May 23, 2007 Mr. Michael R. Kansler President Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601
SUBJECT:
INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 AND 3 - RESPONSE TO GENERIC LETTER 2006-02 "GRID RELIABILITY AND THE IMPACT ON PLANT RISK AND THE OPERABILITY OF OFFSITE POWER" (TAC NOS.
MD0990 AND MD0991)
Dear Mr. Kansler:
On February 1, 2006, the U.S. Nuclear Regulatory Commission (NRC) issued Generic Letter (GL) 2006-02, Grid Reliability and the Impact on Plant Risk and the Operability of Offsite Power (Agencywide Document Access and Management System (ADAMS) Accession No. ML060180352) to all holders of operating licenses for nuclear power reactors except those who have permanently ceased operation and have certified that fuel has been removed from the reactor vessel.
GL 2006-02 notified licensees of the NRC staffs need for information in four areas as follows:
(1) use of protocols between the nuclear power plant (NPP) and the transmission system operator (TSO), independent system operator (ISO), or reliability coordinator/authority (RC/RA) and the use of transmission load flow analysis tools (analysis tools) by TSOs to assist NPPs in monitoring grid conditions to determine the operability of offsite power systems under plant technical specifications (TSs). (The TSO, ISO, or RA/RC is responsible for preserving the reliability of the local transmission system. In this GL, the term TSO is used to denote these entities);
(2) use of NPP/TSO protocols and analysis tools by TSOs to assist NPPs in monitoring grid conditions for consideration in maintenance risk assessments; (3) offsite power restoration procedures in accordance with Section 2 of NRC Regulatory Guide (RG) 1.155, Station Blackout; and (4) losses of offsite power caused by grid failures at a frequency equal to or greater than once in 20 site-years in accordance with RG 1.155.
Subsequent to the GL, the NRC issued a Request for Additional Information (RAI), (ADAMS Accession No. ML063380308) regarding the resolution of GL 2006-02 to 63 of 65 holders of operating licenses for nuclear power reactors. The RAI requested licensees respond to questions in the following areas:
M. Kansler (1) Switchyard Minimum Voltage; (2) Loss of Real-Time Contingency Analysis (RTCA) Capability; (3) Verification of RTCA Predicted Post-Trip Voltage; (4) Identification of Applicable Single Contingencies; (5) Seasonal Variation in Grid Stress (reliability and Loss-of-offsite power (LOOP) Probability; (6) Interface With Transmission System Operator During Extended Plant Maintenance.
By letters dated April 3, 2006, and January 31, 2007, (ADAMS Accession Nos. ML061010632 and ML070470267) you responded to the information request of GL 2006-02 and the subsequent RAI. Based on the information you provided, the NRC staff has concluded that compliance is being maintained with NRC regulatory requirements governing electric power sources and associated personnel training and considers your response to GL 2006-02 complete.
Please contact me at (301) 415-2901 if you have any questions on this issue.
Sincerely,
/RA/
John P. Boska, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286 cc: See next page
ML061010632 and ML070470267) you responded to the information request of GL 2006-02 and the subsequent RAI. Based on the information you provided, the NRC staff has concluded that compliance is being maintained with NRC regulatory requirements governing electric power sources and associated personnel training and considers your response to GL 2006-02 complete.
Please contact me at (301) 415-2901 if you have any questions on this issue.
Sincerely,
/RA/
John P. Boska, Senior Project Manager Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-247 and 50-286 cc: See next page DISTRIBUTION:
PUBLIC RidsNrrDorlLpl1-1 RidsNrrPMJBoska RidsOGCMailCenter LPL1-1 Reading File RidsNrrLASLittle RidsAcrsAcnwMailCenter ECobey, RI RidsNrrDeEeeb ADAMS ACCESSION NUMBER: ML071410034 OFFICE LPL1-1/PM LPL1-1/LA EEEB/BC LPL1-1/BC NAME JBoska SLittle GWilson MKowal DATE 5/22/07 5/22/07 5/22/07 5/23/07
Indian Point Nuclear Generating Unit Nos. 2 & 3 cc:
Mr. Gary J. Taylor Chief Executive Officer Entergy Operations, Inc.
1340 Echelon Parkway Jackson, MS 39213 Mr. John T. Herron Senior Vice President and Chief Operating Officer Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Fred R. Dacimo Site Vice President Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Mr. Paul Rubin General Manager, Plant Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway P.O. Box 249 Buchanan, NY 10511-0249 Mr. Oscar Limpias Vice President Engineering Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Christopher Schwarz Vice President, Operations Support Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. John F. McCann Director, Licensing Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Ms. Charlene D. Faison Manager, Licensing Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Michael J. Columb Director of Oversight Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. James Comiotes Director, Nuclear Safety Assurance Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Mr. Patric Conroy Manager, Licensing Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P. O. Box 249 Buchanan, NY 10511-0249 Assistant General Counsel Entergy Nuclear Operations, Inc.
440 Hamilton Avenue White Plains, NY 10601 Mr. Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Paul Eddy New York State Department of Public Service 3 Empire State Plaza Albany, NY 12223
Indian Point Nuclear Generating Unit Nos. 2 & 3 cc:
Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Senior Resident Inspectors Office Indian Point 2 U. S. Nuclear Regulatory Commission P.O. Box 59 Buchanan, NY 10511 Senior Resident Inspectors Office Indian Point 3 U. S. Nuclear Regulatory Commission P.O. Box 59 Buchanan, NY 10511 Mr. Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Mayor, Village of Buchanan 236 Tate Avenue Buchanan, NY 10511 Mr. Raymond L. Albanese Four County Coordinator 200 Bradhurst Avenue Unit 4 Westchester County Hawthorne, NY 10532 Mr. William DiProfio PWR SRC Consultant 139 Depot Road East Kingston, NH 03827 Mr. Garry Randolph PWR SRC Consultant 1750 Ben Franklin Drive, 7E Sarasota, FL 34236 Mr. William T. Russell PWR SRC Consultant 400 Plantation Lane Stevensville, MD 21666-3232 Mr. Jim Riccio Greenpeace 702 H Street, NW Suite 300 Washington, DC 20001 Mr. Phillip Musegaas Riverkeeper, Inc.
828 South Broadway Tarrytown, NY 10591 Mr. Mark Jacobs IPSEC 46 Highland Drive Garrison, NY 10524