MONTHYEARML0808604252008-03-26026 March 2008 MR-III-08-0008: Announcement of New Perry Outages and Work Management Director ML0805605022008-02-25025 February 2008 Morning Report MR 3-2008-0006 - Management Changes for Firstenergy Nuclear Operating Company ML0805100062008-02-19019 February 2008 Changes in Perry/ Davis Besse Senior Management ML0802307042008-01-23023 January 2008 Morning Report MR 3-2008-0002: Firstenergy Nuclear Operating Co. (FENOC) Names Paul Harden Vice President of Nuclear Support ML0713803842007-05-18018 May 2007 Changes in Perry Senior Management ML0713803002007-05-17017 May 2007 Morning Report; Management Changes at Beaver Valley Power Station ML0630703062006-11-0303 November 2006 Changes in Perry / Davis-Besse Senior Management ML0529901622005-10-25025 October 2005 Morning Report MR 3-2005-0019 - Firstenergy Nuclear Operating Company (FENOC) Announces Temporary Management Change at Perry ML0517504572005-06-24024 June 2005 Morning Report 3-2005-0013 - Firstenergy Management Changes ML0429903312004-10-25025 October 2004 Firstenergy Announces Management Change ML0420902982004-07-27027 July 2004 Firstenergy Names Executive Vice-President and Chief Operating Officer ML0412110102004-04-30030 April 2004 Firstenergy Announces Management Changes ML0402105182004-01-21021 January 2004 Firstenergy Announces Management Changes 2008-03-26
[Table view] |
Text
PRIORITY ATTENTION REQUIRED MORNING REPORT - REGION III Morning Report Date: MAY 18, 2007 Licensee/Facility: Notification:
FIRSTENERGY NUCLEAR OPERATING CO. MR Number: 3-2007-0008 Perry Date: 05/18/2007 Perry, Ohio RIO Dockets: 050-00440
[1] GE-6
Subject:
Changes in Perry Senior Management Discussion:
Effective May 18, 2007, L. William Pearce, the Perry Site Vice-President, has been named FENOC Vice-President. His replacement as Site Vice President at Perry is Barry S. Allen, who was the previous Director of Site Operations at Perry.
Also effective May 18, 2007, Kurt L. Krueger, the Director of Fleet Operations at Perry, assumed the role of Director of Site Operations. Mr. Krueger has more than 20 years of nuclear experience including Plant Manager at Browns Ferry Units 2 and 3, Operations Manager at Hope Creek, and Site Outage Manager at both Salem and Hope Creek.
Regional Action: Information only; no further action anticipated.
Contact:
Org: Phone No: Email:
FRANKE, MARK E R3 (440) 259-3610 MEF1@nrc.gov