June 11, 2007 Mr. L. William Pearce Site Vice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P. O. Box 97, 10 Center Road, A290 Perry, OH 44081-0097
SUBJECT:
PERRY NUCLEAR POWER PLANT INITIAL OPERATOR LICENSE EXAMINATION RE-TAKE WRITTEN EXAMINATION
Dear Mr. Pearce:
In a telephone conversation on May 23, 2007, between Mr. D. Zielenski, License Training Instructor, and Mr. D. McNeil, Senior Operations Engineer, arrangements were made for the administration of a re-take examination at Perry Nuclear Power Plant during the week of August 6, 2007.
As agreed during the telephone conversation, your staff will prepare the re-take examination based on the guidelines in Revision 9 of NUREG-1021, Operator Licensing Examination Standards for Power Reactors. The NRCs regional office will discuss with your staff any changes that might be necessary before the examinations are administered. To meet the above schedule, it was necessary for your staff to furnish the examination outlines by June 4, 2007, which they have completed. The written re-take examination and supporting reference materials identified in Attachment 2 to ES-201 will be due by July 2, 2007. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations, an authorized representative of the facility licensee shall approve the outlines, examinations, and tests before they are submitted to the NRC for review and approval. All materials shall be complete and ready-to-use. We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked.
Any delay in receiving the required examination and reference materials, or the submission of inadequate or incomplete materials, may cause the examinations to be rescheduled.
Appendix E to NUREG-1021 contains a number of NRC policies and guidelines that will be in effect while the written examinations is being administered. To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator license applications (Office of Management and Budget (OMB) approval number 3150-0090),
medical certifications (OMB approval number 3150-0024), and waiver requests (OMB approval number 3150-0090) at least 30 days before the first examination date. If the applications are not received at least 30 days before the examination date, a postponement may be necessary.
Signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.
L. Pearce This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under approval number 3150-0018, which expires on June 30, 2009. The public reporting burden for this collection of information is estimated to average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, writing the examinations, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to BJS1@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number.
In accordance with Title 10, Section 2.390, of the Code of Federal Regulations, Rules of Practice, a copy of this letter and its enclosures will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the Electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. Mr. Zielinski has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRCs examination procedures and guidelines, please contact Mr. D. McNeil at (630) 829-9737 or me at (630) 839-9707.
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No. 50-440 License No. NPF-58 DISTRIBUTION See next page
L. Pearce This letter contains information collections that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by OMB, under approval number 3150-0018, which expires on June 30, 2009. The public reporting burden for this collection of information is estimated to average 500 hours0.00579 days <br />0.139 hours <br />8.267196e-4 weeks <br />1.9025e-4 months <br /> per response, including the time for reviewing instructions, gathering and maintaining the data needed, writing the examinations, and completing and reviewing the collection of information. Send comments on any aspect of this collection of information, including suggestions for reducing the burden, to the Information and Records Management Branch (T-6 F33), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet electronic mail to BJS1@nrc.gov; and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0018), Office of Management and Budget, Washington, DC 20503.
The NRC may neither conduct nor sponsor, and a person is not required to respond to, an information collection, unless it displays a currently valid OMB control number.
In accordance with Title 10, Section 2.390, of the Code of Federal Regulations, Rules of Practice, a copy of this letter and its enclosures will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the Electronic Reading Room page of the NRCs public Web site at http://www.nrc.gov/reading-rm/adams.html.
Thank you for your cooperation in this matter. Mr. Zielinski has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRCs examination procedures and guidelines, please contact Mr. D. McNeil at (630) 829-9737 or me at (630) 839-9707.
Sincerely,
/RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No. 50-440 License No. NPF-58 DISTRIBUTION See next page DOCUMENT NAME: C:\\FileNet\\ML071650281.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII:DRS RIII:DRS NAME DMcNeil:co HPeterson DATE 06/11/07 06/11/07 OFFICIAL RECORD COPY
Letter to L. William Pearce from Hironori Peterson dated June 11, 2007.
SUBJECT:
PERRY NUCLEAR POWER PLANT INITIAL OPERATOR LICENSE EXAMINATION RE-TAKE WRITTEN EXAMINATION cc:
J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations - FENOC D. Pace, Senior Vice President, Fleet Engineering - FENOC J. Rinckel, Vice President, Fleet Oversight R. Anderson, Vice President, Nuclear Support Director, Fleet Regulatory Affairs Manager, Fleet Licensing Manager, Site Regulatory Compliance D. Jenkins, Attorney, FirstEnergy Public Utilities Commission of Ohio Ohio State Liaison Officer R. Owen, Ohio Department of Health
Letter to L. William Pearce from Hironori Peterson dated June 11, 2007.
SUBJECT:
PERRY NUCLEAR POWER PLANT INITIAL OPERATOR LICENSE EXAMINATION RE-TAKE WRITTEN EXAMINATION cc:
J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations - FENOC D. Pace, Senior Vice President, Fleet Engineering - FENOC J. Rinckel, Vice President, Fleet Oversight R. Anderson, Vice President, Nuclear Support Director, Fleet Regulatory Affairs Manager, Fleet Licensing Manager, Site Regulatory Compliance D. Jenkins, Attorney, FirstEnergy Public Utilities Commission of Ohio Ohio State Liaison Officer R. Owen, Ohio Department of Health DISTRIBUTION:
RAG1 TEB TJW2 RidsNrrDirsIrib GEG KGO MEF1 CAA1 LSL (electronic IRs only)
C. Pederson, DRS (hard copy - IRs only)
DRPIII DRSIII PLB1 TXN NLS