ML071590365

From kanterella
Jump to navigation Jump to search
Response to Disputed Non-cited Violations Inspection Report 05000254/2006-002(DRS); 05000265/2006002(DRS)
ML071590365
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 06/05/2007
From: Grant G
Region 3 Administrator
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
EA-06-229, IR-06-002
Download: ML071590365 (9)


See also: IR 05000254/2006002

Text

June 5, 2007

EA-06-229

Mr. Christopher M. Crane

President and Chief Nuclear Officer

Exelon Nuclear

Exelon Generation Company, LLC

Quad Cities Nuclear Power Station

4300 Winfield Road

Warrenville, IL 60555

SUBJECT:

RESPONSE TO DISPUTED NON-CITED VIOLATIONS

QUAD CITIES NUCLEAR POWER STATION UNITS 1 AND 2

INSPECTION REPORT 05000254/2006002(DRS); 05000265/2006002(DRS)

Dear Mr. Crane:

Thank you for your response by letter dated August 31, 2006, to our inspection report issued on

July 31, 2006, concerning activities conducted at your facility. In your response, you denied two

of the Non-Cited Violations (NCVs) contained in the inspection report: NCV 05000254(265)/

2006002-01, associated with the safe shutdown makeup pump; and NCV 05000254(265)/

2006002-02, associated with residual heat removal service water cross-tie. You also denied

the existence of a cross-cutting aspect to NCV 05000254(265)/2006002-04, associated with

your stations fire pre-plans. By letter dated September 27, 2006, we informed you that we

were evaluating your reply and would inform you of the results of our evaluations. We have

completed our review of your response.

The NRC conducted a detailed review of your response and the applicable licensing and

regulatory documents. The review was conducted by NRC staff that were independent of the

initial inspection effort, including the Office of Nuclear Reactor Regulation, and the results were

reviewed by the NRC Office of Enforcement. After careful consideration of the bases for your

denial of the NCV, we have concluded that the violations occurred as stated in the inspection

report. We have provided a summary of our evaluation and conclusions as an enclosure to this

letter. The enclosure also discusses an evaluation of your denial of an existing cross-cutting

aspect for an inspection finding.

C. Crane

-2-

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter, its

enclosure and your August 31, 2006, response will be available electronically for public

inspection in the NRC Public Document Room or from the NRC's document system (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely,

/RA/

Geoffrey E. Grant

Deputy Regional Administrator

Docket Nos. 50-254; 50-265

License Nos. DPR-29; DPR-30

Enclosure:

(EA-06-229) Evaluation of Basis for Disputed Non-Cited

Violations and Conclusions

cc w/encl:

Site Vice President - Quad Cities Nuclear Power Station

Plant Manager - Quad Cities Nuclear Power Station

Regulatory Assurance Manager - Quad Cities Nuclear Power Station

Chief Operating Officer

Senior Vice President - Nuclear Services

Senior Vice President - Mid-West Regional

Operating Group

Vice President - Mid-West Operations Support

Vice President - Licensing and Regulatory Affairs

Director Licensing - Mid-West Regional

Operating Group

Manager Licensing - Dresden and Quad Cities

Senior Counsel, Nuclear, Mid-West Regional

Operating Group

Document Control Desk - Licensing

Vice President - Law and Regulatory Affairs

Mid American Energy Company

Assistant Attorney General

Illinois Emergency Management Agency

State Liaison Officer, State of Illinois

State Liaison Officer, State of Iowa

Chairman, Illinois Commerce Commission

Chief Radiological Emergency Preparedness Section,

Dept. Of Homeland Security

D. Tubbs, Manager of Nuclear

MidAmerican Energy Company

Crane

-2-

In accordance with 10 CFR 2.390 of the NRC's Rules of Practice, a copy of this letter, its enclosure and your

August 31, 2006, response will be available electronically for public inspection in the NRC Public Document Room or

from the NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html.

