May 15, 2007 LICENSEE:
Tennessee Valley Authority FACILITY:
Browns Ferry Unit 1
SUBJECT:
MEETING
SUMMARY
FOR MAY 14, 2007-INTERNAL MEETING OF THE BROWNS FERRY UNIT 1 RESTART PANEL AND RECOMMENDATION FOR RESTART-DOCKET NO. 50-259 On May 14, 2007, the Nuclear Regulatory Commission (NRC) held a meeting via teleconference of the NRC Browns Ferry Unit 1 (BF1) Restart Oversight Panel to discuss the Panels recommendation for restart of BF1. The Panel was established in accordance with NRC Inspection Manual Chapter (IMC) 2509, Browns Ferry Unit 1 Restart Project Inspection Program. The purpose of IMC 2509 is to provide the policies and requirements for the restart inspection program, the BF1 Restart Oversight Panel, and the documentation of the major regulatory and license actions associated with the restart. In addition, the IMC provides guidance for assessing the licensees readiness for restart and the return of the unit to the Reactor Oversight Process (ROP). The Restart Panel was established via a charter issued on October 13, 2005. The purpose of this meeting was to review and discuss TVAs Completion of Unit 1 Restart Issues Letter dated May 12, 2007 and provide a recommendation for restart of BF1. All Panel members were present during the meeting and voted unanimously to recommend that the Regional Administrator, in consultation with the Director of NRR and the Executive Director for Operations, authorize the restart of Browns Ferry Unit 1. contains a list of panel members participating in the May 14, 2007, meeting and other NRC attendees. Enclosure 2 contains the Inspection Plan and Schedule Report.
Documents associated with the NRC oversight of the BF1 Recovery can be found on the NRCs website at http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/bf1-recovery.html.
Sincerely,
/RA/
Joseph W. Shea, Director Division of Reactor Safety Docket No.:
50-259 License No.:
Enclosures:
- 1. List of Attendees
- 2. Browns Ferry Unit 1 Inspection Plan and Schedule Full Report Distribution w/encls: (See page 2)
OFFICE RII:DRP RII:DRP RII:DRS SIGNATURE TXN /RA/
MTW /RA/
JWS /RA/
NAME TNazario MWidmann JShea DATE 05/14/2007 05/15/2007 05/15/2007 E-MAIL COPY?
YES NO YES NO YES NO YES NO YES NO YES NO YES NO
TVA 2
May 15, 2007
SUBJECT:
MEETING
SUMMARY
FOR MAY 14, 2007-INTERNAL MEETING OF THE BROWNS FERRY UNIT 1 RESTART PANEL AND RECOMMENDATION FOR RESTART-DOCKET NO. 50-259 Distribution w/encls:
W. Bearden, DRP E. Brown, NRR C. Haney, NRR M. Lesser, DCI T. McGinty, NRR L. Mellen, DRP T. Nazario, DRP L. Raghavan, NRR T. Boyce, NRR T. Ross, DRP J. Shea, DRS C. Stancil, DRP M. Widmann, DRP List of Attendees NRC Browns Ferry Unit 1 Restart Oversight Panel Meeting (May 14, 2007)
Nuclear Regulatory Commission Panel Members Region II J. Shea, Director, Division of Reactor Safety (DRS) - Chairman M. Widmann, Chief, Branch 6, Division of Reactor Projects (DRP) - Member W. Bearden, Senior Resident Inspector Unit 1, Branch 6, DRP - Member (voted via teleconference)
M. Lesser, Chief, Division of Construction Inspection (DCI) - Member L. Mellen, Senior Project Engineer, Branch 6, DRP - Member Headquarters T. McGinty, Deputy Director, Division of Operating Reactor Licensing (DORL), NRR -
Acting Vice-Chairman (voted via teleconference)
L. Raghavan, Chief, Plant Licensing Branch III-1, DORL, NRR - Member (voted via teleconference)
Other Participants T. Ross, Senior Resident Inspector Units 2 and 3, Branch 6, DRP, Region II T. Nazario, Project Engineer, Branch 6, DRP, Region II T. Boyce, Chief, Plant Licensing Branch, DORL, NRR - Member (participated via teleconference)
E. Brown, Project Manager, DORL, NRR (participated via teleconference)