Palisades, Commitment Revision Letter
ML071360054
Person / Time
Site: Palisades Entergy icon.png
Issue date: 05/03/2007
From: Schwarz C J
Entergy Nuclear Operations
To:
Document Control Desk, NRC/NRR/ADRO
References
GL-03-001
Download: ML071360054 (2)


Text

Entergy Nuclear Operations, Inc.Palisades Nuclear Plant Blue Star Memorial Highway Covert, MI 49043 May 3, 2007 10 CFR 50, Appendix A U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Palisades Nuclear Plant Docket 50-255 License No. DPR-20 Commitment Revision Letter

Dear Sir or Madam:

By letter dated November 23, 2004, NMC (the former licensee for Palisades Nuclear Plant (PNP)) provided a revised schedule of commitments in regards to Generic Letter 2003-01, "Control Room Habitability." In the letter, commitment

  1. 4 was made to submit Technical Specification changes 120 days from issuance of Technical Specification Task Force (TSTF) 448, "Control Room Habitability," at PNP. TSTF-448 was issued on January 17, 2007. Therefore, commitment
  1. 4 would have been due May 17, 2007.Subsequent to the issuance of TSTF-448, Entergy Nuclear Operations, Inc. (ENO)determined that additional time was necessary to complete commitment
  1. 4 at PNP.Therefore, ENO is revising this commitment as described below.Summary of Commitments This letter contains no new commitments and one revision to existing commitments.

Commitment made by letter dated November 23, 2004: 4. Development of technical specification changes (and any associated plant modifications) to support requested information GL 2003-01 item 1(c). The schedule for completion was T+120 days (1).(1) Technical Specification submittal dates are contingent on timely approval and issuance of the CLIIP for the TSTF-448 traveler on control room habitability.

Completion dates may change based upon any plant modifications determined to be necessary by the testing.4io2.

Document Control Desk Page 2 Revised commitment:

ENO will submit a license amendment request based on TSTF-448 at PNP by August 31, 2007.-1 i1stopher J.Sahwa Site Vice President Palisades Nuclear Plant CC Administrator, Region Ill, USNRC Project Manager, Palisades, USNRC Resident Inspector, Palisades, USNRC