Sincerely,

/RA/

Geoffrey E. Grant

Deputy Regional Administrator

Docket Nos. 50-254; 50-265

License Nos. DPR-29; DPR-30

Enclosure:

(EA-06-229) Evaluation of Basis for Disputed Non-Cited

Violations and Conclusions

cc w/encl:

Site Vice President - Quad Cities Nuclear Power Station

Plant Manager - Quad Cities Nuclear Power Station

Regulatory Assurance Manager - Quad Cities Nuclear Power Station

Chief Operating Officer

Senior Vice President - Nuclear Services

Senior Vice President - Mid-West Regional

Operating Group

Vice President - Mid-West Operations Support

Vice President - Licensing and Regulatory Affairs

Director Licensing - Mid-West Regional

Operating Group

Manager Licensing - Dresden and Quad Cities

Senior Counsel, Nuclear, Mid-West Regional

Operating Group

Document Control Desk - Licensing

Vice President - Law and Regulatory Affairs

Mid American Energy Company

Assistant Attorney General

Illinois Emergency Management Agency

State Liaison Officer, State of Illinois

State Liaison Officer, State of Iowa

Chairman, Illinois Commerce Commission

Chief Radiological Emergency Preparedness Section,

Dept. Of Homeland Security

D. Tubbs, Manager of Nuclear

MidAmerican Energy Company

See Previous Concurrence

Distribution:

See Next Page

DOCUMENT NAME: C:\\FileNet\\ML071590365.wpd

G Publicly Available

G Non-Publicly Available

G Sensitive

G Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII

OE

RIII

NAME

Jlara: jb

  • CCarpenter

CPederson

DATE

05/25/07

05/24/07

05/28/07

OFFICE RIII

RIII

RIII

RIII

NAME

MRing

KOBrien

GGrant

DATE

05/29/07

05/24/07

06/05/07

OFFICIAL RECORD COPY

  • OE concurrence provided by Cheryl Montgomery in email from D. Starkey to K. OBrien

C. Crane

-3-

Letter to Mr. Christopher M. Crane from Mr. Geoffrey E. Grant dated June 5, 2007.

SUBJECT:

RESPONSE TO DISPUTED NON-CITED VIOLATIONS

QUAD CITIES NUCLEAR POWER STATION UNITS 1 AND 2

INSPECTION REPORT 05000254(265)/2006002

DISTRIBUTION:

MXM2

JFW1

KKB

ADAMS (PARS)

SECY

OCA

W. Kane, DEDR

C. Carpenter, OE

D. Solorio, OE

D. Starkey, OE

J. Caldwell, RIII

G. Grant, RIII

L. Chandler, OGC

B. Jones, OGC

J. Dyer, NRR

S. Richards, Chief, IIPB, NRR

M. Tschiltz, Chief, SPSB, NRR

D. Merzke, NRR

J. Stang, NRR

D. Holody, Enforcement Officer, RI

C. Evans, Enforcement Officer, RII

K. OBrien, Enforcement Officer, RIII

K. Fuller, Enforcement Officer, RIV

R. Pascarelli, Enforcement Coordinator, NRR

K. Stoedter, Seniro Resident Inspector

E. Brenner, OPA

H. Bell, OIG

G. Caputo, OI

P. Pelke, RIII:EICS

V. Mitlyng, RIII:PA

R. Lickus, RIII

J. Lynch, RIII

OEWEB

OEMAIL

TEB

RidsNrrDirsIrib

MPP

SXB3

CAA1

DRPIII

DRSIII

PLB1/TXN

ROPreports@nrc.gov

Enclosure

1

QUAD CITIES NUCLEAR POWER STATION (QCNPS) UNITS 1 AND 2; INSPECTION REPORT

05000254(265)/2006002

(EA-06-229) EVALUATION OF BASIS FOR DISPUTED NON-CITED VIOLATIONS AND CONCLUSIONS

NRCs Evaluation of Licensees Response:

Region III conducted an independent review of the technical and enforcement issues associated with the

two Non-Cited Violations (NCVs) referenced in Inspection Report

No. 05000254(265)/2006002. As part of this review process, the Region III staff reviewed QCNPS

August 31, 2006 response, requested additional information and conducted a teleconference with licensee

staff to ensure a clear understanding of QCNPS position. Furthermore, the Region III staff received

technical assistance from the Office of Nuclear Reactor Regulation (NRR) staff responsible for fire

protection issues. The technical assistance was provided via a Task Interface Agreement (TIA) (2006-

005, dated September 28, 2006; ADAMS Accession Number ML062710539), and the associated

response dated

March 27, 2007; (ADAMS Accession Number ML070640415). In accordance with 10 CFR 2.390 of the

NRC's Rules of Practice, a copy of this letter, its enclosure and your

August 31, 2006, response will be available electronically for public inspection in the NRC Public

Document Room or from the NRC's document system (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html.

