Letter - Issuance Indian Point Unit 2 License Amendment Request to Modify Tech Specs for Staffing Requirements Following Spent Fuel Transfer to Dry Storage ML23100A1172023-11-17017 November 2023 NRC Response - Indian Point Energy Center Generating Units 1, 2, and 3 Letter with Enclosures Regarding Changes to Remove the Cyber Security Plan License Condition ML23100A1432023-11-16016 November 2023 Letter - Issuance Indian Point Energy Center Generating Units 1, 2, and 3 Exemption Concerning Onsite Property Damage Insurance (Docket Nos. 50-003, 50-247, 50-286) L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23064A0002023-11-13013 November 2023 NRC Issuance for Approval-Indian Point EC Units 1, 2 and 3 Emergency Plan and Emergency Action Level Scheme Amendments ML23306A0992023-11-0202 November 2023 And Indian Point Energy Center, Notification of Changes in Schedule in Accordance with 10 CFR 50.82(a)(7) ML23063A1432023-11-0101 November 2023 Letter - Issuance Holtec Request for Indian Point Energy Center Generating Units 1, 2, and 3 Exemptions from Certain Emergency Planning Requirements of 10 CFR 50.47 and Part 50 ML23292A0262023-10-19019 October 2023 LTR-23-0211-RI Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report-RI ML23289A1582023-10-16016 October 2023 Decommissioning International - Registration of Spent Fuel Casks and Notification of Permanent Removal of All Indian Point Unit 3 Spent Fuel Assemblies from the Spent Fuel Pit ML23270A0082023-09-27027 September 2023 Registration of Spent Fuel Casks ML23237A5712023-09-22022 September 2023 09-22-2023 Letter to Dwaine Perry, Chief, Ramapo Munsee Nation, from Chair Hanson, Responds to Letter Regarding Opposition of the Release and Dumping of Radioactive Waste from Indian Point Nuclear Power Plant Into the Hudson River ML23242A2182023-09-12012 September 2023 IPEC – NRC Response to the Town of New Windsor, Ny Board Certified Motion Letter Regarding Treated Water Release from IP Site (Dockets 50-003, 50-247, 50-286) ML23250A0812023-09-0707 September 2023 Registration of Spent Fuel Casks ML23255A0142023-08-31031 August 2023 LTR-23-0211 Thomas Congdon, Executive Deputy, Department of Public Service, Chair, Indian Point Decommissioning Oversight Board, Letter Independent Spent Fuel Storage Installation Inspection and Office of the Inspector General Report IR 05000003/20230022023-08-22022 August 2023 NRC Inspection Report 05000003/2023002, 05000247/2023002, 05000286/2023002, and 07200051/2023002 ML23227A1852023-08-15015 August 2023 Request for a Revised Approval Date Regarding the Indian Point Energy Center Permanently Defueled Emergency Plan and Emergency Action Level Scheme ML23222A1442023-08-10010 August 2023 Registration of Spent Fuel Casks ML23208A1642023-07-26026 July 2023 Village of Croton-on-Hudson New York Letter Dated 7-26-23 Re Holtec Wastewater ML23200A0422023-07-19019 July 2023 Registration of Spent Fuel Casks 2024-09-18
[Table view] |
Text
OFFICE OF THE SECRETARY CORRESPONDENCE CONTROL TICKET Date Printed: Jul 10, 2007 16:11 PAPER NUMBER: ACTION OFFICE: AUTHOR: AFFILIATION:
ADDRESSEE:
SUBJECT:
LTR-07-0461 LOGGING DATE: 07/09/2007 EDO Q E-DEDO DEDMRS Susan Shapiro " DEDIA NY AO Dale Klein Q Request additional 60 days for filing of petitions to intervene when the appl for Indian Poin license renewal is docketed and a notice of receipt is issued ACTION: DISTRIBUTION:
LETTER DATE: ACKNOWLEDGED SPECIAL HANDLING: Appropriate Chairman, Comrs 06/22/2007 No Made publicly available in ADAMS via EDO/DPC NOTES: FILE LOCATION: ADAMS DATE DUE: DATE SIGNED:
FUSE (FRIENDS UNITED FOR SUSTAINABLE ENERGY)21 PERLMAN DRIVE SPRING VALLEY, NY 10977 (845) 371-2100 TEL (845)371-3721 FAX 6/22/07 Dr. Pao-Tsin Kuo, PE Director, Division of License Renewal Mail Stop Q-11F1 Washington, DC 20555 Richard Barkley Nuclear Regulatory Commission
("NRC")475 Allendale Road King of Prussia, PA 19406 Chairnan's Office Nuclear Regulatory Commission
("NRC")Washington, DC 20555-0001
Dear Dr. Pao-Tsin Kuo:
After many years of preparation, Entergy submitted its license renewal application for Indian Point 2 and 3 on or about April 30th, 2007. The timing of the application submission indicates a purposeful attempt by the applicant (Entergy) to reduce, abrogate and inequitably interfere with Stakeholders' ability to Intervene and participate in the relicensing process in a meaningful manner.If the NRC accepts the application on or about July 1, then Stakeholders only have 60 days to file Intervener petition.
