May 29, 2007 Mr. John S. Keenan Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 770000 San Francisco, CA 94177-0001

SUBJECT:

SUPPLEMENT TO THE ENVIRONMENTAL ASSESSMENT AND DRAFT FINDING OF NO SIGNIFICANT IMPACT RELATED TO THE CONSTRUCTION AND OPERATION OF THE DIABLO CANYON INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Dear Mr. Keenan:

The U.S. Nuclear Regulatory Commission (NRC) has completed a supplement to the environmental assessment (EA) and a draft Finding of No Significant Impact (FONSI) for the Diablo Canyon Independent Spent Fuel Storage Installation (ISFSI) (Enclosure 1). NRC issued its EA and FONSI for this action on October 24, 2003, and subsequently issued a license for the Diablo Canyon ISFSI to the Pacific Gas and Electric Company on March 22, 2004. The NRC staff has prepared this supplement to the EA and draft FONSI, which addresses the environmental impacts from potential terrorist acts against the Diablo Canyon ISFSI, at the direction of the Commission, in response to the June 2006 decision by the United States Court of Appeals for the Ninth Circuit.

Enclosed, for your information, is the supplement to the EA and draft FONSI for the Diablo Canyon ISFSI, and the Federal Register notice announcing the availability of the supplement and draft FONSI for the Diablo Canyon ISFSI (Enclosure 2). The notice has been forwarded to the Office of the Federal Register for publication.

If you have any questions about this action, please contact me at (301) 492-3319.

Sincerely,

/RA/

James R. Hall, Senior Project Manager Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards Docket No. 72-26 (50-275, -323)

Enclosures:

1. Supplement to the Environmental Assessment and draft FONSI for the Diablo Canyon ISFSI
2. Notice of Availability of Supplement to the EA and draft FONSI cc: Mailing List

Mr. John S. Keenan May 29, 2007 Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Power Plant P.O. Box 770000 San Francisco, CA 94177-0001

SUBJECT:

SUPPLEMENT TO THE ENVIRONMENTAL ASSESSMENT AND DRAFT FINDING OF NO SIGNIFICANT IMPACT RELATED TO THE CONSTRUCTION AND OPERATION OF THE DIABLO CANYON INDEPENDENT SPENT FUEL STORAGE INSTALLATION

Dear Mr. Keenan:

The U.S. Nuclear Regulatory Commission (NRC) has completed a supplement to the environmental assessment (EA) and a draft Finding of No Significant Impact (FONSI) for the Diablo Canyon Independent Spent Fuel Storage Installation (ISFSI) (Enclosure 1). NRC issued its EA and FONSI for this action on October 24, 2003, and subsequently issued a license for the Diablo Canyon ISFSI to the Pacific Gas and Electric Company on March 22, 2004. The NRC staff has prepared this supplement to the EA and draft FONSI, which addresses the environmental impacts from potential terrorist acts against the Diablo Canyon ISFSI, at the direction of the Commission, in response to the June 2006 decision by the United States Court of Appeals for the Ninth Circuit.

Enclosed, for your information, is the supplement to the EA and draft FONSI for the Diablo Canyon ISFSI, and the Federal Register notice announcing the availability of the supplement and draft FONSI for the Diablo Canyon ISFSI (Enclosure 2). The notice has been forwarded to the Office of the Federal Register for publication.

If you have any questions about this action, please contact me at (301) 492-3319.

Sincerely,

/RA/

James R. Hall, Senior Project Manager Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards Docket No. 72-26 (50-275, -323)

Enclosures:

1. Supplement to the Environmental Assessment and draft FONSI for the Diablo Canyon ISFSI
2. Notice of Availability of Supplement to the EA and draft FONSI cc: Mailing List DISTRIBUTION:

SFPO r/f NMSS r/f ML071270695 OFC:

SFST NMSS SFST NSIR FSME OGC SFST NAME:

JRHall EKraus MDeBose PHolahan LCamper LClark RNelson DATE:

05/18/07 05/17/07 0518/07 05/08/07 05/11/07 05/18/07 05/18/07 C = COVER E = COVER & ENCLOSURE N = NO COPY OFFICIAL RECORD COPY

Diablo Canyon Power Plant, Units 1 and 2 cc:

NRC Resident Inspector Diablo Canyon Nuclear Power Plant c/o U.S. Nuclear Regulatory Commission P.O. Box 369 Avila Beach, CA 93424 Sierra Club San Lucia Chapter ATTN: Andrew Christie P.O. Box 15755 San Luis Obispo, CA 93406 Ms. Nancy Culver San Luis Obispo Mothers for Peace P.O. Box 164.

Pismo Beach, CA 93448 Chairman, San Luis Obispo County Board of Supervisors 1055 Monterey Street, Suite D430 San Luis Obispo, CA 93408 Mr. Truman Burns Mr. Robert Kinosian California Public Utilities Commission 505 Van Ness, Room 4102 San Francisco, CA 94102 Diablo Canyon Independent Safety Committee ATTN: Robert R. Wellington, Esq.

Legal Counsel 857 Cass Street, Suite D Monterey, CA 93940 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower & Pavilion 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 Antonio Fernandez, Esq.

Pacific Gas & Electric Company Post Office Box 7442 San Francisco, CA 94120 City Editor The Tribune 3825 South Higuera Street P.O. Box 112 San Luis Obispo, CA 93406-0112 Director, Radiologic Health Branch State Department of Health Services P.O. Box 997414 (MS 7610)

Sacramento, CA 95899-7414 Mr. James D. Boyd, Commissioner California Energy Commission 1516 Ninth Street (MS 31)

Sacramento, CA 95814 Mr. James R. Becker, Vice President Diablo Canyon Operations and Station Director Diablo Canyon Nuclear Power Plant P.O. Box 56 Avila Beach, CA 93424 Jennifer Tang Field Representative United States Senator Barbara Boxer 1700 Montgomery Street, Suite 240 San Francisco, CA 94111 Diane Curran Harmon, Curran, Spielberg, & Eisenberg, L.L.P 1726 M Street N.W., Suite 600 Washington, D.C. 20036 Notice of Availability of Supplement to the Environmental Assessment and Draft Finding of No Significant Impact for the Diablo Canyon Independent Spent Fuel Storage Installation