The NRC staff recognizes that fire protection program changes made following the 1998 Confirmatory

Action Letter resulted in a decrease in the number and the complexity of operator actions required to meet

Appendix R,Section III.G.3 requirements. Nonetheless, the program changes must continue to meet

existing regulations consistent with established regulatory guidance.

In summary, the NRC staff concluded that QCNPS made changes to the plants fire protection program

which were not consistent with 10 CFR 50 Appendix R requirements, as stated in the NCVs. Therefore,

the NRC staff reaffirmed the original NCVs. The reasons are discussed below.

The Region III staff also reviewed the additional information provided by QCNPS with regard to the cross-

cutting aspect of NCV 05000254(265)/2006002-04. The results of this review are also documented below.

1.

Non-Cited Violation 05000254(265)/2006002-01

Restatement of Violation:

Title 10 CFR Part 50.48, Fire Protection, and 10 CFR Part 50, Appendix R, Fire Protection Program for

Nuclear Power Facilities Operating Prior to January 1, 1979, establishes specific fire protection features

required to satisfy 10 CFR Part 50, Appendix A, General Design Criterion 3, Fire Protection. Appendix R

applies to licensed nuclear power electric generating stations that were operating prior to January 1, 1979,

which included QCNPS. Section III.G.2 of Appendix R to 10 CFR Part 50 requires, in part, that, where

cables or the equipment of a redundant train of systems necessary to achieve and maintain hot shutdown

conditions are located within the same fire area outside of primary containment, one of a specified means

of ensuring that one of the redundant trains is free of fire damage shall be provided.

Section III.G.3 of Appendix R to 10 CFR Part 50 requires, in part, that, alternative or dedicated shutdown

capability should be provided where the protection of systems whose function is required for hot shutdown

does not satisfy the requirement of Paragraph III.G.2. Subsection 3 of Section III.L., Alternative and

Dedicated Shutdown Capability, to 10 CFR Part 50,

Appendix R requires, in part, that the shutdown capability shall be independent of the specific fire area(s)

Enclosure

2

and shall accommodate postfire conditions where offsite power is available and where offsite power is not

available for 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />. Procedures shall be in effect to implement this capability.

Contrary to the above, in the event of a fire in any of these fire areas (TB-III, 13-1, or 24-1), QCNPS failed

to ensure that one of the redundant trains of reactor coolant inventory makeup water remained free of fire

damage. Instead, QCNPS credited the use of the dedicated safe shutdown makeup pump (SSMP) for

reactor coolant inventory makeup without having analyses and procedures that demonstrated their full

compliance with Sections III.G.3 and III.L, or requesting prior NRC approval. Once identified, QCNPS

entered the finding into their corrective action program as IR 00502702, NRC Inspection Finding

Concerning Appendix R Redundant Trains, dated June 22, 2006. Because this violation was of very low

safety significance and it was entered into QCNPS corrective action program, this violation is being

treated as a NCV, consistent with Section VI.A.1 of the NRC Enforcement Policy.

Summary of Licensees Response and NRC Evaluations

Licensee Response:

In summary, QCNPS maintained that the SSMP and reactor core isolation cooling (RCIC) systems meet

the NRC requirements to be considered redundant and therefore no violation of NRC requirements exists.

This is based on the SSMP and RCIC performing the same design functions. The QCNPS cited two

primary documents as a basis: Generic Letter (GL) 86-10, Implementation of Fire Protection

Requirements, [Question 3.8.3 Redundant Trains/Alternate Shutdown,] and Nuclear Energy Institute

(NEI) Guidance Document 00-01, Guidance for Post-Fire Safe Shutdown Circuit Analysis. The QCNPS

maintained that the basis for the NCV was inconsistent with NRC or industry guidance related to Appendix

R redundant versus alternate system classification.