Because that time falls squarely in the middle of the summer, many citizen Stakeholders, elected officials and government bodies are on summer vacation and/or short staffed because of vacation schedules.
In fact many courts, businesses, and attorneys throughout the country take time off in August.Therefore, we respectfully submit that the NRC exhibit evenhandedness, fairness and equitable impartiality, by either extending the period in which Interveners may submit petitions for an additional 60 days, or in the alternative the NRC can delay acceptance of the application for an additional 60 days.
A few more months of processing the license application will not harm the licensee in any meaningful way, as the process is expected to take between 2-3 years. Therefore we respectfully request that in the event the NRC accepts the licensee's application that the period for Intervener petition submission be 120 days, In addition, the Relicense Application incorporates by reference a variety of materials, including but not limited to, documents, studies, charts, maps, etc., which have not been made available to the Stakeholder communities.
Many of the reference materials need special computer programs to download from ADAMS, and therefore are inaccessible to community Stakeholders.
Therefore, until such time that ANY and ALL such materials that are incorporated by reference in the Relicense Application, including but not limited to, documents, studies, charts, maps, etc, are made available in a public place, such as a library, within the Stakeholder community, the NRC cannot start the Intervener petition clock. Therefore, we respectfully.
request all such reference materials be made available for inspection, immediately, and until such time ANY and ALL reference materials are made available the NRC cannot start the Intervener petition clock.Si ly ýSusan Shapiri;;-"-, FUSE 21 Perlman Drive Spring Valley, NY 10977 Paul Gunther Nuclear Information and Resource Service (NIRS)6930 Carroll Avenue, Suite 340, Takoma Park, MD 20912 Thomas J. Abinanti Westchester County Legislature 61 Kathwood Road White Plains, NY 10607 Susan Zimet Ulster County Legislature 100 BUtterville Road New Paltz, NY 12561 Hector Rodriques Ulster County Legislator 69 Main Street New Paltz, NY 12561 Andy Kossover Ushter County Public Defender P.O. Box 399 New Paltz, NY 12561 Manna Jo Greene, Environmental Director Hudson River Sloop Clearwater 112 Market St.Poughkeepsie, NY 12601 Jason K. Babbie Senior Environmental Policy Analyst NYPIRG -New York Public Interest Research Group 9 Murray Street, 3rd Floor New York, NY 10007 Alice Slater Nuclear Age Peace Foundation, New York 446 E. 86 St.New York, NY 10028 Deb Katz Citizen's Awareness Network PO Box 83 Shelburne Falls, MA 01370 Sherwood Martinelli Green Nuclear Butterfly 351 Dykman Street Peekskill, NY 10566 Judy Allen 24 Seifert Lane Putnam Valley, NY 10579 Gary Shaw 9 Van Cortlandt Place Croton on Hudson, NY 10520 Kenneth L. Okin 570 Scarborough Rd Briarcliff Manor, NY 10510 Mark Jacobs 46 Highland Drive Garrison, NY 10254 Allegra Dengler 60 Judson Avenue Dobbs Ferry, NY 10522 Maureen Ritter Rockland FUSE 46 Campbell Avenue Suffem, NY 10901 Nancy Burton 147 Cross Highway Redding Ridge CT 06876 Tel. 203-938-3952 Ed McCann 193 Tillson Lake road Wallkill, NY 12589 Richard Kollath 193 Tillson Lake Road Wallkill, NY 12589 Judith Hakam PO Box 53 Stone Ridge, NY 12484 Ken Wishnick 12 Hawk Hill Road New Paltz, NY 12561 Mildred Hable P.O. Box 601 New Paltz, NY 12561 Raymond T. Miller 45 Church Street New Paltz, NY 12561 Steven Lewis 28 CragswoodRoad New Paltz, NY 12561 Kristen Brown 10 Pughkeepsie Ave New Paltz, NY 12561 Donnie Kaye 15 Millard Road New Paltz, NY 12561 Laura Kaye 15 Millard Road New Paltz, NY 12561 Janet Hamilton 131-B Purtuese Lane New Paltz, NY 12561 Anne Ellman 136 N. Chestnut Street New Paltz, NY 12561 Louise Bendman 21 Holland Lane New Paltz, NY 12561 Josh Honing 80 Burkish Road New Paltz, NY 12561 Sandra Leorrian P.O. Box 254 New Paltz, NY 12561 Michel Lee 265 Madison Road Scarsdale, NY 10583