NRC Evaluation:

The NRC staff performed a review of the regulatory guidance documents relating to Appendix R as part of

this review, including those referenced by QCNPS. While the NRC inspection report and licensee position

reference GL 86-10, Question 3.8.3, the NRC staff response to GL 86-10 Question 5.1.2, also provides

regulatory guidance with respect to what constitutes a preferred system. In that response, the staff stated,

in part, For the purposes of analysis to

Section III.G.2 criteria, the safe shutdown capability is defined as one of the two normal safe shutdown

trains. If the criteria of Section III.G.2 are not met, an alternative shutdown capability is required.

The QCNPS originally did not protect redundant safe shutdown trains in specific fire areas and did not

provide an alternate shutdown capability using existing sytems. Therefore, the SSMP was installed as a

new system to provide dedicated shutdown system capability to comply with 10 CFR Part 50, Appendix R,

Section III.G.3. This new system installation approach was consistent with the response to Question 3.8.3

and Footnote 1 in Appendix R, ...dedicated shutdown capability is provided by installing new structures

and systems for the function of post-fire shutdown.

With respect to QCNPS position that classification of the SSMP as redundant is supported by the

guidance in NEI 00-01, the NRC staff notes that this guidance document was developed, and endorsed by

NRC, for resolving circuit failure issues; which is not pertinent to this NCV. Nonetheless, the guidance

contained therein (i.e., 3.1.1 Criteria Assumptions) with respect to identifying systems required for safe

shutdown functions is consistent with the NCV basis and the associated TIA response.

Licensees can perform a 10 CFR 50.59 evaluation (or other equivalent adverse effects evaluation) for fire

protection program changes to change compliance strategies

(i.e., Sections III.G.2 to III.G.3, and vice versa). However, licensees must evaluate the adverse effects on

Enclosure

3

safe shutdown and remain in compliance with the provisions of the specified requirements in 10 CFR Part 50, Appendix R. In this particular case, QCNPS reclassified the SSMP from a dedicated shutdown system

to a redundant system, and asserted that the SSMP met the Appendix R,Section III.G.2 requirements.

However, since the function of the SSMP system (a dedicated system) is for Appendix R safe shutdown,

the SSMP did not perform the same design function as the RCIC system. Additionally, since the SSMP

was also not one of the two normal safe shutdown trains, it was therefore an alternative (dedicated)

shutdown capability. Furthermore, in accordance with Section III.L.3, dedicated systems must

demonstrate shutdown capability when offsite power is and is not available.

Accordingly, the SSMP system is not redundant and the design function of the SSMP system should

remain characterized as a Dedicated Shutdown system. The QCNPS has not demonstrated that the

SSMP design function is the same as the RCIC system design function (i.e., a redundant system). As

stated in the referenced TIA documents, the acceptability of reliance on a system, other than the normal

shutdown trains for the purpose of establishing compliance with 10 CFR Part 50, Appendix R, Section

III.G.2, necessitates significant safety analysis and regulatory reviews.

For the above reasons, the staff concludes that the violation occurred as stated.

Enclosure

4

2.

Non-Cited Violation 05000254(265)/2006002-02

Restatement of Violation:

Title 10 CFR Part 50.48, Fire Protection, and 10 CFR Part 50, Appendix R, Fire Protection Program for

Nuclear Power Facilities Operating Prior to January 1, 1979, establishes specific Fire Protection features

required to satisfy 10 CFR Part 50, Appendix A, General Design Criterion 3, Fire Protection. Appendix R

applies to licensed nuclear power electric generating stations that were operating prior to January 1, 1979,

which includes QCNPS. Section III.G.2 of Appendix R to 10 CFR Part 50 required, in part, that, where

cables or equipment of redundant trains of systems necessary to achieve and maintain hot shutdown

conditions are located within the same fire area outside of primary containment, one of a specified means

of ensuring that one of the redundant trains is free of fire damage be provided.

Contrary to the above, in the event of a fire in Fire Areas TB-III, 13-1, or 24-1 (i.e., a III.G.2 area), QCNPS

failed to meet the requirement of Section III.G.2 of 10 CFR Part 50, Appendix R. Specifically, in the event of

a fire in any of these areas, QCNPS credited the opposite Unit RHRSW system instead of ensuring one of

the redundant trains of RHRSW from the respective unit with fire was available. Once identified, QCNPS

entered the finding into their corrective action program as IR 00502702, NRC Inspection Finding

Concerning Appendix R Redundant Trains, dated June 22, 2006. Because this violation was of very low

safety significance and it was entered into QCNPS corrective action program, this violation is being treated

as a NCV, consistent with Section VI.A.1 of the NRC Enforcement Policy.

Summary of Licensees Response and NRC Evaluations

Licensee Response:

In summary, QCNPS maintained that for multiple unit plants, the systems shared between units may be

credited as redundant for each unit, provided the system performs its design function within the design

basis of the plant. The residual heat removal (RHR) service water (RHRSW) system design function was

to provide cooling water to the RHR system heat exchangers, and was required for containment cooling

and safe reactor shutdown during abnormal operating events. The plant design basis fully acknowledged

the RHRSW system and inter-unit capabilities. Utilization of the crosstie was fully integrated into station

operating procedures, including certain procedures used for post-fire safe shutdown.

Furthermore, QCNPS maintained that the NRC acknowledged the industrys use of shared inter-unit

systems for redundant safe shutdown in Technical Report R7017/U7010-3/95.

NRC Evaluation:

The NRC staff performed a review of the regulatory guidance documents relating to Appendix R as part of

this review, including those referenced by QCNPS. The NRC staff concludes that QCNPS cannot rely

upon on a multi-unit cross-tie capability for the purpose of meeting 10 CFR Part 50, Appendix R, Section

III.G.2., unless an exemption request has been granted.

Enclosure

5

Title 10 CFR 50.48 states that, Each operating nuclear power plant must have a fire protection plan that

satisfies Criterion 3 of Appendix A of this part. Therefore, each of the QCNPS units must individually

comply with this regulation. With respect to compliance with 10 CFR Part 50, Appendix R, since the

redundant trains of the RHRSW system in one unit could be affected by a single fire, QCNPS seeks to

credit the non-fire affected units RHRSW system as being redundant to the fire affected units RHRSW

system and vice versa. Without an exemption, this approach does not satisfy the requirements of III.G.2

for a plant licensed to operate before January 1, 1979, because the redundant RHRSW system trains in

the same unit are not free of fire damage.

The QCNPS approach could be acceptable as an alternative shutdown method provided that the

requirements of 10 CFR Part 50, Appendix R, Section III.G.3 and Section III.L were met. This approach

would necessitate assurance that during all modes and alignments on one unit, the RHRSW system is

available to support fire safe shutdown of the opposite unit.

With respect to the referenced technical report and its examples of cross-tied equipment between units, the

report was intended as a general guidance document for international audiences and has no regulatory

basis for establishing compliance with NRC regulations.

For the above reasons, the staff concludes that the violation occurred as stated.

3.

Cross-Cutting Aspect of Non-Cited Violation 05000254(265)/2006002-04

The QCNPS provided additional information for consideration regarding this NCV. Specifically, while

QCNPS did not contest the NCV, QCNPS did not believe that there was a cross-cutting aspect to this NCV

because Problem identification and Resolution (PI&R) was not the underlying cause of the performance

deficiency.

The staff concludes that this issue did affect the cross-cutting area of PI&R because the previous

corrective actions developed were narrowly focused. The NRC PI&R cross-cutting area contains an area

component of Corrective Action Program. This area component is further defined by licencee actions

which ensure that issues potentially impacting nuclear safety are promptly identified and fully evaluated.

Actions are also taken to address the issues in a timely manner. The QCNPS corrective actions were

narrowly focused on individual specific deficiencies rather than the broader issue of inaccurate fire plans.

The staff recognizes that this finding had very low safety significance.